Gas 'dreams': Failure to get eco-clearance for submarine pipeline costs Gujarat PSU another Rs 760 crore

By A Representative
Failure to get forest and environmental clearance for laying down Rs 826 crore submarine pipeline to tap the gas found off Andhra Pradesh coast has cost former bluechip public sector undertaking (PSU), Gujarat State Petroleum Corporation (GSPC), dear. Latest information available from an internal note has suggested that the GSPC will have to shell out a total of around another US dollars 123.66 million as “standby” or “idle” charges to Punj Lloyd Ltd (PLL), the top multinational contractors who were hired in an international bid, to lay down the submarine pipeline in 2011.
The note, which is in possession of Counterview, said that the total amount would have to be paid “expeditiously”, as the contractors are unable to continue their work because of the failure of the GSPC to get necessary clearances on time, as required by the terms of agreement. “PLL has already submitted communication indicating their standby claim. Early resolution of the issue is necessary to preempt any further claims on account of standby”, the note, put up before a recent board meeting of the GSPC, said. Sources added, failure to get necessary clearances has delayed the completion of the project -- scheduled to end in April 2013 -- by at least a year.
Already, the note says, the GSPC has paid PLL an amount of 71.25 million dollars (or Rs 440 crore). However, insiders said, as the money was disbursed without approval of the GSPC board, there was considerable commotion in the Gujarat bureaucratic circles. “Hence, GSPC managing director Tapan Ray decided to approach the GSPC board for getting an approval for the rest of the amount, which comes to around Rs 44.41 million dollars. The board, which met recently, was “undecided” on the matter, and asked a committee under retired IAS bureaucrat MM Shrivastav to look into the matter and decide on the matter.
The note asks the GSPC board to pay up at least 15 million dollars of the amount still a final decision is made. It says, it should be an “interim measure” till the “final settlement is arrived at”. In the meanwhile, the necessary clearances would be taken. Arguing in favour of the payment, the note said, payment to the contracts is “necessary” because 72 per cent of the work in tapping gas from the Deendayal (West) field off Andhra coast is already over, and gas’ commercial production is pending completion of the submarine project. It has expressed the apprehension, at stake is 2.2 billion dollars investment in tapping gas.
Arguing that the “submarine pipeline is the only interconnection” between the GSPC’s Deendayal fields and the onshore facilities, which would refine the gas and send them into the national grid, the note say, “rescinding the contract at this stage” would imply a new tender would have “delay” the commercial production by another 9-12 months to float. “Nature of the work calls for international competitive bidding”, it points out, adding, there always apprehension that “sufficient offers may not come”. Further, it adds, “dispute resolution with PLL” may prove to be “messy, time consuming and costly.”
The GSPC also expresses the apprehension that the overall cost of maintaining the infrastructure set up by the GSPC for commercial production of gas may go up drastically to 300 million dollars per annum. This includes the “additional burden of fixed cost of already installed capacities, interest payment on borrowed capital, operation and maintenance cost” and so on. On the other hand, “assistance to PLL to mobilize resources would facilitate completion of pipeline project by March 2014.”
The GSPC's Rs 760 crore blow came close on the heels of its formal decision to withdraw from its most important overseas adventure – Egypt. The decision was taken as it was proving to be a very costly affair. Deeply under debt of Rs 8,000 crore, the exploration in Egypt would have cost the GSPC another Rs 5,000, with no surety about possibility of getting gas or oil. It was the first major step to bring out GSPC from the financial mess it is in right now.
Interestingly, the GSPC not just failed to get environmental and coastal regulatory zone (CRZ) clearance for the submarine pipeline but also its onshore gas terminal, a 20 MW captive power plant, 20 underground gas pipelines along with optical fibre cable (OFC), and 10 inches effluent disposal pipeline -- of which it badly needed for commercial production of the gas it struck several years ago. Some of these facilities were to pass through CRZ area of Yanam-Puducherry along the Andhra Pradesh coast. 
It simultaneously failed to get clearance for its offshore process-cum-living quarter platform in at the Deendayal block in the KG Basin in Andhra sea, where the top PSU had claimed in 2005 to have found 20 trillion cubic metres (tcf) of gas -- a claim which has been quashed, as total gas available is just 2 tcf, of which one third is recoverable.
In May last year, the environmental appraisal committee (EAC) had asked the GSPC to “defer” construction commercial facilities until certain conditions were fulfilled. It refused to give blanket CRZ clearance for laying down underground gas pipeline, optical fibre cable (OFC), an effluent disposal pipeline, and process-cum-living quarter platform and captive power plant – all of which would require he CRZ clearance, as these facilities are to be part of the Yanam-Puducherry coastal region. The GSPC wanted all these to be cleared together but the EAC ruled against it, asking the GSPC to make separate applications.
The EAC wanted the GSPC to submit: (1) details of the critical environmental issues identified during laying of pipeline, (2) environment clearance for enhancement of captive power plant, under consideration of environmental appraisal committee (EAC) of the thermal committee, which has also sought examining the requirement of wildlife clearance in view of Coringa Sanctuary located in 2.5 km distance, and (3) the plan of the pipeline to pass through the mangroves. Based on these observations, it recommended to defer the proposal.

