Minutes of CRZ clearance to Mithi Virdi N-plant silent on dangers to Alang Yard

Paryavaran Suraksha Samiti’s (PSS’) senior activists Krishnakant, Rohit Prajapati and Swati Desai have written a letter to Anil Razdan, chairman, Expert Appraisal Committee for Projects related to Infrastructure Development, Ministry of Environment, Forests and Climate Change, New Delhi, opposing the recent CRZ clearance recommended for the proposed Mithi Virdi Nuclear Power Plant at village Mithi Virdi, Dist Bhavnagar, Gujarat. Copy of the letter:

In March 2015 we read in the Indian Express that the proposed Mithi Virdi nuclear power plant had received the coastal regulatory zone (CRZ) clearance from the EAC of the Ministry of Environment, Forests and Climate Change.
We thereafter became aware of the minutes of the 144th meeting of Expert Appraisal Committee (EAC) for Projects related to Infrastructure Development, Coastal Regulation Zone, Building/Construction and Miscellaneous projects held on January 28-30, 2015 in which the broad, vague grounds for giving CRZ clearance to the proposed Mithi Virdi Nuclear Power plant are mentioned. It appears that the CRZ clearance is now rushed through all decision-making bodies, including the Ministry of Environment, Forests and Climate Change, defeating the very purpose of setting up the CRZ norms, meant to protect the environment.
We oppose the CRZ recommendation on the following grounds:
The minutes give no clarity on the composition of the EAC, its members and most importantly have no mention of its findings even in the annexure.
The CRZ rules mandate that EAC should have visited the site and also consulted the local villagers who stand to be affected by the proposed project, which according to the local villagers as well as the local Panchayats never happened. This indicates that the EAC either never visited the site, or if it did, did not consult the local population and Panchayats and if that is the case then the visit should be considered unconstitutional and illegal.
The EAC studies and its discussion are not mentioned in the minutes of the 144th meeting at all, so neither the local villagers nor public have any knowledge as to what basis the EAC recommends the CRZ clearance. This prevents the people from forming an informed decision to support, contest or critique the CRZ clearance, which is in contradiction to the Constitution of India.
The EAC has indicated that a “groyne-based channel type seawater intake system has been proposed with the sump at the shore”. However, a detailed study considering the impact of the groyne on the long-shore drift of sediments and the likely pattern of erosion/accretion that may result has yet to be conducted, without which CRZ clearance should not be granted.
The mechanism by which the Nuclear Power Corporation of India Ltd (NPCIL) will unload construction materials and heavy equipment for the proposed project is conspicuously absent from the proposal. The EAC has failed to inquire about how the company plans to go about sea-surface transport in the absence of a provision for the construction of a jetty.
The EAC minutes are silent about the potential danger posed to the coastal environment by the project’s proximity to Alang Sosiya Ship Breaking Yard. The Ship Breaking Yard, which has been functioning since 1983 and stretches over 10 km, is in the immediate vicinity of the proposed Mithi Virdi Power Plant. In fact, parts of the yard fall within the Village Jaspara, one of the villages land to be acquired by the NPCIL. The entire coastal area adjacent to the Yard is contaminated with solid, liquid, gaseous and hazardous waste including paint chips, asbestos, oily sludge, used/spent oil, toxic chemicals, radioactive waste, PCBs and ACMs. In the Writ Petition (C) No. 657 of 1995 the Supreme Court established a High Powered Committee under the Chairmanship of Prof. M. G. K. Menon which averted that “at present there is no single point access to the yards and. therefore, hazardous waste is being illegally dumped at various places.”
It put forth the following recommendations to rectify the environmental and occupational health crisis at Alang:
Before a ship arrives at port, it should have proper consent from the authority concerned or the State Maritime Board, stating that it does not contain any hazardous waste or radioactive sub-stances. AERB should be consulted in the matter in appropriate cases.
The ship should be properly decontaminated by the ship owner prior to the breaking. This should be ensured by SPCBs.
Waste generated by the ship-breaking process should be classified into hazardous and non-hazardous categories, and their quantity should be made known to the authority concerned or the State Maritime Board.
Disposal of waste material viz, oil, cotton, dead cargo of inorganic material like hy-drated/solidified elements, thermocol pieces, glass wool, rubber, broken tiles, etc. should be done in a proper manner, utilising technologies that meet the criteria of an effective destruction efficiently of 99.9 per cent, with no generation of persistent organic pollutants, and complete containment of all gaseous, liquid and solid residues for analysis and, if needed, reprocessing. Such disposed of material should be kept at a specified place earmarked for this purpose. Special care must be taken in the handling of asbestos wastes, and total quantities of such waste should be made known to the authorities concerned. The Gujarat Pollution Control Board should authorise appropriate final disposal of asbestos waste.
The ship-breaking industries should be given authorization under Rule 5 of the HW Rules, 2003, only if they have provisions for disposal of the waste in environmentally sound manner. All authorisations should be renewed only if an industry has facilities for disposal of waste in environmentally sound manner.
The State Maritime Board should insist that all quantities of waste oil, sludge and other similar mineral oils and paint chips are carefully removed from the ship and taken immediately to areas outside the beach, for safe disposal.
There should be immediate ban of burning of any material whether hazardous or non-hazardous on the beach.
The State Pollution Control Board (of Gujarat and other coastal States where this ship-breaking activity is done) be directed to close all units which are not authorised under the HW Rules.
That the plots where no activities are being currently conducted should not be allowed to commence any fresh ship-breaking activity unless they have necessary authorisation.
The Gujarat PCBs should ensure continuous monitoring of ambient air and noise level as per the standards fixed. The Gujarat PCBs be further directed to install proper equipment and infrastructure for analysis to enable them to conduct first-level inspection of hazardous material, radioactive substances (wherever applicable). AERB shall be consulted in such cases.
The Gujarat SPCB should ensure compliance with the new Gujarat Maritime Board (Prevention of Fire and Accidents for Safety and Welfare of Workers and Protection of Environment during Ship breaking Activities) Regulations, 2000, by the Gujarat Maritime Board and should submit a compliance report to the Court within one year of the coming into force of the said Regulations.
The notification issued by GMB in 2001 on gas free for hot work, should be made mandatory and no ship should be given a beaching permission unless this certificate is shown. Any explosion irrespective of the possession of certification should be dealt with sternly and the licence of the plot-holder should be cancelled and the Explosives Inspector should be prosecuted accordingly for giving the false certificate.
A complete inventory of hazardous waste on board of ship should be made mandatory for the ship-owner. And no breaking permission should be granted without such an inventory. This inventory should also be submitted by GMB to SPCBs concerned to ensure safe disposal of hazardous and toxic waste.
The Gujarat Maritime Board and Gujarat SPCB officers should visit sites at regular intervals so that the plot-owners know that these institutions are serious about improvement in operational standards. An inter-ministerial Committee comprising Ministry of Surface Transport, Ministry of Steel, Ministry of Labour and Ministry of Environment should be constituted with the involvement of labour and environment organisations and representatives of the ship-breaking industry.
SPCBs along with the State Maritime Boards should prepare landfill sites and incinerators as per CPCB guidelines and only after prior approval of CPCB. This action should be taken in a time-bound manner. The maximum time allowed should be one year.
At the international level, India should participate in international meetings on ship-breaking at the level of the International Maritime Organisation and the Basel Convention’s Technical Working Group with a clear mandate for the decontamination of ships of their hazardous substances such as asbestos, waste oil, gas and PCBs, prior to export to India for breaking. Participation should include from Central and State level.
The continuation or expansion of the Alang ship-breaking operations should be permitted subject to compliance with the above recommendations by the plot-holders.
The above conditions also apply to other ship-breaking activities in other coastal States.
The SC Order on Alang can be accessed here.

