Skip to main content

Gas 'dreams': Failure to get eco-clearance for submarine pipeline costs Gujarat PSU another Rs 760 crore

By A Representative
Failure to get forest and environmental clearance for laying down Rs 826 crore submarine pipeline to tap the gas found off Andhra Pradesh coast has cost former bluechip public sector undertaking (PSU), Gujarat State Petroleum Corporation (GSPC), dear. Latest information available from an internal note has suggested that the GSPC will have to shell out a total of around another US dollars 123.66 million as “standby” or “idle” charges to Punj Lloyd Ltd (PLL), the top multinational contractors who were hired in an international bid, to lay down the submarine pipeline in 2011.
The note, which is in possession of Counterview, said that the total amount would have to be paid “expeditiously”, as the contractors are unable to continue their work because of the failure of the GSPC to get necessary clearances on time, as required by the terms of agreement. “PLL has already submitted communication indicating their standby claim. Early resolution of the issue is necessary to preempt any further claims on account of standby”, the note, put up before a recent board meeting of the GSPC, said. Sources added, failure to get necessary clearances has delayed the completion of the project -- scheduled to end in April 2013 -- by at least a year.
Already, the note says, the GSPC has paid PLL an amount of 71.25 million dollars (or Rs 440 crore). However, insiders said, as the money was disbursed without approval of the GSPC board, there was considerable commotion in the Gujarat bureaucratic circles. “Hence, GSPC managing director Tapan Ray decided to approach the GSPC board for getting an approval for the rest of the amount, which comes to around Rs 44.41 million dollars. The board, which met recently, was “undecided” on the matter, and asked a committee under retired IAS bureaucrat MM Shrivastav to look into the matter and decide on the matter.
The note asks the GSPC board to pay up at least 15 million dollars of the amount still a final decision is made. It says, it should be an “interim measure” till the “final settlement is arrived at”. In the meanwhile, the necessary clearances would be taken. Arguing in favour of the payment, the note said, payment to the contracts is “necessary” because 72 per cent of the work in tapping gas from the Deendayal (West) field off Andhra coast is already over, and gas’ commercial production is pending completion of the submarine project. It has expressed the apprehension, at stake is 2.2 billion dollars investment in tapping gas.
Arguing that the “submarine pipeline is the only interconnection” between the GSPC’s Deendayal fields and the onshore facilities, which would refine the gas and send them into the national grid, the note say, “rescinding the contract at this stage” would imply a new tender would have “delay” the commercial production by another 9-12 months to float. “Nature of the work calls for international competitive bidding”, it points out, adding, there always apprehension that “sufficient offers may not come”. Further, it adds, “dispute resolution with PLL” may prove to be “messy, time consuming and costly.”
The GSPC also expresses the apprehension that the overall cost of maintaining the infrastructure set up by the GSPC for commercial production of gas may go up drastically to 300 million dollars per annum. This includes the “additional burden of fixed cost of already installed capacities, interest payment on borrowed capital, operation and maintenance cost” and so on. On the other hand, “assistance to PLL to mobilize resources would facilitate completion of pipeline project by March 2014.”
The GSPC's Rs 760 crore blow came close on the heels of its formal decision to withdraw from its most important overseas adventure – Egypt. The decision was taken as it was proving to be a very costly affair. Deeply under debt of Rs 8,000 crore, the exploration in Egypt would have cost the GSPC another Rs 5,000, with no surety about possibility of getting gas or oil. It was the first major step to bring out GSPC from the financial mess it is in right now.
Interestingly, the GSPC not just failed to get environmental and coastal regulatory zone (CRZ) clearance for the submarine pipeline but also its onshore gas terminal, a 20 MW captive power plant, 20 underground gas pipelines along with optical fibre cable (OFC), and 10 inches effluent disposal pipeline -- of which it badly needed for commercial production of the gas it struck several years ago. Some of these facilities were to pass through CRZ area of Yanam-Puducherry along the Andhra Pradesh coast. 
It simultaneously failed to get clearance for its offshore process-cum-living quarter platform in at the Deendayal block in the KG Basin in Andhra sea, where the top PSU had claimed in 2005 to have found 20 trillion cubic metres (tcf) of gas -- a claim which has been quashed, as total gas available is just 2 tcf, of which one third is recoverable.
In May last year, the environmental appraisal committee (EAC) had asked the GSPC to “defer” construction commercial facilities until certain conditions were fulfilled. It refused to give blanket CRZ clearance for laying down underground gas pipeline, optical fibre cable (OFC), an effluent disposal pipeline, and process-cum-living quarter platform and captive power plant – all of which would require he CRZ clearance, as these facilities are to be part of the Yanam-Puducherry coastal region. The GSPC wanted all these to be cleared together but the EAC ruled against it, asking the GSPC to make separate applications.
The EAC wanted the GSPC to submit: (1) details of the critical environmental issues identified during laying of pipeline, (2) environment clearance for enhancement of captive power plant, under consideration of environmental appraisal committee (EAC) of the thermal committee, which has also sought examining the requirement of wildlife clearance in view of Coringa Sanctuary located in 2.5 km distance, and (3) the plan of the pipeline to pass through the mangroves. Based on these observations, it recommended to defer the proposal.

