Bargi Pumped Storage Project moves forward, local groups protest lack of consultation

By A Representative 
The Expert Appraisal Committee has cleared the application for issuing Terms of Reference (ToR) to conduct an Environmental Impact Assessment, prepare an Environmental Management Plan, and hold a public hearing for the proposed 1,000 MW Bargi Open Pumped Storage Hydropower Project. 
The ToR will be sent separately by the Ministry of Environment to M/s Serenitica. The company had applied to the Ministry of Environment, Forest and Climate Change for environmental clearance for the project, which falls under Category A, Item 1(c) “River Valley Projects” of the Environmental Impact Assessment Notification, 2006, and therefore requires appraisal at the central level.
The proposal involves using the existing Bargi reservoir for the open-loop pumped storage system and constructing a new upper reservoir with a total storage capacity of 24.44 MCM and a maximum dam height of 25 metres. 
The project requires about 381.50 hectares of land, including 110.50 hectares of private land and 271 hectares of forest land. Diversion of forest land for non-forest use will be required, but no application for forest clearance has yet been submitted.
According to the application, the state Renewable Energy Department in Bhopal issued a preliminary allocation letter on August 11, 2025, allowing development of the 1,000 MW project. The estimated cost of the project is ₹4,689.89 crore. It proposes four units of 200 MW each and two units of 100 MW each, expected to generate 2,078.50 million units of electricity annually. 
People from five villages are likely to be displaced. The project is proposed in the villages of Pindrai Mal, Salaiya Mal, Jamthar, Khapa, Niwari and Pondi in Narayanganj and Bijadandi blocks of Mandla district.
Raj Kumar Sinha of the Bargi Dam Displaced and Affected Association questioned why the project process is advancing in Fifth Schedule areas without first obtaining consent from the concerned gram sabhas. 
He said the Renewable Energy Department has already issued an allocation letter to the company, while the Narmada Valley Development Authority is reluctant to provide irrigation water from the Bargi reservoir to local farmers but moves swiftly to approve pumped storage projects. 
The association has demanded that the government address the long-pending demand for lift irrigation from the Bargi reservoir through dialogue with local farmers before granting approval to the pumped storage project.

Comments

TRENDING

Sardar made up his mind on Pakistan in Dec 1946 "before" Mountbatten's Partition Plan

By Hari Desai* One has to be extra cautious while dealing with the history of towering personalities of the Indian freedom struggle, especially that of Sardar Vallabhbhai Patel (October 31, 1875 - December 15, 1950). Present-day politicians prefer to "pronounce” on his life and quote him according to their convenience like a blind person describing an elephant.

To Sonam Wangchuk: 'Will undertake 70 hour solidarity fast in Gujarat'

By Martin Macwan *  Dear Colleague Sonam Wangchuk, I have never met you personally. I wrote a short article at the time of your arrest. Your work correctly introduces you. There is truth in your words. You have embarked on a fast, following the footsteps of Gandhiji. Your intention is to make people think. Your demand is reasonable; I believe that the resignation of a single education minister will not improve the state of education in India. However, the question you have raised is extremely important for the future generation of the marginalized. Education is the key to power, development, and progress, which empowers a citizen.

Remembering Rampur ka Tiraha: State violence and the birth of Uttarakhand’s struggle

By Vidya Bhushan Rawat*  In the turbulent political landscape of the early 1990s, India witnessed events that reshaped its social and regional equations. After the Babri Masjid demolition in 1992, Uttar Pradesh politics shifted dramatically, bringing the Samajwadi Party–Bahujan Samaj Party coalition to power in 1993 under Mulayam Singh Yadav. But the partnership was uneasy. Mulayam was never entirely comfortable playing the “Mandal card.” While Kanshi Ram and the BSP had consistently demanded the implementation of the Mandal Commission recommendations, Mulayam hesitated, wary of how the move might play out.