Rather than taking into consideration the present state of pollution at the Alang Sosiya Ship Breaking Yard-affected coastal area, the EAC Minutes merely state that there “is no intensive fishing activity in the proposed site”. It has studied neither how the proposed project will affect the rehabilitation effort mandated by the Supreme Court Monitoring Committee, nor has it properly examined the comprehensive impact on the fishing patterns and bio-diversity of this once-pristine coastal area.
On the Eastern side of the project site is the Golden Corridor, where industrial development and urbanisation has led to an alarming pollution level. The comprehensive impact of the Mithi Virdi Project on an already critically polluted coastal area with high ecological value has not been taken into account by the EAC in its recommendation for CRZ clearance.
The Village Mithi Virdi where the project is to be located inherits its name which means sweet water from its plethora of fresh ground water despite its proximity to the coast. In all, 152 villages with a population of more than 200,000 in 30 km radius of the proposed nuclear power plant will be “adversely affected” by the project. The main occupation of the villagers is agriculture. The rich alluvial soil here supports crops like groundnut, wheat, bajra, and cotton, and fruits like mango, chikoos and coconut. The area also grows and supplies vegetables like onion, brinjal, gourd, tomatoes, and drumsticks on a regular basis to other parts of the state, and the climate and the soil are suitable for cashew nuts. This rich agriculture is threatened by the proposed nuclear plant. The backbone of the local agrarian economy is its extremely fertile land which supports the growth of three crops, annually. The extraction of fresh water by the proposed plant and its impact on the local agriculture-dependent economy has not been mentioned in the consideration for CRZ.
Since the MoEF & CC too is proceeding in giving the CRZ clearance in a manner which indicates that its basic mandate of protecting environment is being diluted and mortgaged to protect and further vested interests, we demand:
That the EAC immediately withdraw its recommendation for the CRZ Clearance, as it has failed to take into consideration crucial components related to the coastal environment at Mithi Virdi area.
That EAC composition detail, its study for the proposed Mithi Virdi Nuclear Power Plant and all the documents, including the Main Application of NPCIL for the CRZ clearance, that detail the reasons for which it recommends CRZ clearance be made public immediately, with a copy given to the residents and local Panchayat body.
That the citizens, particularly the residents and local bodies at Mithi Virdi area be given at least a month’s time to register their response to the CRZ clearance recommendation as mandated by the law.

