Greenpeace targets Adani Group's $10 billion Australian coal mining project, says it is "uncommercial"

By Rajiv Shah
Top international environmental group Greenpeace in a new report has targeted premier Gujarat-based business group Adanis, saying that one of its overseas operations in Australia for mining coal may have become “uneconomical.” Titled “The Adani Group: Remote Prospects. A financial analysis of Adani’s coal gamble in Australia’s Galilee Basin”, and prepared by the Institute for Energy Economics and Financial Analysis, Cleveland, Ohio, US, for Greenpeace Australia Pacific, the report states, “We view Adani Enterprises’ development of the Carmichael deposit as an uneconomic proposition. The low energy and high ash content are major constraints to the value of the coal.”
Adanis term Greenpeace report “shortsighted”
The Adanis have termed the Greenpeace-commissioned report as “short-sighted”, prepared by “vested interests” who “ignore the long-term fundamentals that underpin Adani’s project in the Galilee Basin and the development of the country (Australia) at large.” Issued by Adani Abbot Point Terminal Pvt Ltd in response to Australian media reports (see South Asia Times) on the Greenpeace report, the statement says, “Development of the Galilee Basin is essential for both Queensland’s and Australia’s economy. Recognizing this, the Queensland government recently released its Galilee Basin strategy that confirms its commitment to developing this important region.”
Saying that the Adanis are “a key partner in that development”, the rejoinder says, “Adani Mining will be a long-term player in Australia and has complete confidence in the viability of the pipeline of projects it is currently developing, including the Carmichael Coal Mine and Rail Project, and the expansion of the Abbot Point Coal Terminal. In the short to medium-term these projects will create many thousands of jobs and generate significant flow on economic benefits. The motivation at the heart of these reports is short-sighted.” 
The Carmichael, at 10 billion tonnes, is considered the largest single coal deposit in the world. Last year, Adanis announced plans to proceed with a $10 billion development of its Carmichael scheme, including large-scale infrastructure investment, that would create 9,000 jobs, and export coal to India from 2016. Questioning the ambitious plan, the Greenpeace-sponsored report has said, “The remote location and lack of infrastructure will significantly add to the cost of mining and transporting the coal to market.” The report, running into 68 pages and authored by Tim Buckley and Tom Sanzillo, adds, “The financial leverage within the Adani Group adds significant financial risk to this project.”
Even as giving credit to the Adani Group for “an excellent ports and logistics business in India”, the report says, ”The distraction of a major expansion outside the geographic and product expertise of the Group is likely to continue to erode shareholder value.” Detailing the project, it adds, “Adani Enterprises is proposing to develop an at peak 60 million tonne per annum (Mtpa) thermal coal mine complex in the Galilee Coal Basin, 160 km north-west of the town of Clermont, central Queensland, Australia. Coal produced would be transported by a greenfield rail line to Abbot Point Port, where the company proposes a new 70Mtpa coal terminal (T0) in additional to an existing terminal (T1) for which it has a 99-year lease.”
Pointing out that the “Adani Enterprises anticipates selling much of the coal in India to support the nation’s plan to expand the use of coal-fired generation for its electricity grid”, the report says, “We view this US$7 billion (bn) proposal – the Carmichael Mine and Rail project (the Carmichael project) – as uncommercial for investors. The project’s economics don’t stack up. The short- and long-term price of coal globally, and within the principal outtake market of India, does not support the cost structure of this mining project.”
