It is tragic that a 24 year old journalist died on 23rd October of injuries that he sustained while walking on the road and falling into an under construction storm water drain at Ashok Nagar in Chennai, sustaining severe injuries from the protruding iron rods at the site.
This is not the first time that such an accident has taken place due to the under construction storm water drain project in Chennai. Earlier, a bank executive lost her life as a tree fell on her vehicle, where storm water drain work was going on. So many other minor and not so minor accidents have taken place in the last few months in Chennai, most of which have not been reported in the media.
Several technocrats have pointed out that the project has been designed with outdated technology and is unsuitable for the existing conditions in Chennai city.and quality of the implementation is so poor, that the residents have been put to great hardships.
As part of the project, digging of the road has been done to around 5 to 6 feet deep and width of around 4 to 5 feet. The drains have been constructed using steel reinforced cement concrete with two walls on either side with provisions for manhole, chute etc. This has been done in front of several houses leaving little space between the gate of the house and that of the drainage structure.
Experts have expressed shock that the storm water drain has been constructed in such a way that it’s top level is around one foot above the road level.
If there would be rainfall, the rain water would get inside the house, as the top portion of the drainage structure is above the floor level in the house. As a result, it appears that the residents have to spend around Rs.1 lakh to raise the floor level in the compound to the top level of the drainage structure.
Experts point out that in constructing the storm water drain, gradients have to be maintained to enable free flow of water. It appears no measurement has been made properly to ensure the gradient level.
The area around the storm water drainage structure where soil has been removed earlier has been now filled with loose soil, posing a safety hazard for people.
It is shocking to see that the workers, most of whom appear to be unskilled, are carrying out the work and removing the electric cables from the ground carelessly without being provided with the hand gloves, gumboots and safety goggles . Several citizens say that there has been no proper supervision of the work by the authorities and the entire work is left to the contractors who largely employ unskilled workers. In several places, electric cables have been left on the road , exposed to sun and rain.
Experts wonder whether the various technological options and alternate ways for laying the storm water drain have been carefully examined, considering the local conditions in Chennai such as rainfall intensity , periodicity of flooding, extent of flooding, the existing road construction and traffic intensity and density of population in the local area. On the other hand, the same design has been adopted for the entire city , not considering the local conditions. Careful evaluation of these factors are necessary that could have facilitated the least expensive way for building storm water drains, that can be finished in quick time without causing inconvenience and problems for the residents.
It appears that the authorities have chosen the most expensive and time consuming way of laying storm water drain, by digging deep into the soil and using steel reinforced concrete, chute pipe, manhole cover, inlet chambers, retailing wall etc.
Experts say that in a crowded city like Chennai , drainage pipes could have been used for draining the storm water and the pipes can be laid under the ground, instead of the present pattern of ongoing work. 
There are PVC and HDPE pipe options, both of which have become extremely popular in drainage applications in recent years all over the world, thanks to their resistance to collapse and chemical corrosion, flexibility and durability. While PVC pipes are quite easy to install, HDPE is generally the better choice for high pressure systems. Suitable provisions can be made in the pipes for connection, inspection, cleaning etc. from time to time ,as required.
In view of the poor execution of the project, several roads are now in an extremely bad shape and it is unsafe even for walkers in several places , apart from those who drive the two wheelers, three wheelers and four wheelers.
Further, storm water drainage projects are being implemented in areas without adequate study for it’s need.
For example, in Besant Nagar and Kalakshetra area, which is near the seashore, the soil is loose and rain water can easily penetrate into the ground . . Whatever stagnation has occurred in the road in the past in the area has been only due to uneven roads.
Ministers and officials have been claiming that more than 85% of the storm water drainage work has been completed. This does not appear to be so , if one would see the ground conditions in various places in the city.
The disappointment of the public with regard to the design and implementation are clearly evident and Greater Chennai Corporation owes an explanation to the people ,as several hundred crores of rupees have been invested in this project and people have been put to huge sufferings.
The overall public view appears to be that this storm water drainage project would not save Chennai city from water stagnation in any significant way during the forthcoming monsoon.
The consensus view amongst the experts is that for the future students studying subjects related to civil engineering and public works, the design and execution of storm water drainage system presently executed by Greater Chennai Corporation is a case study as to how the future storm water drainage project should not be designed and implemented.
It is necessary that a high level technical committee should be immediately constituted to scrutinize the design of the project and methodology of implementation and the role of the engineers and officials at various levels from top- to bottom in conceiving and implementing this project.
The findings of the enquiry committee will help the Chennai Corporation and authorities by providing guidelines for such future projects.
---
*Trustee, Nandini Voice For The Deprived, Chennai

Comments

TRENDING

From algorithms to exploitation: New report exposes plight of India's gig workers

By Jag Jivan   The recent report, "State of Finance in India Report 2024-25," released by a coalition including the Centre for Financial Accountability, Focus on the Global South, and other organizations, paints a stark picture of India's burgeoning digital economy, particularly highlighting the exploitation faced by gig workers on platform-based services. 

