Inappropriate dam operation: What India can learn from 2011 Australian floods judgment

In a judgment on November 29, 2019 Australia’s New South Wales Supreme Court has held the State of Queensland, Wivenhoe Dam operators and engineers are responsible for “inappropriate operation of the dam”, leading to the devastating Brisbane 2011 floods. A South Asia Network on Dams, Rivers and People (SANDRP) note on the relevance of the judgment for India:
***
In a landmark judgment, the January 2011 Brisbane (Australia) floods class action decision was announced by the New South Wales Supreme Court (Justice Robert Beech-Jones) on Nov 29, 2019. The court held the State of Queensland, Wivenhoe Dam operators and engineers responsible for inappropriate operation of the dam. It’s one of the largest ever class action suits of Australia and could cost the government millions of dollars.
Brisbane Times reported on Nov 29, 2019: “More than 6800 victims of the 2011 Brisbane flood have won a historic class action against Seqwater, Sunwater and the Queensland government over the management of the Wivenhoe Dam. The NSW Supreme Court on Friday ruled that the dam’s flood engineers relied too closely on “rain on the ground” estimates in 2011 and did not appropriately use rainfall forecasts to manage Wivenhoe Dam, as required by its manual.” The manual was gazetted by the Queensland government in 2010, a year before the flood.
Justice Robert Beech-Jones ruled that the four flood engineers who had operated the Wivenhoe Dam in January 2011 had “in some respects” breached their duty of care in managing the flow of water from the dam. Announcing a complex ruling over almost two hours, Justice Beech Jones said Seqwater, Sunwater and the state government were “negligent”.
Maurice Blackburn lawyers lodged the class action on behalf of the 6870 flood victims. Other tests cases will now be evaluated before a further hearing in the NSW Supreme Court on February 21, 2020. That opens the doors to a potential payout of hundreds of millions of dollars – law firms suggest it could run to a billion dollars.

The Jan 2011 Brisbane floods

The summary of the Judgment describes these as: “In early January 2011, the Brisbane River Basin experienced extensive rainfall, culminating in extreme downfalls from 9 to 11 January 2011. On 11 and 12 January 2011, there was flooding of many homes and businesses as a result of the Brisbane River, the lower Bremer River and Lockyer Creek breaking their banks. Of the recorded peak flow on the Brisbane River at Moggill, at the height of the flooding somewhere between 39% and 51% of the flow was attributable to releases made from Wivenhoe Dam.”

The Accused

The summary of Judgment: “The plaintiff sued the three defendants, who were said to be legally responsible for the actions of four flood engineers who were responsible for conducting flood operations at Wivenhoe Dam and Somerset Dam from 2 January 2011 to 11 January 2011. Seqwater was the owner of the Dams and the employer of two of these flood engineers. SunWater was contracted to provide flood management services to Seqwater and was the employer of one of the four flood engineers. The (Queensland) State employed the fourth and final flood engineer. The plaintiff sued the three defendants in negligence, nuisance and trespass.”

