Skip to main content

Madhya Pradesh yet to pay up over Rs 3,100 crore as share of Narmada Project: Gujarat government to NCA

By Rajiv Shah
In a controversial statement, the Gujarat government’s powerful arm implementing the Sardar Sarovar Project (SSP), Sardar Sarovar Narmada Nigam Ltd (SSNNL), has said that Madhya Pradesh has yet to pay up a whopping Rs 3,159.88 crore against the nieghbouring state’s share of expenditure in the SSP, followed by Maharashtra’s Rs 1,437.50 crore and Rajasthan’s Rs 471.70 crore. The statement is an “update” as on May 12, 2013 of the “Status Report on SSP”, sent by the SSNNL to the Narmada Control Authority (NCA) – the Government of India-appointed inter-state authority to give a final nod to the project’s various components – in December 2012.
The total amount the three states must pay up, according to the SSNNL, comes to Rs 5,059.08 crore. A further breakup, worked out by the SSNNL, suggests that out of Rs 3,159.88 crore that Madhya Pradesh must pay up, nearly two-thirds, or Rs 1,826.80 crore, is as interest, piling up for years for its failure to make regular payment against the project cost. As for Maharashtra, it must pay up Rs 865.32 crore as interest, followed by Rajasthan’s Rs 471.10 crore.
An inter-state project, while Gujarat would get the lion’s share of irrigation water from the SSP once the project’s various components are completed, including the canal network and the dam height (which are pending for long), Madhya Pradesh and Maharashtra are already getting the benefit of 1,450 MW of power, being produced from the river-bed and canal-based power plants. The power plants are operational to full capacity, with Madhya Pradesh (the biggest defaulter in sharing expenditure) getting 57 per cent of power, followed by Maharashtra (27 per cent), and Gujarat (16 per cent).
The total expenditure that has been incurred on the SSP comes to 38,536.14 crore, the statement says, adding, of this, Gujarat should have actually spend Rs 29,614.16 crore, Madhya Pradesh Rs 5,286.92 crore, Maharashra 2,504.37 crore, and Rajasthan Rs 1,118.34 crore. However, interestingly, Gujarat would have spent a much higher amount, as the neighbouring states have yet to pay up most of the amount. And, not only have the three neighbouring states refused to pay the full amount to Gujarat, the SSNNL statement goes on to show that they have put most of the amount they must pay up in the “disputed” category.
Thus, Madhya Pradesh has told Gujarat that it would not pay up the “disputed” amount of Rs 2,483.85 crore, including the interest and Rs 644.73 against rehabilitating the oustees; Maharashtra Rs 1,176.55 crore, which include the interest and Rs 305.39 against rehabilitating the oustees; and Rajasthan Rs 440.30 crore – most of which is interest. According to the three states “the undisputed” share they are ready to pay are – Madhya Pradesh Rs 676.03 crore, Maharashtra Rs 290.95 crore, and Rajasthan Rs 30.80 crore.
Pointing out that all these figures are of the 2008-09 price level, the statement does not say how much more the SSNNL would have to spend now, though it does give details of the work yet to be done. Thus, most interestingly, out of 17.92 lakh hectares (ha) area which Gujarat must develop for irrigation with Narmada waters, the state has “created” an irrigation potential of 5.59 lakh ha by developing the canal network, of which only one-third is actually being irrigated. On the other hand, Rajasthan’s progress is much better – it has completed 2.05 lakh ha, out of 2.46 lakh ha it has decided to.
Incomplete canal network: The statement gives important details of the work which remains to be done over and above raising the dam height from the current 121.92 metres to 138.64 metres, which is dependent on rehabilitation and resettlement of the Narmada dam oustees. While the main canal, which goes right into Rajasthan, has been completed, out of 17.72 lakh ha to be irrigated from the Narmada waters in Gujarat, the work for even Phase-I (up to 144 km from the Narmada dam) has not been completed – here, the distribution network, including sub-minors, remain incomplete in about 18-20 per cent areas. Thus, for sub-minors, 82 per cent of mudwork is over, 78 per cent of excavation is over, and 83 per cent of lining work is over.
Further on, in Phase-II, Part A (from 144 km to 263 km), branch canals remain to be completed on the Saurashtra side in about 10 per cent of area, and distribution network in 85 per cent of area. Further, while mudwork for the distribution system in this phase is over for 40 per cent of the area, followed by excavation (23 per cent area) and lining work (14 per cent), the work for sub-minors –the field channels that take water up to the farms – has not even begun till now.
Coming to Phase-II (B), from 263 km to 357 km, while the branch canals are completed in 90 per cent of the area, the distribution network is yet to be completed in about 40 per cent of area – only 56 per cent of mudwork, 23 per cent of excavation and 14 per cent of lining is over. As for sub-minors, like in the previous phase, here, too, the work has not begun. In phase-II (C), from 357 km to 458 km, while the main canal is “almost complete”, the branch canals remain to be completed in 80 per cent of cases, with mudwork completed in 42 per cent of cases, excavation in 83 per cent of cases, and lining in 20 per cent of cases.
The situation with regard to the Kutch branch canal in this phase is equally bad – mudwork is over in 67 per cent area, excavation in 74 per cent area, and lining in 40 per cent. As for the distribution work, 68 per cent of mudwork, 52 per cent of excavation and 6 per cent of lining work is over. The work for sub-minors, like in all the other Phase-II sections, has not even begun.

Comments

TRENDING

A comrade in culture and controversy: Yao Wenyuan’s revolutionary legacy

By Harsh Thakor*  This year marks two important anniversaries in Chinese revolutionary history—the 20th death anniversary of Yao Wenyuan, and the 50th anniversary of his seminal essay "On the Social Basis of the Lin Biao Anti-Party Clique". These milestones invite reflection on the man whose pen ignited the first sparks of the Great Proletarian Cultural Revolution and whose sharp ideological interventions left an indelible imprint on the political and cultural landscape of socialist China.