'Condonation of war crimes against women and children’: IPSN on Trump’s Gaza Board

By A Representative   The India-Palestine Solidarity Network (IPSN) has strongly condemned the announcement of a proposed “Board of Peace” for Gaza and Palestine by former US President Donald J. Trump, calling it an initiative that “condones war crimes against children and women” and “rubs salt in Palestinian wounds.”

Gig workers hold online strike on republic day; nationwide protests planned on February 3

By A Representative   Gig and platform service workers across the country observed a nationwide online strike on Republic Day, responding to a call given by the Gig & Platform Service Workers Union (GIPSWU) to protest what it described as exploitation, insecurity and denial of basic worker rights in the platform economy. The union said women gig workers led the January 26 action by switching off their work apps as a mark of protest.

India’s road to sustainability: Why alternative fuels matter beyond electric vehicles

By Suyash Gupta*  India’s worsening air quality makes the shift towards clean mobility urgent. However, while electric vehicles (EVs) are central to India’s strategy, they alone cannot address the country’s diverse pollution and energy challenges.

Jayanthi Natarajan "never stood by tribals' rights" in MNC Vedanta's move to mine Niyamigiri Hills in Odisha

By A Representative The Odisha Chapter of the Campaign for Survival and Dignity (CSD), which played a vital role in the struggle for the enactment of historic Forest Rights Act, 2006 has blamed former Union environment minister Jaynaynthi Natarjan for failing to play any vital role to defend the tribals' rights in the forest areas during her tenure under the former UPA government. Countering her recent statement that she rejected environmental clearance to Vendanta, the top UK-based NMC, despite tremendous pressure from her colleagues in Cabinet and huge criticism from industry, and the claim that her decision was “upheld by the Supreme Court”, the CSD said this is simply not true, and actually she "disrespected" FRA.

Stands 'exposed': Cavalier attitude towards rushed construction of Char Dham project

By Bharat Dogra*  The nation heaved a big sigh of relief when the 41 workers trapped in the under-construction Silkyara-Barkot tunnel (Uttarkashi district of Uttarakhand) were finally rescued on November 28 after a 17-day rescue effort. All those involved in the rescue effort deserve a big thanks of the entire country. The government deserves appreciation for providing all-round support.

Whither space for the marginalised in Kerala's privately-driven townships after landslides?

By Ipshita Basu, Sudheesh R.C.  In the early hours of July 30 2024, a landslide in the Wayanad district of Kerala state, India, killed 400 people. The Punjirimattom, Mundakkai, Vellarimala and Chooralmala villages in the Western Ghats mountain range turned into a dystopian rubble of uprooted trees and debris.

Over 40% of gig workers earn below ₹15,000 a month: Economic Survey

By A Representative   The Finance Minister, Nirmala Sitharaman, while reviewing the Economic Survey in Parliament on Tuesday, highlighted the rapid growth of gig and platform workers in India. According to the Survey, the number of gig workers has increased from 7.7 million to around 12 million, marking a growth of about 55 percent. Their share in the overall workforce is projected to rise from 2 percent to 6.7 percent, with gig workers expected to contribute approximately ₹2.35 lakh crore to the GDP by 2030. The Survey also noted that over 40 percent of gig workers earn less than ₹15,000 per month.

Fragmented opposition and identity politics shaping Tamil Nadu’s 2026 election battle

By Syed Ali Mujtaba*  Tamil Nadu is set to go to the polls in April 2026, and the political battle lines are beginning to take shape. Prime Minister Narendra Modi’s visit to the state on January 23, 2026, marked the formal launch of the Bharatiya Janata Party’s campaign against the ruling Dravida Munnetra Kazhagam (DMK). Addressing multiple public meetings, the Prime Minister accused the DMK government of corruption, criminality, and dynastic politics, and called for Tamil Nadu to be “freed from DMK’s chains.” PM Modi alleged that the DMK had turned Tamil Nadu into a drug-ridden state and betrayed public trust by governing through what he described as “Corruption, Mafia and Crime,” derisively terming it “CMC rule.” He claimed that despite making numerous promises, the DMK had failed to deliver meaningful development. He also targeted what he described as the party’s dynastic character, arguing that the government functioned primarily for the benefit of a single family a...