Dam shortcut results in hydropower project hit by massive landslide in North-East

Counterview Desk 
The advocacy group South Asia Network on Dams, Rivers and People (SANDRP), commenting on a massive landslide which hit the Subajsiri Hydropower project on the border of Assam-Arunachal Pradesh, has said that this is in continuation of India facing “multiple dam disasters”. One of the biggest in recent times washing away of the massive 1200 MW Teesta 3 dams in Sikkim.
It underlined, “It is high time that the authorities wake up and do no allow hydropower developers allow to adopt short cuts, the way Teesta 3 dam developers did and now NHPC seems to be doing in case of Lower Subansiri HEP.”

Text:

Once again, after several such incidents in the past, the controversial 2000 MW Lower Subansiri Hydropower project on Assam Arunachal Border was hit by a massive landslide at around 11.30 am on Oct 27 2023. The landslide damaged the project, further delaying the commissioning of the first unit, increasing the cost and time over runs of the expensive, much delayed project. Following the landslide, the only functioning diversion tunnel no 1 of the project, about 200 m upstream from the dam was blocked.
The river water, about 997 cumecs (cubic meters per second) suddenly started flowing towards the dam, where the spillway gates were still under installation, yet to be tested. The water could overflow from the under construction spillway gates once the reservoir reached 145 meters level (above Mean Sea Level).
The massive, majestic Subansiri river was completely without any flow till the river water started flowing through the spillway gates about twelve hours later. (Feature photo above shows the snapshot when landslide started and in the foreground, water is seen rushing towards the dam).
Diversion Tunnels (DT) are constructed to take river water from the upstream of the coffer (temporary) dam to downstream of the dam site so that dam site can remain dry for the work to go on. For Lower Subansiri HEP, five such diversion tunnels each of diameter 9.5 meters have been constructed on the left bank at about 100 m above mean sea level.
A senior official of NHPC said: “The other four numbers of diversion tunnels had already been blocked earlier”, partly due to landslide, the official did not say. Even this last functioning DT was also hit by a landslide in April 2023 and also October 2022.

NHPC needs to follow CEA directions

An “Indian Express” report earlier mentions that the “Central Electricity Authority (CEA) in April 2022 had advised the NHPC to engage a specialized agency to examine the strength of the project’s powerhouse retention wall and also assess the impact of diversion tunnels on the site’s slope stability before the onset of monsoon”.
However, the studies were not carried out. The report also lists the landslide incidents at project site since beginning of the project work in 2005. This negligence by NHPC in not taking measures suggested by CEA and not taking necessary follow up action has once again led to the fresh damage to the project and delayed its commissioning.
Interestingly, a senior NHPC official told media: “We are working in the hills and construction activity can trigger such situations.” This acceptance that the hydropower projects can trigger landslides is something hydropower companies never accept.
The NHPC is likely to say that the reduction in water flow in the Subansiri river for about twelve hours will in any case happen whenever they close the DT. However, this closure of DT is not happening as per a planned activity. Since the spillway gates are not yet ready, they will either have to open one of the DTs or build a coffer dam to isolate the spillway gates where work is still incomplete, which will take additional cost, time and impacts ultimately.
CEA had clearly said in its tour report of April 2022: “Further, the reservoir filling would commence only after the dam achieves a certain height and provided all Spillway Radial Gates have been erected and tested.” The reservoir filling taken up now on Oct 27 2023 clearly violates this CEA directions since it is happening while all Spillway Radial Gates have not been erected and tested.
The CEA report further states: “It is understood that the civil works would proceed only in dry/ lean season. Further, after the Civil Contractor hands over the (Spillway) bays to HM Contractor, it would take a minimum of 3.5 months for erection of Spillway Radial Gates and their testing.”
All these processes need to go as directed, else there is bound to be serious issues concerning safety of the project. We hope NHPC is not bypassing any of these directions and CEA, CWC and NDMA (National Disaster Management Authority) will not allow NHPC to bypass of the safety measures. It is not clear why the NHPC did not use the silt flushing tunnel to continue the flow in the river downstream, assuming the dam has silt flushing tunnel at the bottom. 
Local authorities have reported that lakhs of fish have died due to the sudden drop in the water level of the Subansiri River. This will have huge implications not only for the aquatic biodiversity, habitat and livelihoods not only currently, but for future too.
The Assam government must assess these impacts and ensure that NHPC compensates the losses to the affected people. The North Lakhimpur District came out with an advisory notice for safety in the downstream area, but the official needs to go far beyond to ensure the affected people are compensated.

