Diminishing returns: Hydro projects contribute less than 10% of India's power generation

Counterview Desk 

Pointing out that India’s hydro generation remains around 10% for the last six years, the advocacy group South Asia Network on Dams, Rivers and People (SANDRP) has said that power generation from hydropower projects continues to show diminishing returns, as has been the story close to three decades now.
Yet, says SANDRP in a note, the Government of India continues to push large hydro by announcing a slew of additional subsidies for hydropower projects, more for political economy reason. In fact, attempts are being made to flog unviable hydropower projects with various kind of manipulations, illegalities and violations, it adds.

Text:

In last six years, from 2016-17 to 2021-22, India’s large hydropower projects (projects above 25 MW installed capacity) have contributed just around 10% of the total power generation, going as low as 9.68% in 2017-18. In fact, in three of these six years, large hydro contributed less than 10% and recovering only marginally in the rest, thanks to surplus monsoon.
Projects with installed capacity above 25 MW as projects with installed capacity below 25MW are called small hydro.
The South West Monsoon Rainfall was 10.46 % above normal in 2018-19, 8.74% above normal in 2019-20, 0.7% above normal in 2020-21 and 6.8% above normal in 2021-22. The October rainfall has also been generally above normal in recent years. These have helped the hydropower generation go marginally up above 10% in last three years.
In 2016-17, for the first time in independent India’s history, power generation from large hydropower projects in India fell below 10% of total electricity generation and remained below 10% for the next three years: 2016-17, 2017-18 and 2018-19. This analysis is based on actual generation (measured as million or billion Units) as reported by Central Electricity Authority (CEA) and not installed capacity (measured in Mega Watts).
One unit equals one Kilowatt hour, which is the power generated when 1 KW of installed capacity runs for one hour. The units are actually consumable and provide the correct picture of power available for consumption.
For the latest year ending on March 31, 2022, the power generation from large hydropower projects (CEA only reports large hydro generation) in 2021-22 was 151.63 BU, when total power generation in India (including renewables generation of 181.37 BU, but excluding Bhutan imports of 7.49 BU) was 1491.86 BU, hence hydropower generation in 2021-22 was 10.86% of total electricity generation.
The hydropower generation proportion to total electricity generation was 9.90% in 2016-17; 9.68% in 2017-18 and 9.84% in 2018-19, 11.26% in 2019-20 and 11.62% in 2020-22. Reduced overall generation due to Covid Pandemic was also a reason for increased proportion of hydropower generation to total generation in 2019-20, 2020-21 and 2021-22.
Diminishing returns, Declining proportion However, power generation from hydropower projects continues to show diminishing returns, as has been the story close to three decades now, see the trend-line in graph below where we have plotted MU electricity generated per MW hydro installed capacity over the years since 1993-94.
Similarly, the proportion of hydropower in overall electricity generation continues to show declining proportion, slight increase in last three years notwithstanding. Some of the major reasons for this declining proportion of hydropower generation are: diminishing generation of existing hydropower projects in India (see the graph above) and large hydropower projects becoming more and more unviable.
Even NHPC chief agrees they are unviable. As the then power minister of India stated in the Parliament, at least 15 large hydro projects (NHPC chief says 40 HEPs need bailout package, see below) with capacity close to 6000 MW remains stranded in India.
A direct fall out of this could be seen in the capacity addition trends, see the chart below, where we can see the flattening of the graph in latest years. The capacity addition that was 7028 MW in 1999-2004 and 5371 MW in 2004-09 has fallen to 3646 during 2009-2014 and 4875 MW during 2014-19. In the latest five years (2017-22) capacity addition has been 2242 MW.