Comments

TRENDING

Academics urge Azim Premji University to drop FIR against Student Reading Circle

  By A Representative   A group of academics and civil society members has issued an open letter to the leadership of Azim Premji University expressing concern over the filing of a police complaint that led to an FIR against a student-run reading circle following a recent incident of violence on campus. The signatories state that they hold the university in high regard for its commitment to constitutional values, critical inquiry and ethical public engagement, and argue that it is precisely because of this reputation that the present development is troubling.

Was Netaji forced to alter face, die in obscurity in USSR in 1975? Was he so meek?

  By Rajiv Shah   This should sound almost hilarious. Not only did Subhas Chandra Bose not die in a plane crash in Taipei, nor was he the mysterious Gumnami Baba who reportedly passed away on 16 September 1985 in Ayodhya, but we are now told that he actually died in 1975—date unknown—“in oblivion” somewhere in the former Soviet Union. Which city? Moscow? No one seems to know.

UAPA action against Telangana activist: Criminalising legitimate democratic activity?

By A Representative   The National Investigation Agency's Hyderabad branch has issued notices to more than ten individuals in Telangana in connection with FIR No. RC-04/2025. Those served include activists, former student leaders, civil rights advocates, poets, writers, retired schoolteachers, and local leaders associated with the Communist Party of India (CPI) and the Indian National Congress. 

Asbestos contamination in children’s products highlights global oversight gaps

By A Representative   A commentary published by the International Ban Asbestos Secretariat (IBAS) has drawn attention to the challenges governments face in responding effectively to global public-health risks. In an article written by Laurie Kazan-Allen and published on March 5, 2026, the author examines how the discovery of asbestos contamination in children’s play products has raised questions about regulatory oversight and international product safety. The article opens by reflecting on lessons from the COVID-19 pandemic, noting that governments in several countries were slow to respond to early warning signs of the crisis. Referring to the experience of the United Kingdom, the author writes that delays in implementing protective measures contributed to “232,112 recorded deaths and over a million people suffering from long Covid.” The commentary uses this example to illustrate what it describes as the dangers of underestimating emerging threats. Attention then turns...

Aligning too closely with U.S., allies, India’s silence on IRIS Dena raises troubling questions

By Vidya Bhushan Rawat*  The reported sinking of the Iranian ship IRIS Dena in the Indian Ocean near Sri Lanka raises troubling questions about international norms and the credibility of the so-called rule-based order. If indeed the vessel was attacked by the American Navy while returning from a joint exercise in Visakhapatnam, it would represent a serious breach of trust and a violation of the principles that govern such cooperative engagements. Warships participating in these exercises are generally not armed for combat; they are meant to symbolize solidarity and friendship. The incident, therefore, is not only shocking but also deeply ironic.

The kitchen as prison: A feminist elegy for domestic slavery

By Garima Srivastava* Kumar Ambuj stands as one of the most incisive voices in contemporary Hindi poetry. His work, stripped of ornamentation, speaks directly to the lived realities of India’s marginalized—women, the rural poor, and those crushed under invisible forms of violence. His celebrated poem “Women Who Cook” (Khānā Banātī Striyāṃ) is not merely about food preparation; it is a searing indictment of patriarchal domestic structures that reduce women’s existence to endless, unpaid labour.

India’s foreign policy at crossroads: Cost of silence in the face of aggression

By Venkatesh Narayanan, Sandeep Pandey  The widely anticipated yet unprovoked attack on Iran on March 1 by the United States and Israel has drawn sharp criticism from several quarters around the world. Reports indicate that the strikes have resulted in significant civilian casualties, including 165 elementary school girls, 20 female volleyball players, and many other civilians. 

India’s green energy push faces talent crunch amidst record growth at 16% CAGR

By Jag Jivan*  A new study by a top consulting firm has found that India’s cleantech sector is entering a decisive growth phase, with strong policy backing, record capacity additions and surging investor interest, but facing mounting pressure on talent supply and rising compensation costs .

Buddhist shrines were 'massively destroyed' by Brahmanical rulers: Historian DN Jha

Nalanda mahavihara By Rajiv Shah  Prominent historian DN Jha, an expert in India's ancient and medieval past, in his new book , "Against the Grain: Notes on Identity, Intolerance and History", in a sharp critique of "Hindutva ideologues", who look at the ancient period of Indian history as "a golden age marked by social harmony, devoid of any religious violence", has said, "Demolition and desecration of rival religious establishments, and the appropriation of their idols, was not uncommon in India before the advent of Islam".