Just 8.2% projects stalled due to land acquisition, 4.2% for environmental reasons: Union finance ministry

By A Representative
A Union finance ministry reply to a right to information (RTI) plea has revealed that, as of February 2015, as many as  804 projects were stalled due to variety of reasons, but just about eight per cent of the projects (66) were stalled because of land acquisition problems. Based on the reply, Venkatesh Nayak of the Commonwealth Human Rights Initiative says, this suggests, "the argument that the slowdown in the economy is due to land acquisition projects is a myth."
The data, from 25 states and two union territories, suggest that Maharashtra tops the list with 125 stalled projects, followed by Gujarat (63 projects), West Bengal (55 projects), Karnataka (52 projects) and Telangana (52). The private sector projects account for 78 per cent of projects, outnumbering the public sector projects planned by the Central or state governments, or public sector enterprises or local municipal boards and autonomous authorities.
"Of the 66 projects stalled due to land acquisition issues, only 11 (1.36 per cent of 804 projects) directly relate to the well being of the disadvantaged or less affluent segments of society such as slum rehabilitation projects or construction of budget housing projects or a bus stand (which few affluent people use)", Nayak says in his analysis. forwarded to Counterview.
He comments, "So the proposal to amend the Land Acquisition Act to waive the requirement for taking consent of the village assembly in the areas where land is to be acquired for providing affordable housing for the poor will affect a minuscule number of projects." Therefore, he adds, the justification tom-tommed for the amendment becomes "untenable."
On the other hand, 145 of the stalled projects (18 per cent) are for the "affluent and the rich as they are projects involving the construction of shopping malls or elite hotels and resorts (4 and 5 star), multiplexes, elite residences and villas, golf courses and a racing track", says Nayak, adding, "Another 25 stalled projects are about setting up townships", yet "nothing in the list provided by Finance Ministry indicates which segment of society they are intended to benefit."
Further, Nayak says, "Lack of environmental clearances account for a mere 4.2 per cent of the stalled projects, whereas lack of clearance from the state governments amount to 11.8 per cent of the total." He comments, "It looks like the regulatory regimes have contributed to only 16 per cent of the stalled projects. So the license inspector raj also does not appear to be a major contributor to the stalling of the 804 projects, if the latest data are accurate."
"The largest proportion of projects that have stalled (38.8 per cent) are due to unfavourable market conditions or lack of funds or promoter interest or raw material or fuel supply problems", Nayak says, adding, "Several of these projects are owned or promoted by some of the biggest industrial houses in India and a handful of foreign ownership."
Then there are projects listed as "Others" as the reason for the stalling of 19 per cent of the projects (153). "Reasons for stalling are simply not available for 15 per cent of the projects (121). Taken together the projects for which reasons for stalling are either unspecified or simply not available amount to more than a third of the total number of projects (34 per cent).
While projects like those related with power generation, airport construction or expansion, road and railway expansion, pharmaceutical, textile, software and SEZ projects, mining projects for coal and uranium, are part of the stalled projects list, there is no answer to "What is the total value of all 804 projects?" In fact, the RTI reply refuses to divulge the detail despite the fact that a recent Finance Department meet revealed that 300 projects valuing Rs 18.13 lakh crore had remained stalled.

Comments

TRENDING

A comrade in culture and controversy: Yao Wenyuan’s revolutionary legacy

By Harsh Thakor*  This year marks two important anniversaries in Chinese revolutionary history—the 20th death anniversary of Yao Wenyuan, and the 50th anniversary of his seminal essay "On the Social Basis of the Lin Biao Anti-Party Clique". These milestones invite reflection on the man whose pen ignited the first sparks of the Great Proletarian Cultural Revolution and whose sharp ideological interventions left an indelible imprint on the political and cultural landscape of socialist China.

Gujarat Information Commission issues warning against misinterpretation of RTI orders

By A Representative   The Gujarat Information Commission (GIC) has issued a press note clarifying that its orders limiting the number of Right to Information (RTI) applications for certain individuals apply only to those specific applicants. The GIC has warned that it will take disciplinary action against any public officials who misinterpret these orders to deny information to other citizens. The press note, signed by GIC Secretary Jaideep Dwivedi, states that the Right to Information Act, 2005, is a powerful tool for promoting transparency and accountability in public administration. However, the commission has observed that some applicants are misusing the act by filing an excessive number of applications, which disproportionately consumes the time and resources of Public Information Officers (PIOs), First Appellate Authorities (FAAs), and the commission itself. This misuse can cause delays for genuine applicants seeking justice. In response to this issue, and in acc...

