Skip to main content

Funds, land acquisition issues rock Modi's ambitious Bharatmala highway plan

By Our Representative
The Narendra Modi government has said that it will be spending Rs 14,000 crore for the Prime Minister’s "ambitious" plan to complete the Bharat Mala project, linking Gujarat in the west with Mizoram in the east, but even before it could kickstart, doubts have been expressed about its costs. Meant to “garland” the territory of India, a recent estimate suggests that it would cost at least 53,000 crore or $9 billion.
A top New York-based media group, in a recent expert analysis has called the project as “simply too ambitious”, pointing out, “Building one kilometre of highway in India, according to industry estimates, requires a minimum of about Rs10 crore ($1.5 million). By that measure, constructing 5,300 kilometres of new highway will cost the government, somewhere around Rs 53,000 crore ($9 billion).”
“Presumably, the government will reach out to the private sector for additional funding, but there might not be enough appetite in India Inc. for such a project”, article says, quoting a top expert with the consultants, Deloitte Touche Tohmatsu, as saying, “Most of the funding will have to come from the government itself,” said Vishwas Udgirkar, a partner at consultancy firm.
“These routes will not see heavy traffic and that would mean that the private sector does not see potential”, the expert has pointed out, adding, “Putting out that sort of money won’t exactly be easy for the government either, which has been struggling to cut expenditure, and restrain the fiscal deficit.”
Pointing out that India’s road sector has itself been in a “complete mess”, the article says, “Until January 2014, as many as 161 projects — worth some Rs 83,000 crore — out of a total of 220 projects awarded under the public-private-partnership (PPP) mode were unfinished.”
And, it says, “between April 2014 and January 2015, the road ministry completed construction of only about 3,038 kilometres of road against a target of 6,300 kilometres.” Yet, it wonders why is the Modi government going ahead with planning to complete “construction of 30 kilometres of road per day for the next two years.”
Quoting yet another consultant, Vinayak Chatterjee, chairman at Feedback Infra, the article says, “There is a huge agenda already pending before the road sector both at the central and state level, including challenging areas such as the borders. The announcement of such a project could improve greater confidence if accompanied by scientific traffic flow estimates on the proposed alignment.”
Things are going to be easy another count, the article says: “The Government of India will have to acquire an enormous ribbon of land that could stretch across as many as 13 states. After beginning in Gujarat, the Bharat Mala project will cut through Rajasthan and Punjab.”
Then, it says, the highway will “cover all the Himalayan states—Jammu and Kashmir, Himachal Pradesh, Uttarakhand—before moving to Uttar Pradesh and Bihar”, and “finally touch northeastern states of Sikkim, Assam, Arunachal Pradesh, Manipur and Mizoram.”
The article quotes state roads secretary Vijay Chhibber as saying, “Our idea is to plan for a structured programme for building roads along our borders, especially the northern borders.” But it comments, “Acquiring land across such an expansive stretch won’t be easy. For India’s National Highway Authority, the lead government organisation for road construction in India, the inability to acquire land has been a massive problem.”
“During the review meetings, it is observed that the land acquisition is one of the reasons for delay of completion of projects”, the article further quotes Pon Radhakrishnan, minister of state for roads, as saying last month, adding, “Over 600 road projects in India are currently delayed due to land acquisition problems.”

Comments

TRENDING

132 Gujarat citizens, including IIM-A faculty, others declare solidarity with Kashmiris

Counterview Desk
A week after it was floated, 132 activists, academics, students, artists and other concerned citizens of Gujarat, backed by 118 living in different parts of India and the world, have signed a "solidarity letter" supporting the people of Jammu and Kashmir (J&K), who, it claims, have been silenced and held captive in their own land. The signatories include faculty members and scholars of the prestigious Indian Institute of Management-Ahmedabad (IIM-A).

Bharat Ratna nominee ‘joined hands’ with British masters to 'crush' Quit India

By Shamsul Islam*
The Quit India Movement (QIM), also known as ‘August Kranti' (August Revolution), was a nation-wide Civil Disobedience Movement for which a call was given on August 7, 1942 by the Bombay session of the All-India Congress Committee. It was to begin on August 9 as per Gandhi's call to 'Do or Die' in his Quit India speech delivered in Bombay at the Gowalia Tank Maidan on August 8. Since then August 9 is celebrated as August Kranti Divas.

Gujarat's incomplete canals: Narmada dam filled up, yet benefits 'won't reach' farmers

By Our Representative
Even as the Gujarat government is making all out efforts to fill up the Sardar Sarovar dam on Narmada river up to the full reservoir level (FRL), a senior farmer rights leader has said the huge reservoir, as of today, remains a “mirage for the farmers of Gujarat”.
In a statement, Sagar Rabari of the Khedut Ekta Manch (KEM), has said that though the dam’s reservoir is being filled up, the canal network remains complete. Quoting latest government figures, he says, meanwhile, the command area of the dam has been reduced from 18,45,000 hectares (ha) to 17,92,000 ha.
“According to the website of the Sardar Sarovar Narmada Nigam Ltd, which was last updated on Friday, while the main canal, of 458 km long, has been completed, 144 km of ranch canals out of the proposed length of 2731 km remain incomplete.
Then, as against the targeted 4,569 km distributaries, 4,347 km have been constructed, suggesting work for 222 km is still pending. And of the 15,670 km of minor canal…

Ceramic worker dies: 20,000 workers in Thangadh, Gujarat, 'risk' deadly silicosis

By Our Representative
Even as the country was busy preparing for the Janmashtami festival on Saturday, Hareshbhai, a 46-year-old ceramic worker from suffering from the fatal lung disease silicosis, passed away. He worked in a ceramic unit in Thangadh in Surendranagar district of Gujarat from 2000 to 2016.
Hareshbhai was diagnosed with the disease by the GCS Medical College, Naroda Road, Ahmedabad in 2014. He was found to be suffering from progressive massive fibrosis. He is left behind by his wife Rekha sister and two sons Deepak (18) and Umesh (12),
The death of Hareshbhai, says Jagdish Patel of the health rights group Peoples Training and Research Centre (PTRC), suggests that silicosis, an occupational disease, can be prevented but not cured, and the Factory Act has sufficient provisions to prevent this.
According to Patel, the pottery industry in the industrial town of Thangadh has evolved for a long time and locals as well as migrant workers are employed here. There are abou…

Cess for Gujarat construction workers: Spending less than 10%; no 'direct help' to beneficiaries

By Our Representative
While the Gujarat government’s Building and Other Construction Workers Welfare Board, set up in 2004, as of March 31, 2019, has collected a total cess of Rs 2,097.62 crore from the the builders, it has spent less than 10% -- Rs 197.17 crore. And, as on May 31, 2019, the total cess collection has reached Rs 2,583.16 crore, said a statement issued by Bandhkam Majur Sagathan general secretary Vipul Pandya.
Pointing out that just about 6.5 lakh out of 20 lakh workers have been registered under the board, Pandya said, vis-à-vis other states, Gujarat ranks No 13th in the amount spent on the welfare of the construction workers, while 11th in the amount collected.
And while the builders are obliged to pay just about 1% of the total cost of their project, the calculation of the cess is flawed: It is Rs 3,000 per square yard; accordingly, Rs 30 per square yard is collected. “Had the cess been collected on the real construction cost, it would have been at least Rs 7,000 cr…