Gas 'dreams': Failure to get eco-clearance for submarine pipeline costs Gujarat PSU another Rs 760 crore

By A Representative
Failure to get forest and environmental clearance for laying down Rs 826 crore submarine pipeline to tap the gas found off Andhra Pradesh coast has cost former bluechip public sector undertaking (PSU), Gujarat State Petroleum Corporation (GSPC), dear. Latest information available from an internal note has suggested that the GSPC will have to shell out a total of around another US dollars 123.66 million as “standby” or “idle” charges to Punj Lloyd Ltd (PLL), the top multinational contractors who were hired in an international bid, to lay down the submarine pipeline in 2011.
The note, which is in possession of Counterview, said that the total amount would have to be paid “expeditiously”, as the contractors are unable to continue their work because of the failure of the GSPC to get necessary clearances on time, as required by the terms of agreement. “PLL has already submitted communication indicating their standby claim. Early resolution of the issue is necessary to preempt any further claims on account of standby”, the note, put up before a recent board meeting of the GSPC, said. Sources added, failure to get necessary clearances has delayed the completion of the project -- scheduled to end in April 2013 -- by at least a year.
Already, the note says, the GSPC has paid PLL an amount of 71.25 million dollars (or Rs 440 crore). However, insiders said, as the money was disbursed without approval of the GSPC board, there was considerable commotion in the Gujarat bureaucratic circles. “Hence, GSPC managing director Tapan Ray decided to approach the GSPC board for getting an approval for the rest of the amount, which comes to around Rs 44.41 million dollars. The board, which met recently, was “undecided” on the matter, and asked a committee under retired IAS bureaucrat MM Shrivastav to look into the matter and decide on the matter.
The note asks the GSPC board to pay up at least 15 million dollars of the amount still a final decision is made. It says, it should be an “interim measure” till the “final settlement is arrived at”. In the meanwhile, the necessary clearances would be taken. Arguing in favour of the payment, the note said, payment to the contracts is “necessary” because 72 per cent of the work in tapping gas from the Deendayal (West) field off Andhra coast is already over, and gas’ commercial production is pending completion of the submarine project. It has expressed the apprehension, at stake is 2.2 billion dollars investment in tapping gas.
Arguing that the “submarine pipeline is the only interconnection” between the GSPC’s Deendayal fields and the onshore facilities, which would refine the gas and send them into the national grid, the note say, “rescinding the contract at this stage” would imply a new tender would have “delay” the commercial production by another 9-12 months to float. “Nature of the work calls for international competitive bidding”, it points out, adding, there always apprehension that “sufficient offers may not come”. Further, it adds, “dispute resolution with PLL” may prove to be “messy, time consuming and costly.”
The GSPC also expresses the apprehension that the overall cost of maintaining the infrastructure set up by the GSPC for commercial production of gas may go up drastically to 300 million dollars per annum. This includes the “additional burden of fixed cost of already installed capacities, interest payment on borrowed capital, operation and maintenance cost” and so on. On the other hand, “assistance to PLL to mobilize resources would facilitate completion of pipeline project by March 2014.”
The GSPC's Rs 760 crore blow came close on the heels of its formal decision to withdraw from its most important overseas adventure – Egypt. The decision was taken as it was proving to be a very costly affair. Deeply under debt of Rs 8,000 crore, the exploration in Egypt would have cost the GSPC another Rs 5,000, with no surety about possibility of getting gas or oil. It was the first major step to bring out GSPC from the financial mess it is in right now.
Interestingly, the GSPC not just failed to get environmental and coastal regulatory zone (CRZ) clearance for the submarine pipeline but also its onshore gas terminal, a 20 MW captive power plant, 20 underground gas pipelines along with optical fibre cable (OFC), and 10 inches effluent disposal pipeline -- of which it badly needed for commercial production of the gas it struck several years ago. Some of these facilities were to pass through CRZ area of Yanam-Puducherry along the Andhra Pradesh coast. 
It simultaneously failed to get clearance for its offshore process-cum-living quarter platform in at the Deendayal block in the KG Basin in Andhra sea, where the top PSU had claimed in 2005 to have found 20 trillion cubic metres (tcf) of gas -- a claim which has been quashed, as total gas available is just 2 tcf, of which one third is recoverable.
In May last year, the environmental appraisal committee (EAC) had asked the GSPC to “defer” construction commercial facilities until certain conditions were fulfilled. It refused to give blanket CRZ clearance for laying down underground gas pipeline, optical fibre cable (OFC), an effluent disposal pipeline, and process-cum-living quarter platform and captive power plant – all of which would require he CRZ clearance, as these facilities are to be part of the Yanam-Puducherry coastal region. The GSPC wanted all these to be cleared together but the EAC ruled against it, asking the GSPC to make separate applications.
The EAC wanted the GSPC to submit: (1) details of the critical environmental issues identified during laying of pipeline, (2) environment clearance for enhancement of captive power plant, under consideration of environmental appraisal committee (EAC) of the thermal committee, which has also sought examining the requirement of wildlife clearance in view of Coringa Sanctuary located in 2.5 km distance, and (3) the plan of the pipeline to pass through the mangroves. Based on these observations, it recommended to defer the proposal.