Job opportunities decreasing, wages remain low: Delhi construction workers' plight

By Bharat Dogra*   It was about 32 years back that a hut colony in posh Prashant Vihar area of Delhi was demolished. It was after a great struggle that the people evicted from here could get alternative plots that were not too far away from their earlier colony. Nirmana, an organization of construction workers, played an important role in helping the evicted people to get this alternative land. At that time it was a big relief to get this alternative land, even though the plots given to them were very small ones of 10X8 feet size. The people worked hard to construct new houses, often constructing two floors so that the family could be accommodated in the small plots. However a recent visit revealed that people are rather disheartened now by a number of adverse factors. They have not been given the proper allotment papers yet. There is still no sewer system here. They have to use public toilets constructed some distance away which can sometimes be quite messy. There is still no...

Uttarakhand tunnel disaster: 'Question mark' on rescue plan, appraisal, construction

By Bhim Singh Rawat*  As many as 40 workers were trapped inside Barkot-Silkyara tunnel in Uttarkashi after a portion of the 4.5 km long, supposedly completed portion of the tunnel, collapsed early morning on Sunday, Nov 12, 2023. The incident has once again raised several questions over negligence in planning, appraisal and construction, absence of emergency rescue plan, violations of labour laws and environmental norms resulting in this avoidable accident.

'MGNREGA crisis deepening': NSM demands fair wages and end to digital exclusions

By A Representative   The NREGA Sangharsh Morcha (NSM), a coalition of independent unions of MGNREGA workers, has warned that the Mahatma Gandhi National Rural Employment Guarantee Act (MGNREGA) is facing a “severe crisis” due to persistent neglect and restrictive measures imposed by the Union Government.

Rally in Patna: Non-farmer bodies to highlight plight of agriculture in Eastern India ahead of march to Parliament

P Sainath By  A  Representative Ahead of the march to Parliament on November 29-30, 2018, organized by over 210 farmer and agricultural worker organisations of the country demanding a 21-day special session of Parliament to deliberate on remedial measures for safeguarding the interest of farm, farmers and agricultural workers, a mass rally been organized for November 23, Gandhi Sangrahalaya (Gandhi Museum), Gandhi Maidan, Patna. Say the organizers, the Eastern region merits special attention, because, while crisis of farmers and agricultural workers in Western, Southern and Northern India has received some attention in the media and central legislature, the plight of those in the Eastern region of the country (Bihar, Jharkhand, West Bengal, Orissa, Chhattisgarh and Eastern UP) has remained on the margins. To be addressed by P Sainath, founder of People’s Archive of Rural India (PARI), a statement issued ahead of the rally says, the Eastern India was the most prosperous regi...

India's health workers have no legal right for their protection, regrets NGO network

Counterview Desk In a letter to Union labour and employment minister Santosh Gangwar, the civil rights group Occupational and Environmental Health Network of India (OEHNI), writing against the backdrop of strike by Bhabha hospital heath care workers, has insisted that they should be given “clear legal right for their protection”.

As 2024 draws nearer, threatening signs appear of more destructive wars

By Bharat Dogra  The four years from 2020 to 2023 have been very difficult and high risk years for humanity. In the first two years there was a pandemic and such severe disruption of social and economic life that countless people have not yet recovered from its many-sided adverse impacts. In the next two years there were outbreaks of two very high-risk wars which have worldwide implications including escalation into much wider conflicts. In addition there were highly threatening signs of increasing possibility of other very destructive wars. As the year 2023 appears to be headed for ending on a very grim note, there are apprehensions about what the next year 2024 may bring, and there are several kinds of fears. However to come back to the year 2020 first, the pandemic harmed and threatened a very large number of people. No less harmful was the fear epidemic, the epidemic of increasing mental stress and the cruel disruption of the life and livelihoods particularly among the weaker s...

Targeted eviction of Bengali-speaking Muslims across Assam districts alleged

By A Representative   A delegation led by prominent academic and civil rights leader Sandeep Pandey  visited three districts in Assam—Goalpara, Dhubri, and Lakhimpur—between 2 and 4 September 2025 to meet families affected by recent demolitions and evictions. The delegation reported widespread displacement of Bengali-speaking Muslim communities, many of whom possess valid citizenship documents including Aadhaar, voter ID, ration cards, PAN cards, and NRC certification.