Bharuch floods: Narmada waters could have been put to 'better use', generating Rs 85 crore

By Himanshu Thakkar*

One of the ways the Narmada waters in the Sardar Sarovar Dam (SSD) could have been put to productive use, instead of draining them from the spillways, leading to major floods in Bharuch between August 29 and September 2, would have been by generating power by operating the 1200 MW River Bed Power House (RBPH) and 250 MW Canal Head Power House (CHPH) at full capacity over a longer period.
A perusal of the Narmada Control Authority’s (NCA’s) Daily Status Reports and Daily Plant Report of the Sardar Sarovar Project (SSP) Power Houses tells us that till August 25, RBPH was generating zero power since July 14 and even CHPH generated no power even on August 25, and just 0.509 MU (Million Units), operating just one of the five 50 MW units for 11 out of 24 hours on August 26.
It was only by September 3 that both RBPH and CHPH started operating at full capacity. If SSD operators had started generating full power even from August 21 (in consultation with NCA and beneficiary states of MP and Maharashtra, they would not have said no to additional power that is rightfully theirs), SSP could have generated additional 283.85 MU in additional ten days, which would have meant additional value generation of Rs 85 crore, assuming price of Rs 3 per unit of power.
But for some strange, unknown reasons, water was not used productively, which would have also helped a step towards avoiding flood disaster in Bharuch.
Why did the SSP power units take over seven days to reach full load? The first unit of RBPH was started at 14.45 hours on August 26, as per NCA daily updates dated Aug 27, 2020. Thereafter slowly other units were started. All six RBPH units started operating for the first time at 0120 hrs on August 30, as per the power station NCA update of Aug 31, 2020.
However, the units were still not operating at full load. The units were operating around 160 MW load against its 200 MW capacity on August 30, August 31, September 1 (164 MW), September 2 (196 MW). It was only on September 4 when all six RBPH units were for the first time operating at or above 200 MW rated capacity, when the RBPH generation reached 28.538 MU as per NCA power plant update dates September 5, 2020.
On Sept 4, 2020, the RBPH discharge also reached a peak of 1,199 cumecs as reported by NCA Daily Status report of September 5, 2020. CHPH power generation reached a peak of 3.902 MU on September 1, and its discharge of 437.8 cumecs was also maximum during that period.
The big mystery is: Why did SSP power units take so many hours and days to reach peak load? The four retired officials’ note (published by Counterview), in their reply to my view (see Counterview), state: "In fact, Operation of River Bed Power House was started on August 26, 2020 and gradually stepped up to operation of all 6 turbines at I0.00 hours on August 30, 2020."
This is clearly wrong in many details, as usual, but agrees that RBPH took five days to start all six units (full load is a different matter). It should have taken no longer than an hour to ramp up all the units of SSP power houses. The delay of so many days not only meant lower power generation, but also additional floods in downstream areas.
Let us take note of the celebrated event of April 5, 2020 when this prowess of quick ramping down and up of hydropower projects was successfully showcased at national level.
On April 5, 2020, when following the Prime Minister's call for 9 minutes lights off at 9 pm, the sudden drop in power demand was 31,089 MW, and that ramping down of generation within minutes could be possible due to hydropower projects, as media reported quoting Union Power Minister, among others.
The demand then jumped by 28,001 MW in the next one hour. Both this ramping down and up, within minutes was possibly due to hydropower projects.
So the mystery of slow ramping of SSP power units remains unresolved.
--
*South Asia Network on Dams, Rivers & People (SANDRP), Delhi

Comments

TRENDING

How strategic is India's commercial expansion in the Mediterranean?

By Vijay Prashad  On 26 October 2026, Greece’s foreign minister George Gerapetritis stood at the United Nations headquarters and rejected the maritime agreement between Turkey and Libya. Gerapetritis spoke on behalf of Greece of course, but also Bahrain, Cyprus, Egypt, the European Union, and the United Arab Emirates. Five days later, the Indian frigate INS Trishul entered Souda Bay in Crete as part of activities with the US Navy installation (Naval Support Activity) and with the NATO Maritime Interdiction Operational Training Centre. The sequence illuminates a developing strategic geography: India’s naval reach, its confrontation with Pakistan’s new Turkish partner, and its ambition to connect Indian capital to European markets increasingly converge in the eastern Mediterranean.

'No vacant geographical spaces’: CMs urged to protect the Ghats from energy infrastructure overload

By A Representative   A prominent power and climate policy analyst has urged the Chief Ministers of Maharashtra, Andhra Pradesh, and Karnataka to comprehensively reassess the rapid proliferation of large pumped storage projects in the ecologically fragile Western and Eastern Ghats. In a detailed representation, addressed to the three Chief Ministers with copies to the Prime Minister and the Union Minister for Environment, Forest and Climate Change, analyst Shankar Sharma warned that the current trajectory of energy storage development risks irreversible ecological and social damage.

Letter to Modi seeks cancellation of "coercive" anti-NGO order on foreign funding rules

By A Representative  Around 70 civil rights organizations have come together to strategize “a collective response to the stifling of civil society space” in the wake of the recent Government of India clampdown on NGOs, telling Prime Minister Narendra Modi that government steps are “coercive” in nature, are “without reasonable cause or due process”, and seek to “cripple” the ability of NGOs to “carry on their legitimate and sanctioned work.”