The government continues to push large hydro

On March 8, 2019, on the eve of India’s last general elections, the Union Government declared a slew of additional subsidies for hydropower projects, but this seemed more for political economy reason, as also suggested by the timing of the announcement, just before the model code of conduct came into force on March 11, 2019. There are many other attempts being made to flog the unviable hydropower projects with various kind of manipulations, illegalities and violations. Just a couple of instances are narrated below:
  • State-owned hydro power giant NHPC signed a pact with Cement Corporation of India (CCI) for meeting cement requirements of the Dibang Project. This happened in 2020 when CCI coming under the Ministry of Heavy Industries and Prakash Javdekar happened to be both the minister of heavy industries and Environment and Forests. And it is MoEF that issues the forest clearance! Earlier on July 17, 2020, the Cabinet Committee on Economic Affairs, chaired by the Prime Minister, approved Rs 1,600 crore for “pre-investment activities and various clearances” of the project.
  • Jindal Power Ltd Chief Executive Officer Bharat Rohra said, generation glut in hydropower project had made an estimated $3.3 billion facility a risky bet for the company to handle: “In the current situation, the project doesn’t look like an attractive investment in view of the huge investment. Further, it is a large project and we feel we’ll struggle to find long-term buyers for the entire capacity but policy support from the government can make the project viable and draw investors.”
Amendment to Electricity Act of 2003, suggested among other changes hydro purchasing obligation norms on the lines of renewable purchasing obligation norms. But this too has not helped. The Discoms, suffering from severe financial troubles are facing the additional burdens in the name of hydro purchasing obligation norms.
Union Power Minister RK Singh said, the power ministry is pushing state-run majors under its wings to take over 29 hydel projects with combined capacity of 30 000 MW entailing estimated investments of up to Rs 2.7 lakh crore (much more in reality) that are languishing with private developers.
None of these are going to help the cause of large hydro projects. The government needs to understand that even these additional subsidies for the already over subsidized hydropower sector is not going to help make them viable. When solar and wind power is available at price below Rs 3 per unit, why is there attempt to push large hydro whose cost is universally over Rs 5-6 per unit or more. Why should the government spend public money through PSUs to push such unviable projects?
It may be noted here that in recent years, the big hydro projects are facing increasing accidents and disasters and this is only likely to increasing with changing climate.
In conclusion India needs to pay attention to optimizing generation from existing hydro and explore the possibilities of installing hydro projects at 97% of India’s existing large dams where there is no hydro component.
We also need to first manage our peak hours’ power demand and optimize generation from existing hydro during peak hours, only after assessing and addressing the social and environmental impacts of peaking hour power generation from large hydro projects.
Else we will be destroying more rivers and their biodiversity and livelihoods of people dependent on such rivers, while throwing more money into the pockets of consultants, contractors, equipment suppliers, cement companies and other vested interests.
The Ministry of Environment and Forests and its Expert Appraisal Committee on River Valley Projects too needs take this opportunity to improve their pathetic environmental governance rather than keep pushing more clearances for projects through corruption, manipulations and violations.

Comments

TRENDING

Budget for 2018-19: Ahmedabad authorities "regularly" under-spend allocation

By Mahender Jethmalani* The Ahmedabad Municipal Corporation’s (AMC's) General Body (Municipal Board) recently passed the AMC’s annual budget estimates of Rs 6,990 crore for 2018-19. AMC’s revenue expenditure for the next financial year is Rs 3,500 crore and development budget (capital budget) is Rs 3,490 crore.

Urgent need to study cause of large number of natural deaths in Gulf countries

By Venkatesh Nayak* According to data tabled in Parliament in April 2018, there are 87.76 lakh (8.77 million) Indians in six Gulf countries, namely Bahrain, Kuwait, Oman, Qatar, Saudi Arabia and the United Arab Emirates (UAE). While replying to an Unstarred Question (#6091) raised in the Lok Sabha, the Union Minister of State for External Affairs said, during the first half of this financial year alone (between April-September 2018), blue-collared Indian workers in these countries had remitted USD 33.47 Billion back home. Not much is known about the human cost of such earnings which swell up the country’s forex reserves quietly. My recent RTI intervention and research of proceedings in Parliament has revealed that between 2012 and mid-2018 more than 24,570 Indian Workers died in these Gulf countries. This works out to an average of more than 10 deaths per day. For every US$ 1 Billion they remitted to India during the same period there were at least 117 deaths of Indian Workers in Gulf ...

History, culture and literature of Fatehpur, UP, from where Maulana Hasrat Mohani hailed

By Vidya Bhushan Rawat*  Maulana Hasrat Mohani was a member of the Constituent Assembly and an extremely important leader of our freedom movement. Born in Unnao district of Uttar Pradesh, Hasrat Mohani's relationship with nearby district of Fatehpur is interesting and not explored much by biographers and historians. Dr Mohammad Ismail Azad Fatehpuri has written a book on Maulana Hasrat Mohani and Fatehpur. The book is in Urdu.  He has just come out with another important book, 'Hindi kee Pratham Rachna: Chandayan' authored by Mulla Daud Dalmai.' During my recent visit to Fatehpur town, I had an opportunity to meet Dr Mohammad Ismail Azad Fatehpuri and recorded a conversation with him on issues of history, culture and literature of Fatehpur. Sharing this conversation here with you. Kindly click this link. --- *Human rights defender. Facebook https://www.facebook.com/vbrawat , X @freetohumanity, Skype @vbrawat