Comments

TRENDING

The soundtrack of resistance: How 'Sada Sada Ya Nabi' is fueling the Iran war

​ By Syed Ali Mujtaba*  ​The Persian track “ Sada Sada Ya Nabi ye ” by Hossein Sotoodeh has taken the world by storm. This viral media has cut across linguistic barriers to achieve cult status, reaching over 10 million views. The electrifying music and passionate rendition by the Iranian singer have resonated across the globe, particularly as the high-intensity military conflict involving Iran entered its second month in March 2026.

Kolkata dialogue flags policy and finance deficit in wetland sustainability

By A Representative   Wetlands were the focus of India–Germany climate talks in Kolkata, where experts from government, business, and civil society stressed both their ecological importance and the urgent need for stronger conservation frameworks. 

Beyond Lata: How Asha Bhosle redefined the female voice with her underrated versatility

By Vidya Bhushan Rawat*  The news of iconic Asha Bhosle’s ‘untimely’ demise has shocked music lovers across the country. Asha Tai was 92 years young. Normally, people celebrate a passing at this age, but Asha Bhosle—much like another legend, Dev Anand—never made us feel she was growing old. She was perhaps the most versatile artist in Bombay cinema. Hailing from a family devoted to music, Asha’s journey to success and fame was not easy. Her elder sister, Lata Mangeshkar, had already become the voice of women in cinema, and most contemporaries like Shamshad Begum, Suraiya, and Noor Jehan had slowly faded into oblivion. Frankly, there was no second or third to Lata Mangeshkar; she became the first—and perhaps the only—choice for music directors and all those who mattered in filmmaking. Asha started her musical journey at age 10 with a Marathi film, but her first break in Hindustani cinema came with the film "Chunariya" (1948). Though she was not the first choice of ...

Maoist activity in India: Weakening structures, 'shifts' in leadership, strategy and ideology

By Harsh Thakor*  Recent statements by government representatives have suggested that Maoism in India has been effectively eliminated, citing the weakening of central leadership and intensified security operations. These claims follow sustained counterinsurgency efforts across key regions, including central and eastern India. However, available information from security agencies and independent observers indicates that while the organizational structure of the CPI (Maoist) has been significantly disrupted, elements of the movement remain active. Reports acknowledge the continued presence of cadres in certain forested regions such as Bastar and parts of Dandakaranya, alongside smaller, decentralized units adapting their operational strategies.

From Manesar to Noida: Workers take to streets for bread, media looks away

By Sunil Kumar*   Across several states in India, a workers’ movement is gathering momentum. This is not a movement born of luxury or ambition, nor a demand for power-sharing within the state. At its core lies a stark and basic plea: the right to survive with dignity—adequate food, and wages sufficient to afford it.

Midnight weeping: The sociology of tragic vision in Badri Narayan’s poetry

By Ravi Ranjan*  Badri Narayan, a distinguished Hindi poet and social scientist, occupies a unique position in contemporary Indian intellectual life by bridging the worlds of creative literature and critical social inquiry. His poetic journey began significantly with the 1993 collection 'Saca Sune Hue Kaï Dina Hue' (Truth Heard Many Days Ago). As a social historian and cultural anthropologist, Narayan pioneered a methodological shift away from elite archives toward the oral traditions and folk myths of marginalized communities. He eventually legitimized "folk-ethnography" as a rigorous academic discipline during his tenure as Director of the G.B. Pant Social Science Institute.  

Why link women’s reservation to delimitation? The unspoken political calculus

By Vikas Meshram*  April 16, 2026, is likely to be recorded as a special day in the history of Indian democracy. In a three-day special session of Parliament, the central government is set to introduce a comprehensive package of three historic bills: the Constitution (131st Amendment) Bill, 2026; the Delimitation Bill, 2026; and the Union Territories Laws (Amendment) Bill, 2026. The stated purpose of all three is the same: to implement the Nari Shakti Vandan Adhiniyam (106th Constitutional Amendment) passed in 2023. However, the political intent concealed behind these measures — and their impact on the federal balance — is far more profound. It is absolutely essential to understand this.

Catholic union opposes FCRA amendments, warns of threat to Church institutions

By A Representative   The All India Catholic Union (AICU) has raised serious concerns over what it describes as growing threats to religious freedom, minority rights, and constitutional safeguards in India, warning that recent policy and legislative trends could undermine the country’s secular and federal framework.

'It's power grab, not reform': Uttarakhand hills fear marginalization under new delimitation

By Vidya Bhushan Rawat*  The proposed delimitation bill, coupled with the women’s reservation bill, is a calculated attempt to divert attention during state elections while laying the groundwork for long-term power consolidation through a north Indian hegemony. India’s constitution-making process was arduous, but it was guided by leaders deeply committed to unity and integrity. They ensured no community felt betrayed, and the foundation of modern India was laid on inclusivity. Any attempt to alter this balance must be approached with caution and respect for that legacy.