People of Bundelkhand certainly need better water access and management as claimed in the Media Briefing Note on the occasion of Union Cabinet clearing the project on Dec 8, 2021. But the Ken Betwa Link Project (KBLP) is not for Bundelkhand, of Bundelkhand or by Bundelkhand. The project will bring unbelievably huge adverse impacts for the Bundelkhand and promises benefits that were promised decades ago, but never realised. In fact much better, cheaper, less impactful and faster options for Bundelkhand exist, if only the government had the will.
Law of the land says that before taking up a project for implementation, it must have all the required clearances including Forest Clearance, Wildlife clearance and any pending legal challenges are resolved. In case of KBLP, it does not final forest clearance, very fundamental questions have been raised about its Wildlife Clearance by the Central Empowered Committee (CEC) of the Supreme Court and SC has yet to take a decision on it, a legal challenge to the Environment Clearance (EC) is pending before the National Green Tribunal. If law of the land is to prevail, the cabinet should not have cleared the project. But a decision was taken purely on political consideration of gaining some electoral benefit in the upcoming Uttar Pradesh assembly elections, the BJP government’s cabinet decided to clear the disastrous project.
The cabinet decision raises the proprietary question, if the cabinet should be endorsing a project that does not have all the statutory clearances and legal challenge to its available clearances is pending before the various judicial bodies? What signal is the Prime Minister & the cabinet sending, what kind of pressures does this endorsement brings on the statutory and judicial decision makers?
In a most path breaking, remarkable report submitted to the Supreme Court on the KBLP on Aug 30, 2019, the CEC has raised fundamental questions not only on the appropriateness of the Wildlife Clearance given to the project, but also the viability, optimality and desirability of the project. It said the project will lead to “the loss of 10500 ha of wildlife habitat in PTR”, in addition to submergence of 9000 ha of the Panna Tiger Reserve (PTR).
The Detailed Project Report of KBLP prepared by the project proponent National Water Development Agency (NWDA) says: “The main objective of the Ken-Betwa link project is to make available water to water deficit areas of upper Betwa basin… ” That upper Betwa region is outside the Bundelkhand & has higher rainfall than Bundelkhand. Most areas of Bundelkhand that are now promised water from KBLP are either already getting water from other existing projects or were made similar promises decades back, the promises remain unrealised. Both the Forest Advisory Committee (FAC) and CEC conclude that the NWDA has not examined the alternatives to the project.
As the then Panna Collector wrote, Panna district, one of the least irrigated areas of Madhya Pradesh, will suffer maximum destruction, while getting very little benefit. Downstream Banda district of UP will suffer such huge impacts that at one stage Principle Secretary of UP wrote in an affidavit before the Supreme Court that the project will bring social unrest in the state!
The project is based on the premise that Ken, the smaller of the two rivers, has surplus water that can be transferred to bigger Betwa river. But the hydrological data that is claimed to support that premise is not in public domain, has never been put to scrutiny by any independent credible agency. Ground realities and available facts show that the hydrological basis of the project is a secret exercise in manipulation.
The CEC report raises the question about the current and future water needs of the Upper Ken basin, which has clearly been ignored. The project is likely to keep this mostly tribal area permanently backward. Ken Basin and Bundelkhand are asked to pay that price for past blunders of irrigation engineers in Betwa basin, as CEC report says: “This faulty planning in development of irrigation facilities in lower Betwa basin at the cost of Upper Betwa basin is proposed to be now rectified by substitution of water from Ken basin.”
