Skip to main content

No official documents exist showing eco-clearance for Garudeshwar Weir

Villagers protest against Garudeshwar Dam
By Rohit Prajapati, Lakhan Musafir*
In our case against Garudeshwar Weir (being set up about 12 km downstream of the Sardar Sarovar Dam in Narmada river) in the National Green Tribunal (NGT), the Ministry of Environment and Forests (MoEF), has said, “… no project proposal regarding Garudeshwar Weir at Garudeshwar village, District Narmada of Gujarat, has been received in this Ministry.” The Sardar Sarovar Narmada Nigam Ltd (SSNNL) has said, its affidavit is only for “the limited purpose”, it is “not dealing with the application parawise”, nor it is “giving elaborate details which would show that construction of Garudeshwar Weir is strictly in conformity with law.” It is now clear: the SSNNL has no documents to show and prove that the construction of Garudeshwar Weir is going on as per the law.
In their replies the MoEF, the Narmada Control Authority (NCA) and the SSNNL do not deny our contention that:There has never been an environment and social impact assessment of the Garudeshwar weir, nor is there any environment and social management plan,
There has never been any public consultation on the issue of Garudeshwar Dam, and
The Garudeshwar Dam requires statutory clearances from the Environment Sub Group, Rehabilitation Sub Group of the NCA and also the NCA itself, but such clearances have not been taken.
In view of this, as mentioned in our petition, the work on Garudeshwar Dam, now going on, is illegal and should immediately stop till all necessary statutory clearances are taken, and till informed consultation process is completed.

MoEF wants to be excused

The MoEF, in its reply filed before the NGT on May 29, 2014, in response to our Application No 10/2014 (WZ) stated, “No project proposal regarding Garudeshwar Weir at Garudeshwar Village, District Narmada of Gujarat has been received in this Ministry.” It has become clear that at no point of time the construction of Garudeshwar Weir had come before it for environmental clearance.
The MoEF implicitly agrees with our contention that the Garudeshwar Dam is a project for which no impact assessment was available before it at any stage. This implies that the affected villages, next to the weir, were neither surveyed, nor environmental and social impact was made known, nor were mitigation and management plans prepared, nor were there any consultations. The impact assessment of Garudeshwar Dam was not part of the studies submitted by Gujarat to the MoEF before the 1987 environmental clearance of the Sardar Sarovar Project (SSP). Thus, environmental clearance for SSP cannot be construed as clearance for Garudeshwar Weir.
The MoEF is not denying the contents of letter dated March 24, 2013 written by Shekhar Singh, an independent member of environment sub-group of the NCA (the statutory body responsible for clearance before taking up construction for the SSP at every stage), and the letters dated October 26 and 28, 2013 of the Paryavaran Suraksha Samiti and villagers. The MoEF only states in its affidavit, “…copies of the letter dated 24.3.2013 by Mr. Shekhar Singh, Member, ESG, Narmada Control Authority and letter dated 26.10.2013 by Applicants could not be traced in the Ministry. Therefore, no responses were made on the subject.”
The Supreme Court order dated October 18, 2000 in the case of Narmada Bachao Andolan v/s Union of India and others states that environment clearance for the Narmada project, approval of the environment sub-group (ESG) and rehabilitation & resettlement sub-group (RSG) of the NCA are necessary at each stage of project construction. Without such explicit approval, the construction of any component of the project cannot be taken up. Since construction of Garudeshwar Weir has not been approved by the ESG and RSG of the NCA at any stage, such construction is illegal and should be stopped.
The MoEF in its affidavit at the end states, “As per contents of the petition, MoEF is not having any role to play in the present petition. Therefore, MoEF may not be made a party in the present Petition.”
But MoEF is an environmental regulator of India, which is responsible for the protection of environment and forest in general, and the secretary, MoEF, is also a chairman of the ESG of NCA. The MoEF cannot shirk its responsibility and it is shocking to see MoEF shirking its responsibility.