Referring specifically to the environmental issues which might inflate the project costs, the report states, “One of the key issues Adani Enterprises faces is the very high ash content of the Carmichael thermal coal. With an ash content of 25-30 per cent before washing and blending, this coal would not comply with proposed new Indian rules with respect to imported coal for ultra mega power plants (UMPPs) in India. The stipulated maximum ash content set by India’s Ministry of Environment and Forests (MoEF) is 12 per cent."
The report quotes the MoEF as saying, “The validity of environmental clearance granted is subject to compliance with the coal quality parameters indicated.” It underlines, “Getting the ash content for Carmichael coal down from 25-30 per cent to 12 per cent is likely to pose significant challenges for Adani Enterprises with respect to their strategy of vertically integrating from the Carmichael project through to the supply of thermal coal into Indian UMPPs.”
The mining site
The report specifies, “The Environmental Impact Statement (EIS) shows the coal produced will vary from 20-40% ash, with an average of 25% over the mine life forecast. With the 75% level of coal preparation and washing forecast by Adani Mining, this gives a 79% yield over the life of the mine… Every 1% higher ash content over the 5,500kcal benchmark assumption of 20% would result in a price penalty of US$0.50/t. The implication is that working with the September 2012 EIS assumption of an ash content averaging 25% would result in a US$2.50/t penalty to Adani.”
Given all this, the report believes that “Adani Group is also financially and operationally constrained and faces a series of logistical barriers in Australia”. The “key issues” it raises include:
· The Carmichael project is uneconomic – a high cost coal product in a low priced coal market with an uncertain future.
· Carmichael coal is a low quality, high cost product challenged by low market prices. Carmichael has a high strip ratio and the coal quality is low by Australian standards (20-30% ash and energy content of 5,260kcal net as received (NAR)).
· Open cut mining to 280 metres is significantly deeper than required in the south of the Galilee Coal Basin.
· India’s power market is fatally flawed. It cannot absorb the high price of coal from the Carmichael project. The domestic price of coal in India is in the US$30/t range and the price Carmichael coal requires is over US$95/t (inclusive of shipping). Successful sales to India of Carmichael coal will place a substantial pressure on power generator profits and the price of electricity in India.
· The Adani Enterprises’ external equity market capitalisation is US$5.17bn against estimated Carmichael project costs of US$7bn. Despite this weak capitalisation, Adani Enterprises has announced an enormous list of new capital intensive ventures.
· The Adani Group is highly geared. Against an external market capitalisation of US$5.17bn, the Adani Group has an estimated US$12bn of net debt, a significant portion of which is US$-denominated with limited hedging.
· Adani Power is financially weak and operationally underperforming. Adani Power’s share price is down 46 per cent year-to-date and down 74 per cent over three years – a massive underperformance relative to the MSCI India Index. Adani Enterprises is down 39 per cent year-to-date and down 70 per cent over three years.
· Adani Enterprises does not have a long or successful history of coal mining: Adani Enterprises has mined 2-4Mtpa in Indonesia over 2010-2013, its first experience in coal mining. Adani Enterprises is now proposing to build the biggest coal mine complex in Australian history.
· The Adani Group has suffered a series of delays to its Australian mining, rail and port plans. Adani Enterprises initially expected to have the Carmichael project selling coal by 2014. Adani Enterprises concedes this timetable has been pushed out to 2016, but the report estimates that its partial production will start in 2017 and full production not before 2022.
· Carmichael coal is in a very remote location. Carmichael is 400 km from the coast and there is no rail infrastructure within 200 km. There is also no commercial power or water infrastructure within 200 km and there is no sealed road access for 90 km.

