Skip to main content

People of Odisha have not yet given up struggle against Posco, which has "acquired" 2,700 acres for steel project

By Kanchi Kohli*
The battlelines have been drawn like never before. While the Odisha state government and Posco India Ltd have made categorical statements that they have acquired 2,700 acres for an eight million tonnes steel project, the agitations in Gobindpur and Dhinkia continue. Each day there are incidents of a tussle when efforts are made to forcibly cut betel vines and dig trenches to construct a boundary wall for the Posco project. There are emphatic statements that land acquisition has been completed, all permissions are in place and construction work will begin soon.
From the other side, there are determined statements that indicate that people of the area have not given up despite an eight-year struggle. They are ready to return to their homes and their betel vines that have been destroyed in the tussle for power. Far away from the site of the contest, legal battles and the opinions of experts continue to ascertain the future of the people of Jagatsinghpur where an investment of `52,000 crore is directed at the construction of a captive steel plant, power plant and port. Many livelihoods dependant on betel vine cultivation, agriculture and fishing in the villages of Dhinkia, Gobindapur, Nuagaon, Polanga, Bhuyanpai, Bayanal, Kandah, Noliasahi and Jatadhar will be affected by the project.
When Posco signed its MoU with the Odisha government way back in 2005, their intention was to set up a 12 MTPA steel plant along with several other components of the project. The first public hearing for the project in April 2007 was for the construction of a 4 MTPA steel plant, a 400 MW power plant along with a captive port. Even as permissions for the above were granted in July and May 2007 respectively, Posco continued to acquire land keeping in mind its final steel plant of 12 MTPA. Posco’s website says they will complete the project in three phases, constructing the steel plant to accommodate 4 MTPA capacity each time, with the first phase to be completed by 2016-17.
With various legal issues and battles on the ground, alongside assessments commissioned by the Union Ministry of Environment and Forests (MoEF), Posco first received its environment clearance in 2007 which was reviewed through the recommendations of the MoEF constituted Meena Gupta Committee’s reports in 2010. A final environment clearance (issued under the Environment Impact Assessment notification, 2006) was granted on January 31, 2011. For all practical purposes this was to be considered the final clearance as project activity had not begun on the proposed site. In May and June 2012, the environment clearances granted to Posco in 2007 also expired given that they were to be valid only for a period of five years.
Meanwhile both the 2011 and 2007 approvals were challenged before the National Green Tribunal (NGT). The tribunal on 30 March 2012 issued a strong judgment upholding that there was indeed a lacuna in the manner in which the approval for Posco had been granted. The tribunal said that it was necessary to ensure optimum use of land (both forest and non-forest) being acquired for Posco keeping in mind a 4 MTPA plant. The company had carried out an Environment Impact Assessment (EIA) as well as the public hearing process on the basis of this capacity. Based on this and several other contentions a fresh review of the environment clearance was to take place.
In mid 2012, two parallel processes began in the MoEF. The first was the process of revalidation of the 2007 clearances and the second the setting up of an expert committee under K.Roy Paul, Former Secretary to the Government of India. The process of revalidation and the review by the Roy Paul committee took place simultaneously till all the documents were placed in a meeting of the MoEF Expert Appraisal Committee (EAC) for industrial projects in March 2013. In this meeting Posco contented that while they are currently pursuing the plan for a 4 MTPA plant, their final intention is to set up a 12 MTPA plant which has not changed. At this stage the EAC sought a revised layout design for not just a 4 MTPA plant but also an 8 MTPA one. 
Many of the contentions made in the Roy Paul Committee report which was submitted to the MoEF in October 2012 did not seem to have been discussed by the EAC, if one is to go by the official minutes of the meeting. In fact the Roy Paul committee had recommended that a range of studies should be carried out by the project proponent related to shoreline changes, source sustainability study of water requirement, marine environmental conservation plan, the impact on the local fishing community etc, which don’t find mention as well.
One of the foremost observations of the Roy Paul committee was that Posco should state unambiguously whether the reduced project area based on land optimisation for 4 MTPA will be able to accommodate all its future expansion plans. The report observes that based on information provided, the project area had been reduced to 2,700 acres by leaving out most of the private land in Govindpur and Dhinkia villages and the portion of forest land where betel vines were being grown by people of these villages. This implies that the project would be constructed around these villages implying these lands are not to be acquired only in the current proposal.
In the subsequent meeting of the EAC of 16-17th May this year, the expert committee recommended the revalidation of the approval for an 8 MTPA plant. What is ironic is that the original application as well as the EIA report of 2007 is all based on the impact assessment of a plant of 4 MTPA capacity. Although the final approval letter from the MoEF is yet to be issued, it is questionable how an approval for 8 MTPA has been recommended by the EAC.
Posco’s legal tussles are also back in the NGT in another form. An application has been filed highlighting that Posco has been carrying out felling of trees on 1253.225 ha of forest land without the final forest clearance order being issued by the Odisha state government. This application builds on the reiteration and interpretation of both the Forest Conservation Act (FCA) 1980, by the NGT Act which states that the permission for diverting forest land for non-forest purposes under Section 2 of the FCA by the MoEF needs to be followed by an order of the state government as well. No construction work on the project can begin till the order of the state government has been issued. In Posco’s case this has not happened.
As per a Right to Information (RTI) response received on March 13 this year to an application filed by Chandranath Dani, the Odisha state government has confirmed that no such order has been issued. Based on this and additional contentions the NGT on May 28 stayed the felling of trees by the company. On July 11 this order was allowed to continue till the next hearing of the case on  August 12.
There are other legal procedures that are likely to crop up for Posco. In the 16th May meeting of the EAC (Industry) a recommendation has been made that Posco should obtain an additional CRZ clearance for discharge of wastewater into the sea through a pipeline. This process is yet to begin.
For the people of India the eight-year-old tryst with Posco has many lessons. There are international and national reports highlighting a list of human rights and regulatory violations that the history of the project is marred with. In Jagatsinghpur, each day is a new day for villagers who don’t know what form of aggression will come their way and how they will be able to withstand it. The fact is that the people of the area have not given up. What is clear for now is that Posco is certainly not a closed chapter.
---
* Kanchi Kohli is a well-known researcher and publicist on environment governance and biodiversity conservation related issues. Kohli's article, also published in  http://www.civilsocietyonline.com, has been shared with www.counterview.net