Key aspects from the Judgment

The defendants (the State of Queensland, Sunwater and SEQWater, the operators and engineers), were variously responsible for inappropriate operation of the dam by failing to evacuate the dam to accommodate rain inflows, and are therefore breached their duty of care. The negligence claims of the plaintiffs succeeded against all of the defendants. Various damages were awarded, with some adjustments for different plaintiffs, depending on several issues, such as compensation already awarded. The exercise of reasonable care would have permitted water releases despite the operation manual’s norms.
In the six days before the flood, the rain forecasts in an already saturated catchment indicated an imminent urban flood event, which should have been declared, and the actual rain was exceeding the forecasts. With dam already full, virtual certainty that flooding would occur.
Justice Beech-Jones raised inconsistencies between the Wivenhoe Dam flood manual and the operation of the dams. He said the flood engineers had relied too closely on “rain on the ground” modelling and not on forecast rainfall, particularly four- and eight-day forecast rainfall in the Wivenhoe Dam’s catchment areas.
“I accept that each of Seqwater, Sunwater and the State are vicariously liable for any breaches of the duty of care owed by the flood engineers that they each employed… The manual unambiguously and stubbornly required that ‘best forecast rainfall’ be used to make predictions for the purpose of determining the anticipated storage levels in the dams in order to select the applicable flood strategy,” said the ruling.
The Judge said he accepted much of the evidence of Utah dam expert Ronald Christensen. Dr Christensen had posed 10 alternative modelling scenarios for managing the Wivenhoe Dam and argued that using flood forecasts was part of the Wivenhoe Dam’s flood manual.
“The Court found that the flood engineers failed to comply with the Manual in these and other respects and that this, in turn, meant that by 11 January 2011 they were forced to make large releases of water to ensure Wivenhoe Dam did not fail. The Court found that the impugned actions of the flood engineers during the January 2011 Flood Event were not reasonable mistakes made in the heat of the moment, but systemic failures to apply the Manual that they had drafted… The Court found that each of the flood engineers’ conduct of flood operations was not to the standard of a reasonably competent flood engineer and that they therefore breached the duty of care they owed to the plaintiff (and group members). 
“The Court accepted three of the simulated alternative flood operations put forward by the plaintiff’s expert as representing the flood operations that a reasonably competent flood engineer would have undertaken during the January 2011 Flood Event (“Simulations C, F and H”). All the simulations were premised on a methodology of conserving dam storage capacity when forecasts pointed to rainfall and then using dam storage capacity to ensure peak releases did not coincide with heavy downstream flows in times of substantial rainfall. The Court accepted that the simulations were consistent with the Manual. 
“Using a two-dimensional numerical hydraulic model of the Brisbane River catchment and other evidence of the effects of the January 2011 Flood Event, the plaintiff sought to demonstrate that its store would not have been inundated had the flood engineers undertaken flood operations in accordance with the simulated flood operations advanced by the plaintiff’s expert. The Court accepted that contention and found that the level of flooding that would have been experienced under Simulation C would not have inundated the plaintiff’s store and the homes of a number of other group members whose cases were also heard in part during this phase of the proceedings. 
“The Manual designated a flow rate of 4000m3/s in the Brisbane River at Moggill as the threshold point at which homes and businesses downstream of the dams would commence to be flooded. The flows in the Brisbane River at Moggill comprise the outflows from Wivenhoe Dam as well as outflows from Lockyer Creek and the Bremer River into the Brisbane River. Unfortunately, to a significant extent the large increase in outflows from Wivenhoe Dam coincided with large outflows from Lockyer Creek and the Bremer River. The peak flow rate experienced at Moggill was at around 1.00pm to 2.00pm on 12 January 2011. It was between 10,420m3/s and 10,700m3/s, of which between 4200m3/s and 5300m3/s was attributable to releases from Wivenhoe Dam.”
(Summary of the Judgment)
The Judgment emphasised that the dam operators were not completely bound by specifics in the dam operation manual which the defendants claimed prevented pre-emptive emptying, but by its more fundamental principles and provisions to prevent flooding. They could have decided to partially empty the dam in the days preceding the flood. They did not have to prioritise maintaining full supply level for the period after the flood over damage prevention and dam safety, and should have placed more weight on rain forecasts. Issues like keeping low-lying bridges open should not have taken precedence over flood prevention.

