Skip to main content

Mining in India has mostly taken place in common grazing land: Study cites environment ministry data

Counterview Desk
A recent study, “Midcourse Manoeuvres: Community strategies and remedies for natural resource conflicts in India”, says that a sectoral and regional distribution of environment clearances for projects granted environmental clearance up to October 2017 indicates that states such as Andhra Pradesh, Gujarat, Maharashtra and Tamil Nadu have “a large number of environment clearances for industrial projects”.
Analyzing 4,553 projects, listed on the environment ministry’s website as of October 2017, as they appeared in January 2018, the study analyses four sectors, mining, thermal power, river valley projects, and infrastructure and CRZ.
Authors Kanchi Kohli, Meenakshi Kapoor, Manju Menon and Vidya Viswanathan of the CPR-Namati Environmental Justice Program, New Delhi, however, regret, the only environmental clearance letters could be used for analysis because the ministry “maintains a record only of the number of approvals and not the land area approved.” 

Excerpts from the study:

The data analysed is for an 11-year period for the years 2005-16. It was in 2004 when several new sectors such as building and construction projects were brought under the purview of the EIA notification. With increased urbanisation, these sectors have had a significant bearing on land use change. According to the Federation of Indian Chambers of Commerce and Industry (FICCI), the real estate sector has been on a “roller coaster ride” since 2005 and is growing at the rate of 20% per annum.
From 2005-16, more than 3,12,524 ha of land was diverted for 116 river valley projects (total river valley projects approved during this period). Out of this, 51,130 ha was forest land. The state wise distribution of the land use change due to river valley projects is presented below. Manipur and Andhra Pradesh stand out because of Tipaimukh (31,950 ha) and Polavaram (46,060 ha) multipurpose dams.
The same data can be also be analysed to understand the year-wise land use change for both forest and non- forest land from 2005-16 for 116 (out of 163) river valley projects approved during that period. The maximum non-forest land was diverted between 2005 and 2006, amounting to a total of 2,04,315 ha. When it comes to forestland, the big peak is in 2008 because of the approval for the Tipaimukh multipurpose project (26,237 ha).

Mining (coal and non-coal mining)

From 2005-16, 7,31,787 ha of land was diverted for 1,881 mining projects. The total mining projects approved during this period were 2,523. Out of this 1,77,206 ha was forestland. Other lands include agricultural and grazing lands. States such as Chhattisgarh, Maharashtra, Madhya Pradesh, Jharkhand, Odisha and Rajasthan are where the largest amount of land use change has taken place due to mining. In Rajasthan (4%) and Gujarat (2%) very little forest area has been approved towards land use change. 
This is because the approval letters indicate that most of the lands taken up for mining are common grazing lands. In Uttarakhand, 82% of the mining is in forest land. However, this is mostly riverbed sand and boulder mining, which has to go through the approval process due to change in regulations in 2015.
The maximum land was approved towards mining in the years 2007-09. In contrast, there has been a slowdown in approvals since 2011 with a spike again in 2014. The data also indicates that there is a larger percentage of non-forest land that has been approved for the mining projects. In 2007, the distribution was 22% forestland and 78% non-forest land; in 2008, it was 33% forestland and 67% non-forest land; in 2009, the distribution was 26% forest land and 74% non-forest land.
There are a few national and international level developments that could help contextualise this. The Ministry of Mines set up the MB Shah Commission in 2010 to probe into illegal mining in several states including Odisha, Goa and Karnataka. While the Commission’s enquiry was underway, there was a slowdown in approvals to several iron ore mining projects. The Commission is said to have submitted its final report in mid-October, just before its term ended on October 16, 2013, as the term was not extended to be able to cover all states where illegal mining was reportedly underway.
State-wise distribution of environment clearances up to October 2017
Another reason for this could be the overall slowdown in the iron ore demand. In 2012, there was a global drop in demand for iron ore, thereby reducing the number of investors who would have pursued new projects and environmental approvals. Indian firms engaged in iron ore mining faced a big setback during this period and are yet to fully recover.
The Coalgate case and judgment also had a bearing on approvals to coal mining projects. On September 24, 2014, the much-awaited decision of the Supreme Court on the allocation of coal blocks was delivered. This direction followed an earlier judgment of August 25, 2014, rendering all coal mine blocks allocated through the government steering committee process since 1993, as illegal and arbitrary. 
The process of granting approvals saw a substantial slow down till the Coal Mines (Special Provisions) Act, 2015 came into place, and the process of auctioning coal blocks was put into place. It is only late 2016 onwards that coal mining blocks that were re-auctioned began to seek fresh or transfer of environmental approvals.
2013 and 2014 saw a spike in approvals when minor mineral projects (even under 5 hectares) were made to go through the approval process following the orders of the Supreme Court and National Green Tribunal. 166 minor mineral projects were approved in Punjab. However, related documents for these approvals have not been uploaded on the ministry’s website.