Comments

TRENDING

'Enough evidence': Covid vaccines impacted women's reproductive health

By Deepika*  In 2024, the news outlets have suddenly started reporting about covid vaccine side effects in a very extensive manner. Sadly, the damage is already done.

A Hindu alternative to Valentine's Day? 'Shiv-Parvati was first love marriage in Universe'

By Rajiv Shah*   The other day, I was searching on Google a quote on Maha Shivratri which I wanted to send to someone, a confirmed Shiv Bhakt, quite close to me -- with an underlying message to act positively instead of being negative. On top of the search, I chanced upon an article in, imagine!, a Nashik Corporation site which offered me something very unusual. 

Dadi, poti discuss 'injustice' under 10 yr Modi rule: Video campaign goes viral

By Our Representative  Watan Ki Raah Mein, a civil society campaign of the Samvidhan Bachao Nagrik Abhiyan, has released a short video conversation on social media of an exchange of letters between a dadi and her poti discussing poverty, unemployment, corruption and women’s safety. The letters also raise the question of  suppression of our fundamental rights of speech, expression and justice. 

US 'frustrated' with India’s discomfort: Maritime exercise in South China Sea

By Vijay Prashad*  In early April 2024, the navies of four countries -- Australia, Japan, the Philippines, and the United States -- held a maritime exercise in the South China Sea. Australia’s Warramunga, Japan’s Akebono, the Philippines’ Antonio Luna, and the United States’ Mobile worked together in these waters to strengthen their joint abilities and -- as they said in a joint statement  -- to “uphold the right to freedom of navigation and overflight and respect for maritime rights under international law.” 

'Uncertainty in Iran': Raisi brokered crucial Chabahar Port deal with India

By Pranjal Pandey*  Ebrahim Raisi, the Iranian President, and the country’s foreign minister were tragically found deceased on May 20, 2024, shortly after their helicopter crashed in foggy conditions. In response, Supreme Leader Ayatollah Ali Khamenei swiftly appointed a relatively unknown vice president as the interim leader.

Informal, outdoor workers 'excluded': Govt of India's excessive heat policies

Counterview Desk  Top civil rights network, National Alliance of People's Movements (NAPM), has demanded urgent government action to protect millions of outdoor workers from extreme heat and heatwaves, insisting declaration of heatwaves as climatic disaster.

Desist from academic censorship, stop threatening scholars: Letter to ICMR

Counterview Desk  In a letter to the Indian Council of Medical Research (ICMR) director, the Universal Health Organisation (UHO) which consists of prominent health experts, has insisted that the Government of India’s top medical research agency should lead high quality research on vaccine safety and “desist from academic censorship”.

WHO move can 'enable' India to detain citizens, restrict freedom, control media

Counterview Desk  In an an open letter to Prime Minister Narendra Modi, with copies to concerned Cabinet ministers, bureaucrats and MPs,  health rights network  People’s Alliance for Public Health (PAPH alias JanSwasthya Morcha), has urged that India should not be a signatory to the World Health Organization ( WHO) Pandemic Agreement and Amendments to the  International Health Regulations (IHR) 2005  to be adopted at the 77th World Health Assembly in Geneva from 27th May to 1st June, 2024.

Vaccine nationalism? Covaxin isn't safe either, perhaps it's worse: Experts

By Rajiv Shah  I was a little awestruck: The news had already spread that Astrazeneca – whose Indian variant Covishield was delivered to nearly 80% of Indian vaccine recipients during the Covid-19 era – has been withdrawn by the manufacturers following the admission by its UK pharma giant that its Covid-19 vector-based vaccine in “rare” instances cause TTS, or “thrombocytopenia thrombosis syndrome”, which lead to the blood to clump and form clots. The vaccine reportedly led to at least 81 deaths in the UK.