In this context the FAC made a very important suggestion that has never been implemented: “It is suggested that a team of independent experts on surface water hydrology, drawn from leading scientific institutions, should have been requested to examine the hydrological aspects of the Ken Betwa river link”. Why is the government afraid of such an independent scrutiny of hydrological foundation of such a expensive and impactful project? Clearly it has a lot to hide.
The CEC report also shows that the KBLP will have much larger impact on PTR than assessed as the East West corridor of movement within PTR will no longer be available.
The CEC has concluded that the Standing Committee of National Board of Wildlife has not examined the “Impact of the project on the downstream Gharial Sanctuary and the vulture nesting sites”, “not given due consideration to the critical observations of the Committee of SC NBWL” and “not taken into account the decision of this Hon’ble court in lA No. 100 in WP (C) No. 33 of 1995 with lA No. 3452 wherein it is held that our approach should be eco centric and not anthropocentric”.
The discourse in the CEC report about the impacts of the KBLP is at an entirely different level compared to the most shameful, shoddy Environment Impact Assessment (EIA) of the project, based on which the project has been given environment clearance (EC) in Aug 2017. A number of official agencies, including the Forest Advisory Committee has noted the factual errors and inadequacies in the EIA-EMP.
The recommendation of the EC for the project by the Expert Appraisal Committee (EAC) of the MoEF in Dec 2016 itself was a huge exercise in manipulation. The EAC for River Valley Projects in its five earlier meetings till Aug 2016 where this project was discussed raised a number of questions. In fact, the then Union Water Resources Minister Ms Uma Bharti publicly threatened the EAC of dharna if the project is not cleared. Finally, MoEF reconstituted the EAC, the reconstituted EAC in its very first meeting, cleared the KBLP without resolving any of the issues raised in the earlier EAC meetings.
The stage I forest clearance accorded to the project on May 27, 2017 is based on a number of conditions that will require fundamental restructuring of the project. The changes required statutorily will affect the project costs, benefits and impacts and hence will require fresh appraisal. Such conditions include the stipulation that the proposed 78 MW power house shall not be constructed in the forest area; in lean season, the entire inflow to the proposed reservoir will be released for the downstream river and flow in the downstream river will be maintained throughout the year till Ken river reaches Yamuna river; no building material is to be taken from the forest area, implementation of the CEC recommendations, among others.
The minutes of the final Forest Advisory Committee meeting held on March 30, 2017 make a disturbing reading, it notes: “The construction of dam in site within Panna Tiger Reserve is not the best possible option for development of water resources in the drought prone area of Bundelkhand keeping in view the pristine forests of the PTR and its rich biodiversity… the total project cost has not included the cost of ecosystem services lost due to the diversion of forest… If the cost of ecosystem services lost is considered than the Benefit/Cost ratio will be very less making the project economically unviable.”
The Conclusion of the FAC is stark: “In an ideal situation, it would have been better to avoid KBLCP in such wilderness areas such as PTR specifically when it runs the risk of providing justification or unhealthy precedence for more such developmental projects within protected areas. Certainly it will not be in the interest of wildlife and the overall well-being of the society in the long-term.” What were the compulsions for the Prime Minister and Cabinet to clear a disastrous project like that, as noted by FAC, no less?
In fact, there has been so much opposition, manipulations and compromised decision making at every step of the project, there is no place for all that in this article. Let us end with what the then secretary in Union Water Resources Ministry told me in a meeting across the table. When asked why is the government pushing a project that will bring so much destruction to Bundelkhand rather than solving its problems, his answer was, to para phrase considering current costs: “It’s a Rs 45 000 Crore proposition”.