1857 War of Independence... when Hindu-Muslim separatism, hatred wasn't an issue

"The Sepoy Revolt at Meerut", Illustrated London News, 1857  By Shamsul Islam* Large sections of Hindus, Muslims and Sikhs unitedly challenged the greatest imperialist power, Britain, during India’s First War of Independence which began on May 10, 1857; the day being Sunday. This extraordinary unity, naturally, unnerved the firangees and made them realize that if their rule was to continue in India, it could happen only when Hindus and Muslims, the largest two religious communities were divided on communal lines.

N-power plant at Mithi Virdi: CRZ nod is arbitrary, without jurisdiction

By Krishnakant* A case-appeal has been filed against the order of the Ministry of Environment, Forest and Climate Change (MoEF&CC) and others granting CRZ clearance for establishment of intake and outfall facility for proposed 6000 MWe Nuclear Power Plant at Mithi Virdi, District Bhavnagar, Gujarat by Nuclear Power Corporation of India Limited (NPCIL) vide order in F 11-23 /2014-IA- III dated March 3, 2015. The case-appeal in the National Green Tribunal at Western Bench at Pune is filed by Shaktisinh Gohil, Sarpanch of Jasapara; Hajabhai Dihora of Mithi Virdi; Jagrutiben Gohil of Jasapara; Krishnakant and Rohit Prajapati activist of the Paryavaran Suraksha Samiti. The National Green Tribunal (NGT) has issued a notice to the MoEF&CC, Gujarat Pollution Control Board, Gujarat Coastal Zone Management Authority, Atomic Energy Regulatory Board and Nuclear Power Corporation of India Limited (NPCIL) and case is kept for hearing on August 20, 2015. Appeal No. 23 of 2015 (WZ) is filed, a...

Spirit of leadership vs bondage: Of empowered chairman of 100-acre social forestry coop

By Gagan Sethi*  This is about Khoda Sava, a young Dalit belonging to the Vankar sub-caste, who worked as a bonded labourer in a village near Vadgam in Banskantha district of North Gujarat. The year was 1982. Khoda had taken a loan of Rs 7,000 from the village sarpanch, a powerful landlord doing money-lending as his side business. Khoda, who had taken the loan for marriage, was landless. Normally, villagers would mortgage their land if they took loan from the sarpanch. But Khoda had no land. He had no option but to enter into a bondage agreement with the sarpanch in order to repay the loan. Working in bondage on the sarpanch’s field meant that he would be paid Rs 1,200 per annum, from which his loan amount with interest would be deducted. He was also obliged not to leave the sarpanch’s field and work as daily wager somewhere else. At the same time, Khoda was offered meal once a day, and his wife job as agricultural worker on a “priority basis”. That year, I was working as secretary...

Two more "aadhaar-linked" Jharkhand deaths: 17 die of starvation since Sept 2017

Kaleshwar's sons Santosh and Mantosh Counterview Desk A fact-finding team of the Right to Feed Campaign, pointing towards the death of two more persons due to starvation in Jharkhand, has said that this has happened because of the absence of aadhaar, leading to “persistent lack of food at home and unavailability of any means of earning.” It has disputed the state government claims that these deaths are due to reasons other than starvation, adding, the authorities have “done nothing” to reduce the alarming state of food insecurity in the state.

Epic war against caste system is constitutional responsibility of elected government

Edited by well-known Gujarat Dalit rights leader Martin Macwan, the book, “Bhed-Bharat: An Account of Injustice and Atrocities on Dalits and Adivasis (2014-18)” (available in English and Gujarati*) is a selection of news articles on Dalits and Adivasis (2014-2018) published by Dalit Shakti Prakashan, Ahmedabad. Preface to the book, in which Macwan seeks to answer key questions on why the book is needed today: *** The thought of compiling a book on atrocities on Dalits and thus present an overall Indian picture had occurred to me a long time ago. Absence of such a comprehensive picture is a major reason for a weak social and political consciousness among Dalits as well as non-Dalits. But gradually the idea took a different form. I found that lay readers don’t understand numbers and don’t like to read well-researched articles. The best way to reach out to them was storytelling. As I started writing in Gujarati and sharing the idea of the book with my friends, it occurred to me that while...

Proposed Modi yatra from Jharkhand an 'insult' of Adivasi hero Birsa Munda: JMM

Counterview Desk  The civil rights network, Jharkhand Janadhikar Mahasabha (JMM), which claims to have 30 grassroots groups under its wings, has decided to launch Save Democracy campaign to oppose Prime Minister Narendra Modi’s Vikasit Bharat Sankalp Yatra to be launched on November 15 from the village of legendary 19th century tribal independence leader Birsa Munda from Ulihatu (Khunti district).

Fate of Yamuna floodplain still hangs in "balance" despite National Green Tribunal rap on Sri Sri event

By Ashok Shrimali* While the National Green Tribunal (NGT) on Thursday reportedly pulled up the Delhi Development Authority (DDA) for granting permission to hold spiritual guru Sri Sri Ravi Shankar's World Culture Festival on the banks of Yamuna, the chief petitioners against the high-profile event Yamuna Jiye Abhiyan has declared, the “fate of the floodplain still hangs in balance.”

Hyderabad Cong leader hospitalized after alleged AIMIM-linked mob attack; party demands justice

By A Representative   A group of Congress leaders and activists have written to the Hyderabad Commissioner of Police, urging immediate action over what they describe as a “mob lynching murderous attack” on party functionary Mohammed Hamed at the Congress Party office in New Kishan Nagar, Asifnagar, on July 21.