A group of 69 former civil servants has urged the Centre and the Arunachal Pradesh government to abandon the 1,750 MW Demwe Lower Hydroelectric Project on the Lohit River, citing ecological risk, local protests and what it calls a compromised wildlife clearance.
In an open letter, the Constitutional Conduct Group wrote to the Union Environment Minister, the Member Secretary of the Standing Committee of the National Board for Wildlife (SC-NBWL) and the Arunachal Chief Minister. The group says it has no party affiliation.
Ecological Concerns
The letter says the project would divert 1,416 hectares of forest land, submerge about 1,590 hectares and fell around 43,000 trees. The dam site and submergence zone lie within 50 metres of the Kamlang Tiger Reserve and extend into its Eco-Sensitive Zone, the signatories say.
As a peaking power plant, the dam would hold back water for about 20 hours a day and then release surges of up to 1,729 cubic metres per second. The signatories warn this would cause downstream bank erosion and harm aquatic life. They flag threats to the critically endangered White-Bellied Heron (about 60 mature individuals worldwide), and to the Bengal Florican and Gangetic Dolphin in Dibru-Saikhowa National Park. Baseline surveys recorded 61 mammal and 105 bird species in the area, including the Mishmi Takin, Red Panda and Eastern Hoolock Gibbon. The group adds that the dam would fragment tiger habitat across Kamlang, Namdapha and the proposed Dibang Tiger Reserve.
A Contested Clearance
The letter traces the project's approvals back to 2011, when non-official expert members of the SC-NBWL reportedly rejected it after a site visit report by Bombay Natural History Society director Asad Rahmani condemned it. The Environment Minister then granted wildlife clearance, overriding that opinion.
In October 2017, the National Green Tribunal suspended the approvals, holding that the minister had acted unlawfully, and ordered a fresh review, including of cumulative downstream impacts. The signatories say a reconstituted committee with only two independent members cleared the project again in 2018 without the multi-season assessment the NGT required. The project then stalled as its developer, Athena, ran into financial trouble.
After Greenko acquired the project in 2026, the SC-NBWL, reconstituted in March with again only two independent experts, took it up in July. The letter alleges the panel considered only the change of developer, relied on the outdated 2018 rapid study, and ignored the Kamlang ESZ, downstream damage and community opposition. It also notes that one of the two independent members is a former forest officer employed by an organisation headed by the Environment Minister.
Local Resistance
The letter says Mishmi and other tribal groups, student unions and environmentalists have resisted the project since its 2010 environmental clearance, partly to protect the sacred Parashuram Kund. It reports fresh uprisings in 2026 against Demwe and other proposed Arunachal projects, including Siang, Menga, Naying and Dibang. It also criticises the state government's decision not to implement the Forest Rights Act, 2006.
Strategic Argument Disputed
The signatories reject the view that the dam would strengthen India's water rights against Chinese upstream damming. Without a bilateral treaty, they argue, downstream infrastructure cannot stop upstream diversion. They add that 70–80% of the Brahmaputra system's volume in India originates within Arunachal Pradesh and Assam.
Call To Reconstitute Panel
The group also says the SC-NBWL has been turned from a safeguard into an "administrative clearing house," and asks that it be reconstituted with a majority of respected non-government experts.
Signatories include former Environment Secretary Meena Gupta, former Foreign Secretary K. Raghunath, former Delhi Lieutenant Governor Najeeb Jung, former Health Secretary K. Sujatha Rao, former Chief Economic Adviser Nitin Desai, and former forest officers Prakriti Srivastava and Avay Shukla.
%20-%202026-11-23T232611.852.jpeg)