*With South Asia Network on Dams, Rivers and People. Source: https://sandrp.in/

Comments

TRENDING

Swami Vivekananda's views on caste and sexuality were 'painfully' regressive

By Bhaskar Sur* Swami Vivekananda now belongs more to the modern Hindu mythology than reality. It makes a daunting job to discover the real human being who knew unemployment, humiliation of losing a teaching job for 'incompetence', longed in vain for the bliss of a happy conjugal life only to suffer the consequent frustration.

Jayanthi Natarajan "never stood by tribals' rights" in MNC Vedanta's move to mine Niyamigiri Hills in Odisha

By A Representative The Odisha Chapter of the Campaign for Survival and Dignity (CSD), which played a vital role in the struggle for the enactment of historic Forest Rights Act, 2006 has blamed former Union environment minister Jaynaynthi Natarjan for failing to play any vital role to defend the tribals' rights in the forest areas during her tenure under the former UPA government. Countering her recent statement that she rejected environmental clearance to Vendanta, the top UK-based NMC, despite tremendous pressure from her colleagues in Cabinet and huge criticism from industry, and the claim that her decision was “upheld by the Supreme Court”, the CSD said this is simply not true, and actually she "disrespected" FRA.

Stands 'exposed': Cavalier attitude towards rushed construction of Char Dham project

By Bharat Dogra*  The nation heaved a big sigh of relief when the 41 workers trapped in the under-construction Silkyara-Barkot tunnel (Uttarkashi district of Uttarakhand) were finally rescued on November 28 after a 17-day rescue effort. All those involved in the rescue effort deserve a big thanks of the entire country. The government deserves appreciation for providing all-round support.

Urgent need to study cause of large number of natural deaths in Gulf countries

By Venkatesh Nayak* According to data tabled in Parliament in April 2018, there are 87.76 lakh (8.77 million) Indians in six Gulf countries, namely Bahrain, Kuwait, Oman, Qatar, Saudi Arabia and the United Arab Emirates (UAE). While replying to an Unstarred Question (#6091) raised in the Lok Sabha, the Union Minister of State for External Affairs said, during the first half of this financial year alone (between April-September 2018), blue-collared Indian workers in these countries had remitted USD 33.47 Billion back home. Not much is known about the human cost of such earnings which swell up the country’s forex reserves quietly. My recent RTI intervention and research of proceedings in Parliament has revealed that between 2012 and mid-2018 more than 24,570 Indian Workers died in these Gulf countries. This works out to an average of more than 10 deaths per day. For every US$ 1 Billion they remitted to India during the same period there were at least 117 deaths of Indian Workers in Gulf ...

Uttarakhand tunnel disaster: 'Question mark' on rescue plan, appraisal, construction

By Bhim Singh Rawat*  As many as 40 workers were trapped inside Barkot-Silkyara tunnel in Uttarkashi after a portion of the 4.5 km long, supposedly completed portion of the tunnel, collapsed early morning on Sunday, Nov 12, 2023. The incident has once again raised several questions over negligence in planning, appraisal and construction, absence of emergency rescue plan, violations of labour laws and environmental norms resulting in this avoidable accident.

Celebrating 125 yr old legacy of healthcare work of missionaries

Vilas Shende, director, Mure Memorial Hospital By Moin Qazi* Central India has been one of the most fertile belts for several unique experiments undertaken by missionaries in the field of education and healthcare. The result is a network of several well-known schools, colleges and hospitals that have woven themselves into the social landscape of the region. They have also become a byword for quality and affordable services delivered to all sections of the society. These institutions are characterised by committed and compassionate staff driven by the selfless pursuit of improving the well-being of society. This is the reason why the region has nursed and nurtured so many eminent people who occupy high positions in varied fields across the country as well as beyond. One of the fruits of this legacy is a more than century old iconic hospital that nestles in the heart of Nagpur city. Named as Mure Memorial Hospital after a British warrior who lost his life in a war while defending his cou...

New RTI draft rules inspired by citizen-unfriendly, overtly bureaucratic approach

By Venkatesh Nayak* The Department of Personnel and Training , Government of India has invited comments on a new set of Draft Rules (available in English only) to implement The Right to Information Act, 2005 . The RTI Rules were last amended in 2012 after a long period of consultation with various stakeholders. The Government’s move to put the draft RTI Rules out for people’s comments and suggestions for change is a welcome continuation of the tradition of public consultation. Positive aspects of the Draft RTI Rules While 60-65% of the Draft RTI Rules repeat the content of the 2012 RTI Rules, some new aspects deserve appreciation as they clarify the manner of implementation of key provisions of the RTI Act. These are: Provisions for dealing with non-compliance of the orders and directives of the Central Information Commission (CIC) by public authorities- this was missing in the 2012 RTI Rules. Non-compliance is increasingly becoming a major problem- two of my non-compliance cases are...

Pairing not with law but with perpetrators: Pavlovian response to lynchings in India

By Vikash Narain Rai* Lynch-law owes its name to James Lynch, the legendary Warden of Galway, Ireland, who tried, condemned and executed his own son in 1493 for defrauding and killing strangers. But, today, what kind of a person will justify the lynching for any reason whatsoever? Will perhaps resemble the proverbial ‘wrong man to meet at wrong road at night!’

Dowry over duty: How material greed shattered a seven-year bond

By Archana Kumar*  This account does not seek to expose names or tarnish identities. Its purpose is not to cast blame, but to articulate—with dignity—the silent suffering of a woman who lived her life anchored in love, trust, and duty, only to be ultimately abandoned.