NCA’s untenable reply

The executive engineer of the NCA filed a reply on behalf of the chairman of the environment and rehabilitation sub-groups of the NCA, the chairman of the NCA, secretary of the Ministry of Social Justice and Empowerment, and also secretary of the Ministry of Water Resources! This is clearly a legally untenable act. The executive engineer of the NCA does not have legal authority and mandate to file joint reply on behalf of these bodies, which have very specific and different roles. Clubbing them in one reply is not only violation of the cause of environment, rehabilitation, water resources development and independent and statutory groups and authorities; it would do disservice to the interests these authorities and ministries are supposed to protect. The affidavit is also in violation of the basic principle of judicial process and hence should be rejected.
The reply is nowhere disputing our contention that social or environmental impact assessment of the construction of Garudeshwar Weir has not been taken up at any stage. Nor is the reply disputing our contention that no participatory decision making process has been followed before starting the construction of the Garudeshwar Weir, involving the affected people and other interest groups.
The reply is also not disputing our contention that at no stage the permissions of the environment sub-group, rehabilitation sub-group, and participating states have been taken for the construction of the Garudeshwar Weir.
In fact the reply is so callous that it does not even bother to state what the impact of the Garudeshwar Dam would be. The reply does not go into merits of the issues about the impact of the Garudeshwar Dam and what has been done about that. It only contends that the application should be dismissed on procedural grounds, and just to contend this, it has taken more than four months, which is clearly an abuse of the time given to it.
If indeed any social and environmental impact assessment of the Garudeshwar Dam has been done, or the authorities have taken and/or expressed and specific permission of the environment and rehabilitation sub-groups of the NCA and the NCA, then this should have been produced. Taking up construction of the Garudeshwar Weir is in violation of the due process, including that of the Supreme Court order.

The SSNNL reply

The reply filed by the SSNNL after taking more than four months is vague; it has tried its best to avoid addressing the basic crucial issue of the furnishing the mandated environmental impact assessment and environment clearance of Garudeshwar Weir.
The SSNNL representative in the reply states “… I am filing this affidavit only for the limited purpose as aforesaid, I am not dealing with the application parawise at this stage nor am I giving elaborate details which would show that construction of Garudeshwar Weir is strictly in conformity with law.” By stating “… nor am I giving elaborate details which would show that construction of Garudeshwar Weir is strictly in conformity with law”, the SSNNL reply makes it crystal clear that it does not have documents to show and prove that the construction of Garudeshwar Weir is going on as per law. It also does not have documents to show that it obtained the necessary environment clearance from the concerned authority.
The SSNNL in its reply further states, “At the outset, I beg to raise the following preliminary objections as regards the maintainability of the present application under the National Green Tribunal Act, 2010 which is purported to have been filed under Section 18(1) read with Section 14 and 15 of the National Green Tribunal Act, 2010. I respectfully pray that the below mentioned preliminary objections be decided first.” This is a ploy adopted by the SSNNL to delay the case and continue with the illegal construction work to defeat the process of justice.

Our Response

We had filed our affidavits in rejoinder, in response to all the affidavits filed by the authorities, and raised above-mentioned issues in our affidavits, and demanded stoppage of irreversible nature of work carried out by the SSNNL for Garudeshwar Weir. Considering that none of the concerned authorities have been able to produce either impact assessment or environment clearance obtained from the MoEF and from the environment and R&R sub-groups of the NCA, the NGT should immediately order stoppage of work.

*Representing Paryavaran Suraksha Samiti, Vadodara, which has filed a petition in the National Green Tribunal to immediately stop work the Garudeshwar Weir, 12 km off Sardar Sarovar dam

Comments

TRENDING

From Kerala to Bangladesh: Lynching highlights deep social faultlines

By A Representative   The recent incidents of mob lynching—one in Bangladesh involving a Hindu citizen and another in Kerala where a man was killed after being mistaken for a “Bangladeshi”—have sparked outrage and calls for accountability.  

Gram sabha as reformer: Mandla’s quiet challenge to the liquor economy

By Raj Kumar Sinha*  This year, the Union Ministry of Panchayati Raj is organising a two-day PESA Mahotsav in Visakhapatnam, Andhra Pradesh, on 23–24 December 2025. The event marks the passage of the Panchayats (Extension to Scheduled Areas) Act, 1996 (PESA), enacted by Parliament on 24 December 1996 to establish self-governance in Fifth Schedule areas. Scheduled Areas are those notified by the President of India under Article 244(1) read with the Fifth Schedule of the Constitution, which provides for a distinct framework of governance recognising the autonomy of tribal regions. At present, Fifth Schedule areas exist in ten states: Andhra Pradesh, Chhattisgarh, Gujarat, Himachal Pradesh, Jharkhand, Madhya Pradesh, Maharashtra, Odisha, Rajasthan and Telangana. The PESA Act, 1996 empowers Gram Sabhas—the village assemblies—as the foundation of self-rule in these areas. Among the many powers devolved to them is the authority to take decisions on local matters, including the regulation...