Infrastructure and CRZ projects

The Environment Ministry’s Expert Appraisal Committee (EAC) for infrastructure and CRZ projects primarily looks at projects such as highways, pipelines, ports and SEZs. It also appraises real estate and construction projects. The projects under CRZ are all those projects which require approval under the Coastal Regulation Zone (CRZ) notification. These could be power plants, tourism projects and sand mining projects in addition to the categories mentioned earlier.
From 2005-16, more than 1,21,797 ha of land was diverted for 694 infrastructure and CRZ projects with most of the land use change in non-forest areas. The total projects approved during this period were 1,325. However, information was not available for several projects, especially linear projects like pipelines and highways where the total land area or its break up is not disclosed on the ministry’s website.
Out of this 6,402 ha was forestland. In Mizoram, all the land use change was in the forest area because of the construction of one road project, which involved the use of 197 ha of forestland. The use of forestland for infrastructure projects is visible in states and union territories such as Uttarakhand, Jammu and Kashmir, Jharkhand, Uttar Pradesh, Chandigarh, Himachal Pradesh. 
The use of forestland in Uttarakhand is essentially for three ropeway projects while in Uttar Pradesh it is for nine highway projects (both new constructions as well as upgradation). In J&K it is for two ropeway projects and one highway project.
Other lands for this sector include agricultural and grazing lands. On the coast, several fishing areas are revenue commons or held by government departments such as fisheries or ports. This could be one of the reasons that for the states, which have a coastline, the forestland diversions are minimal.
Sector-wise environment clearances across states with over 500 projects approvals (1968-2017)
The same data can also be analysed to understand the year-wise land use change for both forest and non-forest land from 2005-16 for 116 (out of 163) infrastructure and CRZ projects approved during that period. The maximum non-forest land was diverted during 2007 and 2014. This amounted to a total of 32,103 ha only for these two years. It is difficult to ascertain the exact reasons for the same.
However, the 2007 peak is because of the inclusion of building and construction projects in the new EIA notification, 2006, which were to be appraised by newly established state level institutions. In the interim, the MoEFCC approved these projects. When it comes to forestland, the big peak is in 2012, 2013 and 2016. The reasons for the same are unclear. 

Thermal Power

From 2005-16, more than 78,428 ha of land was diverted for 271 thermal power projects. This was both new as well as expansion projects. The total projects approved during this period were 552. However, information was not available for several projects, primarily because the website of the ministry either did not have documents uploaded or the environment clearance letters did not mention the land area required for the project.
The maximum amount of non-forest land was approved for thermal projects in the states of Madhya Pradesh, Maharashtra, Andhra Pradesh and Tamil Nadu and Uttar Pradesh. Some of these were extremely high profile projects where conflicts were reported, like the 4x300 MW Jaigad TPP in Ratnagiri, Maharashtra and 2x660 MW IL&FS TPP at Cuddalore, Tamil Nadu.
2,000 ha was forest land for the 25 of the total approved projects for which approval letters specified the breakup of land. Chhattisgarh, Jharkhand and Madhya Pradesh saw maximum amount of forestland diverted during this period accounting to 1506 ha. Some of these projects include 4000 MW Tilaiya Ultra Mega Power Project in Jharkhand (621.59 ha) and 2x660 MW Coal Based Thermal Power Plant at village Salka, in Premnagar, Chhattisgarh (135.7 ha).
The maximum amount of land appears to have been approved during the years 2007-10. One reason for this is the increased investment of the private sector in thermal power generation. A record 52 projects were allocated to the private sector during 2007-09, which included Ultra Mega Power Projects (UMPPs) of groups such as Tata Power and Reliance Power. The other prominent actors were the Adani, Jaypee and Lanco. Following their allocation, several of these projects were granted environment clearance by the environment ministry.
Unlike other sectors, several projects granted environment clearance from 2005-16 were approved indicating that they would be built on approximately 8984 ha of land that was already in possession of the respective project proponents. This was the case with 109 expansion/replacement or augmentation projects. This includes Rihand Super Thermal Power Project Stage-III (2x500 MW) in Uttar Pradesh, which sought to utilise 295.42 ha that was already with the project proponent. The amount of land to be utilised for these projects ranged from 0.068 ha to 450 ha.
---
Download full report HERE

Comments

TRENDING

#MeToo moment in Hyderabad Urdu varsity? Two girl students seek action against authorities