The above points are merely a quick response to the cursory information provided in the EAC Minutes and do not constitute a comprehensive objection to the CRZ Clearance given to the proposed Mithi Virdi Project. We can only prepare a point-wise response after the Ministry provides us with all of the above-mentioned detailed project documents.

Comments

TRENDING

The silencing of conscience: Ideological attacks on India’s judiciary and free thought

By Sunil Kumar*  “Volunteers will pick up sticks to remove every obstacle that comes in the way of Sanatan and saints’ work.” — RSS Chief Mohan Bhagwat (November 6, 2024, Chitrakoot) Eleven months later, on October 6, 2025, a man who threw a shoe inside the Supreme Court shouted, “India will not tolerate insults to Sanatan.” This incident was not an isolated act but a continuation of a pattern seen over the past decade—attacks on intellectuals, writers, activists, and journalists, sometimes in the name of institutions, sometimes by individual actors or organizations.

'Violation of Apex Court order': Delhi authorities blamed for dog-bite incidents at JLN Stadium

By A Representative   People for Animals (PFA), led by Ms. Ambika Shukla, has held the Municipal Corporation of Delhi (MCD) responsible for the recent dog-bite incidents at Jawaharlal Nehru Stadium, accusing it of violating Supreme Court directions regarding community dogs. The organisation’s on-ground fact-finding mission met stadium authorities and the two affected coaches to verify details surrounding the incidents, both of which occurred on October 3.

N-power plant at Mithi Virdi: CRZ nod is arbitrary, without jurisdiction

By Krishnakant* A case-appeal has been filed against the order of the Ministry of Environment, Forest and Climate Change (MoEF&CC) and others granting CRZ clearance for establishment of intake and outfall facility for proposed 6000 MWe Nuclear Power Plant at Mithi Virdi, District Bhavnagar, Gujarat by Nuclear Power Corporation of India Limited (NPCIL) vide order in F 11-23 /2014-IA- III dated March 3, 2015. The case-appeal in the National Green Tribunal at Western Bench at Pune is filed by Shaktisinh Gohil, Sarpanch of Jasapara; Hajabhai Dihora of Mithi Virdi; Jagrutiben Gohil of Jasapara; Krishnakant and Rohit Prajapati activist of the Paryavaran Suraksha Samiti. The National Green Tribunal (NGT) has issued a notice to the MoEF&CC, Gujarat Pollution Control Board, Gujarat Coastal Zone Management Authority, Atomic Energy Regulatory Board and Nuclear Power Corporation of India Limited (NPCIL) and case is kept for hearing on August 20, 2015. Appeal No. 23 of 2015 (WZ) is filed, a...