Comments

TRENDING

'Threat to farmers’ rights': New seeds Bill sparks fears of rising corporate control

By Bharat Dogra  As debate intensifies over a new seeds bill, groups working on farmers’ seed rights, seed sovereignty and rural self-reliance have raised serious concerns about the proposed legislation. To understand these anxieties, it is important to recognise a global trend: growing control of the seed sector by a handful of multinational companies. This trend risks extending corporate dominance across food and farming systems, jeopardising the livelihoods and rights of small farmers and raising serious ecological and health concerns. The pending bill must be assessed within this broader context.

Delhi Jal Board under fire as CAG finds 55% groundwater unfit for consumption

By A Representative   A Comptroller and Auditor General (CAG) of India audit report tabled in the Delhi Legislative Assembly on 7 January 2026 has revealed alarming lapses in the quality and safety of drinking water supplied by the Delhi Jal Board (DJB), raising serious public health concerns for residents of the capital. 

Zhou Enlai: The enigmatic premier who stabilized chaos—at what cost?

By Harsh Thakor*  Zhou Enlai (1898–1976) served as the first Premier of the People's Republic of China (PRC) from 1949 until his death and as Foreign Minister from 1949 to 1958. He played a central role in the Chinese Communist Party (CCP) for over five decades, contributing to its organization, military efforts, diplomacy, and governance. His tenure spanned key events including the Long March, World War II alliances, the founding of the PRC, the Korean War, and the Cultural Revolution. 

Stands 'exposed': Cavalier attitude towards rushed construction of Char Dham project

By Bharat Dogra*  The nation heaved a big sigh of relief when the 41 workers trapped in the under-construction Silkyara-Barkot tunnel (Uttarkashi district of Uttarakhand) were finally rescued on November 28 after a 17-day rescue effort. All those involved in the rescue effort deserve a big thanks of the entire country. The government deserves appreciation for providing all-round support.

Advocacy group decries 'hyper-centralization' as States’ share of health funds plummets

By A Representative   In a major pre-budget mobilization, the Jan Swasthya Abhiyan (JSA), India’s leading public health advocacy network, has issued a sharp critique of the Union government’s health spending and demanded a doubling of the health budget for the upcoming 2026-27 fiscal year. 

Pairing not with law but with perpetrators: Pavlovian response to lynchings in India

By Vikash Narain Rai* Lynch-law owes its name to James Lynch, the legendary Warden of Galway, Ireland, who tried, condemned and executed his own son in 1493 for defrauding and killing strangers. But, today, what kind of a person will justify the lynching for any reason whatsoever? Will perhaps resemble the proverbial ‘wrong man to meet at wrong road at night!’

Jayanthi Natarajan "never stood by tribals' rights" in MNC Vedanta's move to mine Niyamigiri Hills in Odisha

By A Representative The Odisha Chapter of the Campaign for Survival and Dignity (CSD), which played a vital role in the struggle for the enactment of historic Forest Rights Act, 2006 has blamed former Union environment minister Jaynaynthi Natarjan for failing to play any vital role to defend the tribals' rights in the forest areas during her tenure under the former UPA government. Countering her recent statement that she rejected environmental clearance to Vendanta, the top UK-based NMC, despite tremendous pressure from her colleagues in Cabinet and huge criticism from industry, and the claim that her decision was “upheld by the Supreme Court”, the CSD said this is simply not true, and actually she "disrespected" FRA.

Why economic war waged by US has created the situation for Iran's turmoil

By Vijay Prashad   Iran is in turmoil. Across the country, there have been protests of different magnitudes, with violence on the increase with both protesters and police finding themselves in the morgue. What began as work stoppages and inflation protests drew together a range of discontent, with women and young people frustrated with a system unable to secure their livelihood. Iran has been under prolonged economic siege and has been attacked directly by Israel and the United States not only within its borders, but across West Asia (including in its diplomatic enclaves in Syria). This economic war waged by the United States has created the situation for this turmoil, but the turmoil itself is not directed at Washington but at the government in Tehran.

Uttarakhand tunnel disaster: 'Question mark' on rescue plan, appraisal, construction

By Bhim Singh Rawat*  As many as 40 workers were trapped inside Barkot-Silkyara tunnel in Uttarkashi after a portion of the 4.5 km long, supposedly completed portion of the tunnel, collapsed early morning on Sunday, Nov 12, 2023. The incident has once again raised several questions over negligence in planning, appraisal and construction, absence of emergency rescue plan, violations of labour laws and environmental norms resulting in this avoidable accident.