Brisbane Resident Dr. Charles Worringham

Dr. Charles Worringham, a long-time Brisbane resident and former academic described the judgment as historic. He told SANDRP: “Judge Beech-Jones left no doubt that the dam operators were negligent in the days leading up to the catastrophic releases. He gave considerable weight to analyses showing how precautionary releases ahead of time would have reduced the severity of flooding. The dam was already at full supply level while exceptional rains were not just forecast, they were already being exceeded.”
Dr. Worringham described his own experience of the floods: “No-one who lived through these largely preventable floods will forget the devastation they caused, even if they did not personally experience damage. My son and I joined thousands of others filling sand-bags the night before when we all knew what was coming, but this was all too little and too late. Seeing the Bremer river rise nearly 15 meters in just a few hours, watching the debris carried down by the swollen Brisbane river past the University of Queensland, and hearing the eerie roaring sound as it spilled into so many city neighbourhoods are things that stay with you forever.”
Dr Worringham added: “The recovery effort was huge but lasted for months. If a wealthy city like Brisbane with its abundant equipment and resources can be so badly effected, I can only imagine how desparate the situation would be for communities that lack them. While disasters tend to bring out the best in people wherever they occur, voluntary efforts cannot substitute for responsible planning and operation of such important – but potentially hazardous – facilities as dams. And with rainfall patterns becoming less predictable as the climate crisis unfolds, record falls can occur with little notice, making greater caution even more important.”
Dr. Worringham said about future implications: “This judgment really sets a precedent for dam operators everywhere. Given the similarities to operational failures in other jurisdictions that have also led to large-scale loss of life and damage, it is likely to influence not just future court decisions, but encourage dam operators to urgently review their operating procedures and give greater priority to timely flood mitigation and dam safety measures – even if these cause minor conflict with policies favouring high dam levels. Let’s hope the lessons of this episode are well understood everywhere.”
Thanks, Dr. Worringham, for alerting SANDRP about this order and also sharing your views and experience of the Dam floods in Brisbane in January 2011.

Relevance for India:

There are quite a few detailed statements in the judgment that may be relevant to the India including Kerala floods of Aug 2018. We hope Indian courts will also take note of this landmark judgment.

Source: SANDRP

Comments

TRENDING

Budget for 2018-19: Ahmedabad authorities "regularly" under-spend allocation

By Mahender Jethmalani* The Ahmedabad Municipal Corporation’s (AMC's) General Body (Municipal Board) recently passed the AMC’s annual budget estimates of Rs 6,990 crore for 2018-19. AMC’s revenue expenditure for the next financial year is Rs 3,500 crore and development budget (capital budget) is Rs 3,490 crore.

History, culture and literature of Fatehpur, UP, from where Maulana Hasrat Mohani hailed

By Vidya Bhushan Rawat*  Maulana Hasrat Mohani was a member of the Constituent Assembly and an extremely important leader of our freedom movement. Born in Unnao district of Uttar Pradesh, Hasrat Mohani's relationship with nearby district of Fatehpur is interesting and not explored much by biographers and historians. Dr Mohammad Ismail Azad Fatehpuri has written a book on Maulana Hasrat Mohani and Fatehpur. The book is in Urdu.  He has just come out with another important book, 'Hindi kee Pratham Rachna: Chandayan' authored by Mulla Daud Dalmai.' During my recent visit to Fatehpur town, I had an opportunity to meet Dr Mohammad Ismail Azad Fatehpuri and recorded a conversation with him on issues of history, culture and literature of Fatehpur. Sharing this conversation here with you. Kindly click this link. --- *Human rights defender. Facebook https://www.facebook.com/vbrawat , X @freetohumanity, Skype @vbrawat

Licy Bharucha’s pilgrimage into the lives of India’s freedom fighters

By Moin Qazi* Book Review: “Oral History of Indian Freedom Movement”, by Dr Licy Bharucha; Pp240; Rs 300; Published by National Museum of Indian Freedom Movement The Congress has won political freedom, but it has yet to win economic freedom, social and moral freedom. These freedoms are harder than the political, if only because they are constructive, less exciting and not spectacular. — Mahatma Gandhi The opening quote of the book by Mahatma Gandhi sums up the true objective of India’s freedom struggle. It also in essence speaks for the multitudes of brave and courageous individuals who aspired to get themselves jailed for the cause of the country’s freedom. A jail term was a strong testimony and credential of patriotism for them. The book has been written by Dr Licy Bharucha, an academically trained political scientist and a scholar of peace studies and Gandhian studies, who was closely associated throughout her life with those who made the struggle for India’s independence the primar...