In conclusion

As India faces multiple dam disasters this year, including washing away of the massive 1200 MW Teesta 3 dams in Sikkim, it is high time that the authorities wake up and do no allow hydropower developers allow to adopt short cuts, the way Teesta 3 dam developers did and now NHPC seems to be doing in case of Lower Subansiri HEP.
Subansiri is a much bigger river and it also has numerous glaciers in the catchment. It may be added that like in case of Teesta 3, Lower Subansiri HEP spillway also are not designed for Glacier Lake Outburst Floods. On top of it, any shortcuts adopted in construction of spillway for the project can only be invitation to trouble. Like the short cuts adopted in construction of Medigadda Dam on Godavari leading to sinking of its pillars last week. Clearly our Dam Safety Mechanism needs to do a lot more to inspire confidence.

Comments

TRENDING

US govt funding 'dubious PR firm' to discredit anti-GM, anti-pesticide activists

By Our Representative  The Alliance for Sustainable & Holistic Agriculture (ASHA) has vocally condemned the financial support provided by the US Government to questionable public relations firms aimed at undermining the efforts of activists opposed to pesticides and genetically modified organisms (GMOs) in India. 

Modi govt distancing from Adanis? MoEFCC 'defers' 1500 MW project in Western Ghats

By Rajiv Shah  Is the Narendra Modi government, in its third but  what would appear to be a weaker avatar, seeking to show that it would keep a distance, albeit temporarily, from its most favorite business house, the Adanis? It would seem so if the latest move of the Ministry of Environment, Forests and Climate Change (MoEFCC) latest to "defer" the Adani Energy’s application for 1500 MW Warasgaon-Warangi Pump Storage Project is any indication.

Bayer's business model: 'Monopoly control over chemicals, seeds'

By Bharat Dogra*  The Corporate Europe Observatory (CEO) has rendered a great public service by very recently publishing a report titled ‘Bayer’s Toxic Trails’ which reveals how the German agrochemical giant Bayer has been lobbying hard to promote glyphosate and GMOs, or trying to “capture public policy to pursue its private interests.” This report, written by Joao Camargo and Hans Van Scharen, follows Bayer’s toxic trail as “it maintains monopolistic control of the seed and pesticides markets, fights off regulatory challenges to its toxic products, tries to limit legal liability, and exercises political influence.” 

Militants, with ten times number of arms compared to those in J&K, 'roaming freely' in Manipur

By Sandeep Pandey*  The violence which shows no sign of abating in the ongoing Meitei-Kuki conflict in Manipur is a matter of concern. The alienation of the two communities and hatred generated for each other is unprecedented. The Meiteis cannot leave Manipur by road because the next district North on the way to Kohima in Nagaland is Kangpokpi, a Kuki dominated area where the young Kuki men and women are guarding the district borders and would not let any Meitei pass through the national highway. 

105,000 sign protest petition, allege Nestlé’s 'double standard' over added sugar in baby food

By Kritischer Konsum*    105,000 people have signed a petition calling on Nestlé to stop adding sugar to its baby food products marketed in lower-income countries. It was handed over today at the multinational’s headquarters in Vevey, where the NGOs Public Eye, IBFAN and EKO dumped the symbolic equivalent of 10 million sugar cubes, representing the added sugar consumed each day by babies fed with Cerelac cereals. In Switzerland, such products are sold with no added sugar. The leading baby food corporation must put an end to this harmful double standard.

Can voting truly resolve the Kashmir issue? Past experience suggests optimism may be misplaced

By Raqif Makhdoomi*  In the politically charged atmosphere of Jammu and Kashmir, election slogans resonated deeply: "Jail Ka Badla, Vote Sa" (Jail’s Revenge, Vote) and "Article 370 Ka Badla, Vote Sa" (Article 370’s Revenge, Vote). These catchphrases dominated the assembly election campaigns, particularly across Kashmir. 

Swami Vivekananda's views on caste and sexuality were 'painfully' regressive

By Bhaskar Sur* Swami Vivekananda now belongs more to the modern Hindu mythology than reality. It makes a daunting job to discover the real human being who knew unemployment, humiliation of losing a teaching job for 'incompetence', longed in vain for the bliss of a happy conjugal life only to suffer the consequent frustration.

NITI Aayog’s pandemic preparedness report learns 'all the wrong lessons' from Covid-19 response

Counterview Desk The Universal Health Organisation (UHO), a forum seeking to offer "impartial, truthful, unbiased and relevant information on health" so as to ensure that every citizen makes informed choices pertaining to health, has said that the NITI Aayog’s Report on Future Pandemic Preparedness , though labelled as prepared by an “expert” group, "falls flat" for "even a layperson". 

How retraints were imposed on academic freedom on the IIM-Ahmedabad campus

By Sandeep Pandey*  This is the seventh consecutive academic year when I would have gone as a visiting faculty member to the Indian Institute of Management at Ahmedabad to teach an Elective course on Transformational Social Movements to the second year of Post Graduate Programme students. But the invitation has not come so far and it looks like it is the end of my teaching stint at IIM, at least, so long as the Bhartiya Janata Party remains in power at the centre.