History, culture and literature of Fatehpur, UP, from where Maulana Hasrat Mohani hailed

By Vidya Bhushan Rawat*  Maulana Hasrat Mohani was a member of the Constituent Assembly and an extremely important leader of our freedom movement. Born in Unnao district of Uttar Pradesh, Hasrat Mohani's relationship with nearby district of Fatehpur is interesting and not explored much by biographers and historians. Dr Mohammad Ismail Azad Fatehpuri has written a book on Maulana Hasrat Mohani and Fatehpur. The book is in Urdu.  He has just come out with another important book, 'Hindi kee Pratham Rachna: Chandayan' authored by Mulla Daud Dalmai.' During my recent visit to Fatehpur town, I had an opportunity to meet Dr Mohammad Ismail Azad Fatehpuri and recorded a conversation with him on issues of history, culture and literature of Fatehpur. Sharing this conversation here with you. Kindly click this link. --- *Human rights defender. Facebook https://www.facebook.com/vbrawat , X @freetohumanity, Skype @vbrawat

New RTI draft rules inspired by citizen-unfriendly, overtly bureaucratic approach

By Venkatesh Nayak* The Department of Personnel and Training , Government of India has invited comments on a new set of Draft Rules (available in English only) to implement The Right to Information Act, 2005 . The RTI Rules were last amended in 2012 after a long period of consultation with various stakeholders. The Government’s move to put the draft RTI Rules out for people’s comments and suggestions for change is a welcome continuation of the tradition of public consultation. Positive aspects of the Draft RTI Rules While 60-65% of the Draft RTI Rules repeat the content of the 2012 RTI Rules, some new aspects deserve appreciation as they clarify the manner of implementation of key provisions of the RTI Act. These are: Provisions for dealing with non-compliance of the orders and directives of the Central Information Commission (CIC) by public authorities- this was missing in the 2012 RTI Rules. Non-compliance is increasingly becoming a major problem- two of my non-compliance cases are...

Citizens’ group to recall Justice Chagla’s alarm as India faces ‘undeclared' Emergency

By A Representative  In a move likely to raise eyebrows among the powers-that-be, a voluntary organisation founded during the “dark days” of the Indira Gandhi -imposed Emergency has announced that it will hold a public conference in Ahmedabad to highlight what its office-bearers call today’s “undeclared Emergency.”

Celebrating 125 yr old legacy of healthcare work of missionaries

Vilas Shende, director, Mure Memorial Hospital By Moin Qazi* Central India has been one of the most fertile belts for several unique experiments undertaken by missionaries in the field of education and healthcare. The result is a network of several well-known schools, colleges and hospitals that have woven themselves into the social landscape of the region. They have also become a byword for quality and affordable services delivered to all sections of the society. These institutions are characterised by committed and compassionate staff driven by the selfless pursuit of improving the well-being of society. This is the reason why the region has nursed and nurtured so many eminent people who occupy high positions in varied fields across the country as well as beyond. One of the fruits of this legacy is a more than century old iconic hospital that nestles in the heart of Nagpur city. Named as Mure Memorial Hospital after a British warrior who lost his life in a war while defending his cou...

Epic war against caste system is constitutional responsibility of elected government

Edited by well-known Gujarat Dalit rights leader Martin Macwan, the book, “Bhed-Bharat: An Account of Injustice and Atrocities on Dalits and Adivasis (2014-18)” (available in English and Gujarati*) is a selection of news articles on Dalits and Adivasis (2014-2018) published by Dalit Shakti Prakashan, Ahmedabad. Preface to the book, in which Macwan seeks to answer key questions on why the book is needed today: *** The thought of compiling a book on atrocities on Dalits and thus present an overall Indian picture had occurred to me a long time ago. Absence of such a comprehensive picture is a major reason for a weak social and political consciousness among Dalits as well as non-Dalits. But gradually the idea took a different form. I found that lay readers don’t understand numbers and don’t like to read well-researched articles. The best way to reach out to them was storytelling. As I started writing in Gujarati and sharing the idea of the book with my friends, it occurred to me that while...

From seed to soil: How transnational control is endangering food sovereignty

By Bharat Dogra  In recent decades, the world has witnessed a steady erosion of plant diversity in many countries, particularly those in the Global South that were once richly endowed with natural plant wealth. Much of this diversity has been removed from its original ecological and cultural contexts and transferred into gene banks concentrated in developed nations. While conservation of genetic resources is important, the problem arises when access to these collections becomes unequal, particularly when they fall under the control of transnational corporations.