Counterview Desk
Has the #MeToo movement reached Maulana Azad National Urdu University (MAANU)? It would seem so if a recent letter by newly-appointed chancellor Firoz Bakht Ahmed to MAANU vice-chancellor Dr Aslam Parvaiz is any indication. Seeking reinstatement of two girl victims of “sexual harassment and humiliation”, the letter specifically names head of the department of the Media Centre for Journalism, suspecting, the problem could be much deeper.
Text of the letter: It is a matter of utmost perturbation for me to receive the two representations from the girls studying in the MCJ (Media Center for Journalism) regarding their sexual and subsequently, mental and social harassment at the hands of Prof Ehtesham Ahmad Khan, the HOD, MCJ.
We do not know, how many girls have been exploited by him and preferred to be silent for saving their family’s honour; however, there are two brave girls who stood to the depraved advances and misuse by Prof Ehtesham and came up with written complai…

"Ineligible" funding of Sardar Statue in Gujarat: CAG tells Central PSUs, it's not a heritage CSR activity

By Our Representative
The Comptroller and Auditor General (CAG) of India, in its recent report on Central Public Sector Enterprises (CPSE), has qualified public sector undertakings’ (PSUs') funding the 182-metre world’s highest Sardar Statue, currently being constructed in the Narmada river downstream of the Sardar Sarovar dam as an “ineligible” corporate social responsibility (CSR) activity.

"Highly irregular" for PSUs to fund Sardar Statue under Corporate Social Responsibility

Counterview Desk
In a letter to I Srinivas, secretary, Ministry of Corporate Affairs, Government of India, former secretary (economic affairs), Ministry of Finance, EAS Sarma, has raised questions on the funding of the Sardar Patel statue in South Gujarat by Central Public Sector Undertaking (CPSUs) relying on the Comptroller and Auditor General report (No 18/2018).

Murder of Tamil Nadu teenage Dalit girl: "Stoic silence" despite #MeToo movement

Counterview Desk
Brinelle D'souza, who is with the Centre for Health and Mental Health, School of Social Work, Tata Institute of Social Sciences, Mumbai, has prepared a strong statement to protest the brutal murder of 13-year-old Rajalakshmi. "Other than a few media reports, this gruesome killing has not caught national attention despite a very vibrant #MeToo campaign currently underway", regrets D'souza.

29th "NRC-related" suicide in Assam, as Nirod Baran Das takes his life by hanging on a fan

By Our Representative
Reporting 29th case of National Register of Citizens (NRC)-driven suicide in Assam, one of India’s human rights campaign sites has said that, on October 20, tragedy struck Kharupetia town in Darrang district of Assam, when a retired school teacher and advocate Nirod Baran Das “took his life by hanging himself to a fan in his home.” The report adds, “The NRC process has so far claimed over two dozen such lives in the past four months alone.”

World Bank clarifies: Its 26th rank to India not for universal access to power but for ease of doing business

By Our Representative
In a major embarrassment to the Government of India, the World Bank has reportedly clarified that it has not ranked India 26th out of 130 countries for providing power to its population. The top international banker’s clarification comes following Union Power Minister Piyush Goyal’s claim that India has “improved to 26 position from 99” in access to electricity in just one year.

Preventing childhood deaths: India performs worse than Bangladesh, "equals" Pakistan

By Rajiv Shah
A just-released study, “The Pneumonia and Diarrhea Progress Report 2018”, prepared by the International Vaccine Access Centre (IVAC) at the Johns Hopkins Bloomberg School of Public Health, has identified India among 15 other countries which are still far off the mark in achieving the targets of the Global Action Plan for the Prevention of Pneumonia and Diarrhea (GAPPD).

Some Hindu bodies in US defending BJP-RSS' divisive, violent activities: Agnivesh

Counterview Desk  Last week, Washington DC saw speakers at a religious freedom roundtable, chaired by the US Ambassador for Religious Freedom, Sam Brownback, express concern over "eroding" space for religious freedom in India. Dr Mike Ghouse, executive director, of the Center for Pluralism in Washington DC, referring to the roundtable, said in an email alert that Indian-Americans have "a moral duty to prevent India from being labeled as a Country of Particular Concern by the United States Commission on International Religious Freedom (USCIRF)".

Bank account frozen, raid on Amnesty office: Govt of India "treating" human rights NGOs like criminal enterprises

By Abhirr VP*
Amnesty India’s bank accounts have been frozen by the Enforcement Directorate, effectively stopping its work. Amnesty India is thus the latest target of the government’s assault on civil society in the country. The accounts of Greenpeace India were frozen earlier this month.

60 ex-civil servants seek release of CAG reports on Rafale, demonetisation before 2019 polls

Counterview Desk
As many as 60 retired civil servants have asked President Ram Nath Kovind to expedite the release of Comptroller and Auditor General (CAG) reports on demonetisation and the Rafale deal. The letter, signed mainly by former Indian Administrative Service, Indian Foreign Service and Indian Police Service officers, regrets that the status of the audit is "unclear”. According to them, “An impression is gaining ground that CAG is deliberately delaying its audit reports on demonetisation and Rafale deal till after the May 2019 elections so as not to embarrass the present government”.