Comments

TRENDING

Gujarat Information Commission issues warning against misinterpretation of RTI orders

By A Representative   The Gujarat Information Commission (GIC) has issued a press note clarifying that its orders limiting the number of Right to Information (RTI) applications for certain individuals apply only to those specific applicants. The GIC has warned that it will take disciplinary action against any public officials who misinterpret these orders to deny information to other citizens. The press note, signed by GIC Secretary Jaideep Dwivedi, states that the Right to Information Act, 2005, is a powerful tool for promoting transparency and accountability in public administration. However, the commission has observed that some applicants are misusing the act by filing an excessive number of applications, which disproportionately consumes the time and resources of Public Information Officers (PIOs), First Appellate Authorities (FAAs), and the commission itself. This misuse can cause delays for genuine applicants seeking justice. In response to this issue, and in acc...

'MGNREGA crisis deepening': NSM demands fair wages and end to digital exclusions

By A Representative   The NREGA Sangharsh Morcha (NSM), a coalition of independent unions of MGNREGA workers, has warned that the Mahatma Gandhi National Rural Employment Guarantee Act (MGNREGA) is facing a “severe crisis” due to persistent neglect and restrictive measures imposed by the Union Government.

A comrade in culture and controversy: Yao Wenyuan’s revolutionary legacy

By Harsh Thakor*  This year marks two important anniversaries in Chinese revolutionary history—the 20th death anniversary of Yao Wenyuan, and the 50th anniversary of his seminal essay "On the Social Basis of the Lin Biao Anti-Party Clique". These milestones invite reflection on the man whose pen ignited the first sparks of the Great Proletarian Cultural Revolution and whose sharp ideological interventions left an indelible imprint on the political and cultural landscape of socialist China.

Gandhiji quoted as saying his anti-untouchability view has little space for inter-dining with "lower" castes

By A Representative A senior activist close to Narmada Bachao Andolan (NBA) leader Medha Patkar has defended top Booker prize winning novelist Arundhati Roy’s controversial utterance on Gandhiji that “his doctrine of nonviolence was based on an acceptance of the most brutal social hierarchy the world has ever known, the caste system.” Surprised at the police seeking video footage and transcript of Roy’s Mahatma Ayyankali memorial lecture at the Kerala University on July 17, Nandini K Oza in a recent blog quotes from available sources to “prove” that Gandhiji indeed believed in “removal of untouchability within the caste system.”

Targeted eviction of Bengali-speaking Muslims across Assam districts alleged

By A Representative   A delegation led by prominent academic and civil rights leader Sandeep Pandey  visited three districts in Assam—Goalpara, Dhubri, and Lakhimpur—between 2 and 4 September 2025 to meet families affected by recent demolitions and evictions. The delegation reported widespread displacement of Bengali-speaking Muslim communities, many of whom possess valid citizenship documents including Aadhaar, voter ID, ration cards, PAN cards, and NRC certification. 

India's health workers have no legal right for their protection, regrets NGO network

Counterview Desk In a letter to Union labour and employment minister Santosh Gangwar, the civil rights group Occupational and Environmental Health Network of India (OEHNI), writing against the backdrop of strike by Bhabha hospital heath care workers, has insisted that they should be given “clear legal right for their protection”.

Uttarakhand tunnel disaster: 'Question mark' on rescue plan, appraisal, construction

By Bhim Singh Rawat*  As many as 40 workers were trapped inside Barkot-Silkyara tunnel in Uttarkashi after a portion of the 4.5 km long, supposedly completed portion of the tunnel, collapsed early morning on Sunday, Nov 12, 2023. The incident has once again raised several questions over negligence in planning, appraisal and construction, absence of emergency rescue plan, violations of labour laws and environmental norms resulting in this avoidable accident.

Rally in Patna: Non-farmer bodies to highlight plight of agriculture in Eastern India ahead of march to Parliament

P Sainath By  A  Representative Ahead of the march to Parliament on November 29-30, 2018, organized by over 210 farmer and agricultural worker organisations of the country demanding a 21-day special session of Parliament to deliberate on remedial measures for safeguarding the interest of farm, farmers and agricultural workers, a mass rally been organized for November 23, Gandhi Sangrahalaya (Gandhi Museum), Gandhi Maidan, Patna. Say the organizers, the Eastern region merits special attention, because, while crisis of farmers and agricultural workers in Western, Southern and Northern India has received some attention in the media and central legislature, the plight of those in the Eastern region of the country (Bihar, Jharkhand, West Bengal, Orissa, Chhattisgarh and Eastern UP) has remained on the margins. To be addressed by P Sainath, founder of People’s Archive of Rural India (PARI), a statement issued ahead of the rally says, the Eastern India was the most prosperous regi...

Job opportunities decreasing, wages remain low: Delhi construction workers' plight

By Bharat Dogra*   It was about 32 years back that a hut colony in posh Prashant Vihar area of Delhi was demolished. It was after a great struggle that the people evicted from here could get alternative plots that were not too far away from their earlier colony. Nirmana, an organization of construction workers, played an important role in helping the evicted people to get this alternative land. At that time it was a big relief to get this alternative land, even though the plots given to them were very small ones of 10X8 feet size. The people worked hard to construct new houses, often constructing two floors so that the family could be accommodated in the small plots. However a recent visit revealed that people are rather disheartened now by a number of adverse factors. They have not been given the proper allotment papers yet. There is still no sewer system here. They have to use public toilets constructed some distance away which can sometimes be quite messy. There is still no...