New RTI draft rules inspired by citizen-unfriendly, overtly bureaucratic approach

By Venkatesh Nayak* The Department of Personnel and Training , Government of India has invited comments on a new set of Draft Rules (available in English only) to implement The Right to Information Act, 2005 . The RTI Rules were last amended in 2012 after a long period of consultation with various stakeholders. The Government’s move to put the draft RTI Rules out for people’s comments and suggestions for change is a welcome continuation of the tradition of public consultation. Positive aspects of the Draft RTI Rules While 60-65% of the Draft RTI Rules repeat the content of the 2012 RTI Rules, some new aspects deserve appreciation as they clarify the manner of implementation of key provisions of the RTI Act. These are: Provisions for dealing with non-compliance of the orders and directives of the Central Information Commission (CIC) by public authorities- this was missing in the 2012 RTI Rules. Non-compliance is increasingly becoming a major problem- two of my non-compliance cases are...

Urgent need to study cause of large number of natural deaths in Gulf countries

By Venkatesh Nayak* According to data tabled in Parliament in April 2018, there are 87.76 lakh (8.77 million) Indians in six Gulf countries, namely Bahrain, Kuwait, Oman, Qatar, Saudi Arabia and the United Arab Emirates (UAE). While replying to an Unstarred Question (#6091) raised in the Lok Sabha, the Union Minister of State for External Affairs said, during the first half of this financial year alone (between April-September 2018), blue-collared Indian workers in these countries had remitted USD 33.47 Billion back home. Not much is known about the human cost of such earnings which swell up the country’s forex reserves quietly. My recent RTI intervention and research of proceedings in Parliament has revealed that between 2012 and mid-2018 more than 24,570 Indian Workers died in these Gulf countries. This works out to an average of more than 10 deaths per day. For every US$ 1 Billion they remitted to India during the same period there were at least 117 deaths of Indian Workers in Gulf ...

Celebrating 125 yr old legacy of healthcare work of missionaries

Vilas Shende, director, Mure Memorial Hospital By Moin Qazi* Central India has been one of the most fertile belts for several unique experiments undertaken by missionaries in the field of education and healthcare. The result is a network of several well-known schools, colleges and hospitals that have woven themselves into the social landscape of the region. They have also become a byword for quality and affordable services delivered to all sections of the society. These institutions are characterised by committed and compassionate staff driven by the selfless pursuit of improving the well-being of society. This is the reason why the region has nursed and nurtured so many eminent people who occupy high positions in varied fields across the country as well as beyond. One of the fruits of this legacy is a more than century old iconic hospital that nestles in the heart of Nagpur city. Named as Mure Memorial Hospital after a British warrior who lost his life in a war while defending his cou...

Sardar Patel was on Nathuram Godse's hit list: Noted Marathi writer Sadanand More

Sadanand More (right) By  A  Representative In a surprise revelation, well-known Gujarati journalist Hari Desai has claimed that Nathuram Godse did not just kill Mahatma Gandhi, but also intended to kill Sardar Vallabhbhai Patel. Citing a voluminous book authored by Sadanand More, “Lokmanya to Mahatma”, Volume II, translated from Marathi into English last year, Desai says, nowadays, there is a lot of talk about conspiracy to kill Gandhi, Netaji Subhas Chandra Bose, and Shyama Prasad Mukherjee, but little is known about how the Sardar was also targeted.

UP tribal woman human rights defender Sokalo released on bail

By  A  Representative After almost five months in jail, Adivasi human rights defender and forest worker Sokalo Gond has been finally released on bail.Despite being granted bail on October 4, technical and procedural issues kept Sokalo behind bars until November 1. The Citizens for Justice and Peace (CJP) and the All India Union of Forest Working People (AIUFWP), which are backing Sokalo, called it a "major victory." Sokalo's release follows the earlier releases of Kismatiya and Sukhdev Gond in September. "All three forest workers and human rights defenders were illegally incarcerated under false charges, in what is the State's way of punishing those who are active in their fight for the proper implementation of the Forest Rights Act (2006)", said a CJP statement.

Uttarakhand tunnel disaster: 'Question mark' on rescue plan, appraisal, construction

By Bhim Singh Rawat*  As many as 40 workers were trapped inside Barkot-Silkyara tunnel in Uttarkashi after a portion of the 4.5 km long, supposedly completed portion of the tunnel, collapsed early morning on Sunday, Nov 12, 2023. The incident has once again raised several questions over negligence in planning, appraisal and construction, absence of emergency rescue plan, violations of labour laws and environmental norms resulting in this avoidable accident.