What Sister Nivedita understood about India that we have forgotten

By Harasankar Adhikari   In the idea of a “Vikshit Bharat,” many real problems—hunger, poverty, ill health, unemployment, and joblessness—are increasingly overshadowed by the religious contest between Hindu and Muslim fundamentalisms. This contest is often sponsored and patronised by political parties across the spectrum, whether openly Hindutva-oriented, Islamist, partisan, or self-proclaimed secular.

When a city rebuilt forgets its builders: Migrant workers’ struggle for sanitation in Bhuj

Khasra Ground site By Aseem Mishra*  Access to safe drinking water and sanitation is not a privilege—it is a fundamental human right. This principle has been unequivocally recognised by the United Nations and repeatedly affirmed by the Supreme Court of India as intrinsic to the right to life and dignity under Article 21 of the Constitution. Yet, for thousands of migrant workers living in Bhuj, this right remains elusive, exposing a troubling disconnect between constitutional guarantees, policy declarations, and lived reality.

Policy changes in rural employment scheme and the politics of nomenclature

By N.S. Venkataraman*  The Government of India has introduced a revised rural employment programme by fine-tuning the Mahatma Gandhi National Rural Employment Guarantee Act (MGNREGA), which has been in operation for nearly two decades. The MGNREGA scheme guarantees 100 days of employment annually to rural households and has primarily benefited populations in rural areas. The revised programme has been named VB-G RAM–G (Viksit Bharat Guarantee for Rozgar and Ajeevika Mission – Gramin). The government has stated that the revised scheme incorporates several structural changes, including an increase in guaranteed employment from 100 to 125 days, modifications in the financing pattern, provisions to strengthen unemployment allowances, and penalties for delays in wage payments. Given the extent of these changes, the government has argued that a new name is required to distinguish the revised programme from the existing MGNREGA framework. As has been witnessed in recent years, the introdu...

Aravalli at the crossroads: Environment, democracy, and the crisis of justice

By  Rajendra Singh*  The functioning of the Ministry of Environment, Forests and Climate Change has undergone a troubling shift. Once mandated to safeguard forests and ecosystems, the Ministry now appears increasingly aligned with industrial interests. Its recent affidavit before the Supreme Court makes this drift unmistakably clear. An institution ostensibly created to protect the environment now seems to have strayed from that very purpose.

'Structural sabotage': Concern over sector-limited job guarantee in new employment law

By A Representative   The advocacy group Centre for Financial Accountability (CFA) has raised concerns over the passage of the Viksit Bharat – Guarantee for Rozgar and Ajeevika Mission (VB–G RAM G), which was approved during the recently concluded session of Parliament amid protests by opposition members. The legislation is intended to replace the Mahatma Gandhi National Rural Employment Guarantee Act (MGNREGA).

'Festive cheer fades': India’s housing market hits 17‑quarter slump, sales drop 16% in Q4 2025

By A Representative   Housing sales across India’s nine major real estate markets fell to a 17‑quarter low in the October–December period of 2025, with overall absorption dropping 16% year‑on‑year to 98,019 units, according to NSE‑listed analytics firm PropEquity. This marks the weakest quarter since Q3 2021, despite the festive season that usually drives demand. On a sequential basis, sales slipped 2%, while new launches contracted by 4%.  

Safety, pay and job security drive Urban Company gig workers’ protest in Gurugram

By A Representative   Gig and platform service workers associated with Urban Company have stepped up their protest against what they describe as exploitative and unsafe working conditions, submitting a detailed Memorandum of Demands at the company’s Udyog Vihar office in Gurugram. The action is being seen as part of a wider and growing wave of dissatisfaction among gig workers across India, many of whom have resorted to demonstrations, app log-outs and strikes in recent months to press for fair pay, job security and basic labour protections.