New RTI draft rules inspired by citizen-unfriendly, overtly bureaucratic approach

By Venkatesh Nayak* The Department of Personnel and Training , Government of India has invited comments on a new set of Draft Rules (available in English only) to implement The Right to Information Act, 2005 . The RTI Rules were last amended in 2012 after a long period of consultation with various stakeholders. The Government’s move to put the draft RTI Rules out for people’s comments and suggestions for change is a welcome continuation of the tradition of public consultation. Positive aspects of the Draft RTI Rules While 60-65% of the Draft RTI Rules repeat the content of the 2012 RTI Rules, some new aspects deserve appreciation as they clarify the manner of implementation of key provisions of the RTI Act. These are: Provisions for dealing with non-compliance of the orders and directives of the Central Information Commission (CIC) by public authorities- this was missing in the 2012 RTI Rules. Non-compliance is increasingly becoming a major problem- two of my non-compliance cases are...

Sardar Patel was on Nathuram Godse's hit list: Noted Marathi writer Sadanand More

Sadanand More (right) By  A  Representative In a surprise revelation, well-known Gujarati journalist Hari Desai has claimed that Nathuram Godse did not just kill Mahatma Gandhi, but also intended to kill Sardar Vallabhbhai Patel. Citing a voluminous book authored by Sadanand More, “Lokmanya to Mahatma”, Volume II, translated from Marathi into English last year, Desai says, nowadays, there is a lot of talk about conspiracy to kill Gandhi, Netaji Subhas Chandra Bose, and Shyama Prasad Mukherjee, but little is known about how the Sardar was also targeted.

Stands 'exposed': Cavalier attitude towards rushed construction of Char Dham project

By Bharat Dogra*  The nation heaved a big sigh of relief when the 41 workers trapped in the under-construction Silkyara-Barkot tunnel (Uttarkashi district of Uttarakhand) were finally rescued on November 28 after a 17-day rescue effort. All those involved in the rescue effort deserve a big thanks of the entire country. The government deserves appreciation for providing all-round support.

As 2024 draws nearer, threatening signs appear of more destructive wars

By Bharat Dogra  The four years from 2020 to 2023 have been very difficult and high risk years for humanity. In the first two years there was a pandemic and such severe disruption of social and economic life that countless people have not yet recovered from its many-sided adverse impacts. In the next two years there were outbreaks of two very high-risk wars which have worldwide implications including escalation into much wider conflicts. In addition there were highly threatening signs of increasing possibility of other very destructive wars. As the year 2023 appears to be headed for ending on a very grim note, there are apprehensions about what the next year 2024 may bring, and there are several kinds of fears. However to come back to the year 2020 first, the pandemic harmed and threatened a very large number of people. No less harmful was the fear epidemic, the epidemic of increasing mental stress and the cruel disruption of the life and livelihoods particularly among the weaker s...

Warning bells for India: Tribal exploitation by powerful corporate interests may turn into international issue

By Ashok Shrimali* Warning bells are ringing for India. Even as news drops in from Odisha that Adivasi villages, one after another, are rejecting the top UK-based MNC Vedanta's plea for mining, a recent move by two senior scholars Felix Padel and Samarendra Das suggests the way tribals are being exploited in India by powerful international and national business interests may become an international issue. In fact, one has only to count days when things may be taken up at the United Nations level, with India being pushed to the corner. Padel, it may be recalled, is a major British authority on indigenous peoples across the world, with several scholarly books to his credit. 

Call to "enjoy" pilgrimage of Sabarmati beyond Ahmedabad, where river water turns black

Sabarmati at Vautha By A Representative Nagrik Sashaktikaran Manch (NSM), a Gujarat-based civil rights organization, has called upon the state's citizens to join in a "unique yatra" along the river Sabarmati, starting in Ahmedabad and ending off the Gulf of Khambhat, where the river is supposed to merge with the sea. Pointing out that in Hindu culture, rivers are equated with Mother Goddess, NSM convener Jatin Seth says, it will be a "special event of pilgrimage", because, just like Ganga, Sarbarmati possesses "special properties." "Starting at Giaspur, one can see how industries are releasing chemicals in Sabarmati, and you get a Thumbs-Up like colour of the water, and if you drink it, you are sure to be at least affected by cancer, and this way would enable you to book your ticket in the paradise. The river has a special smell, too, emanating from a black cocktail-type colour", says Seth in a statement. A village next to Sabarmati river In...