Bullet train: Just one hectare acquired out of 1,400 ha required for the massive project

By Mahesh Trivedi*
Prime Minister Narendra Modi has been shouting from rooftops that the 750-seat, 10-coach, 350-km-an hour train linking India’s financial capital Mumbai with Ahmedabad, the largest city of his home state of Gujarat, will cover the 508-km elevated rail line in two hours flat even after halting at 12 stations and will benefit well-heeled textile traders, diamond merchants and other professionals shuttling between the two metros.
However, more than a year after it was rolled off, India’s Rs 1.1-trillion ambitious high-speed bullet train project is chugging along at a snail’s pace, with shortage of funds and farmers’ protests now threatening to derail the country’s first cannonball express.
The Japan International Cooperation Agency (JICA), which vowed to bankroll 80% – about Rs 880 billion – of the total cost has so far shelled out the first instalment of only Rs 55 billion, even as Prime Minister Narendra Modi returned from the Land of the Rising Sun on October 29 after a desperate attempt to ensure the second tranche of the 50-year, 0.1% interest soft loan.
Neither the Union Ministry of Railways nor the governments of the two neighboring states controlled by BJP have coughed up a single rupee for his 24-train dream project under which 18 low-noise, aerodynamically-designed trains based on the Shinkansen technology will be imported from Japan while he wants the remaining six trains manufactured under the Make-in-India program.
No wonder, though railway officials are sweating and slaving to complete the project before the 2023 deadline, they now feel that only a 200-km stretch would be made operational by then to keep the promise made to the people.
To add to their woes, Modi, in a bid to make political capital out of the faster and more comfortable high-tech train ahead of the crucial 2019 general elections, advanced the launch date by a year to have it coincide with 75 years of Indian independence on August 15, 2022, saying the crackerjack Indian engineers will pick up the gauntlet.

Farmers protest

Meanwhile, 8,000-odd angry farmers and landowners affected by the project have put a spoke in the wheel of the train by refusing to sell their land, demanding a better compensation and complaining about human rights violation and environmental damage, and are bent on soon presenting their gravamina before JICA officials.
After all, the bullet train will pass through 1,400 hectares of land in 312 villages of Gujarat and Maharashtra, take over 866 hectares of fertile farmland, dissect multiple reserved forests, and cut down some 86,000 trees.
Not surprisingly, about 1,200 sons of the soil have submitted affidavits in the Gujarat High Court saying they do not intend to part with their land for the project. Not long ago, ryots from Surat, Valsad and Navsari districts in Gujarat filed 40 more petitions in the same court challenging the process of land acquisition.
What’s more, irate tribals, farmers and fishermen living in hamlets around Maharashtra’s Palghar town near Mumbai on October 28 held out a threat that officials attempting to enter their villages would be tied to trees, sending shivers down the spine of bureaucrats. The result is that the authorities have been able to acquire hardly one hectare of the 1,400 hectares required for the massive project.
While many say that the high-end train will be out of the reach of the masses and will isolate the middle class and poor sections of society, others pointed out that by snatching away prime fertile land, the Modi regime is compromising on the country’s food security.
Senior Congress leader Arjun Modhwadia told this reporter that instead of squandering Rs 1.1 trillion for providing comfort to 4,500 rich commuters, the government should invest the funds for offering better services to the 9,000 million ordinary passengers who travelled by trains every year, adding that evolving technology would cut travel time and obviate the need for acquiring new land.
“The Indian Railways are doing well by speeding up 400 trains in the last four years and converting 120 trains to superfast expresses. So, a bullet train is a wrong priority and a poor country like India does not need one,” he asserted.
Indeed, the growth in domestic air traffic, decrease in jet fuel and improvement in technology have already brought air fares down and the fares for a Mumbai-Ahmedabad flight may go down to below to Rs 3,000, which will be lower than or on a par with the proposed price of Rs 3,000 for the bullet train.
Radheshyam Goswami, a senior journalist and former member of a railway users’ consultative committee, opined that the bullet train was a total waste of money, arguing that by 2023 when the so-called supersonic train would be operational, people would prefer to travel by airplanes with less time and money.
In sum, the National Transport Development Policy Committee had recommended a semi-high speed rail (160-200 kmph) till the time the high-speed rail projects are found commercially justified, and scholars of Indian Institute of Management-Ahmedabad had concluded that 100 daily trips at full occupancy would be required with a fare of Rs 5,000 between Ahmedabad and Mumbai to make the bullet train financially viable.
But an arrogant Modi wanting to talk about the project till he hits the campaign trail next year has decided to wink at these two important suggestions.
---
*Senior Ahmedabad-based journalist. A version of this article first appeared here

Comments

TRENDING

Swami Vivekananda's views on caste and sexuality were 'painfully' regressive

By Bhaskar Sur* Swami Vivekananda now belongs more to the modern Hindu mythology than reality. It makes a daunting job to discover the real human being who knew unemployment, humiliation of losing a teaching job for 'incompetence', longed in vain for the bliss of a happy conjugal life only to suffer the consequent frustration.

Jayanthi Natarajan "never stood by tribals' rights" in MNC Vedanta's move to mine Niyamigiri Hills in Odisha

By A Representative The Odisha Chapter of the Campaign for Survival and Dignity (CSD), which played a vital role in the struggle for the enactment of historic Forest Rights Act, 2006 has blamed former Union environment minister Jaynaynthi Natarjan for failing to play any vital role to defend the tribals' rights in the forest areas during her tenure under the former UPA government. Countering her recent statement that she rejected environmental clearance to Vendanta, the top UK-based NMC, despite tremendous pressure from her colleagues in Cabinet and huge criticism from industry, and the claim that her decision was “upheld by the Supreme Court”, the CSD said this is simply not true, and actually she "disrespected" FRA.

Urgent need to study cause of large number of natural deaths in Gulf countries

By Venkatesh Nayak* According to data tabled in Parliament in April 2018, there are 87.76 lakh (8.77 million) Indians in six Gulf countries, namely Bahrain, Kuwait, Oman, Qatar, Saudi Arabia and the United Arab Emirates (UAE). While replying to an Unstarred Question (#6091) raised in the Lok Sabha, the Union Minister of State for External Affairs said, during the first half of this financial year alone (between April-September 2018), blue-collared Indian workers in these countries had remitted USD 33.47 Billion back home. Not much is known about the human cost of such earnings which swell up the country’s forex reserves quietly. My recent RTI intervention and research of proceedings in Parliament has revealed that between 2012 and mid-2018 more than 24,570 Indian Workers died in these Gulf countries. This works out to an average of more than 10 deaths per day. For every US$ 1 Billion they remitted to India during the same period there were at least 117 deaths of Indian Workers in Gulf ...

Stands 'exposed': Cavalier attitude towards rushed construction of Char Dham project

By Bharat Dogra*  The nation heaved a big sigh of relief when the 41 workers trapped in the under-construction Silkyara-Barkot tunnel (Uttarkashi district of Uttarakhand) were finally rescued on November 28 after a 17-day rescue effort. All those involved in the rescue effort deserve a big thanks of the entire country. The government deserves appreciation for providing all-round support.

Uttarakhand tunnel disaster: 'Question mark' on rescue plan, appraisal, construction

By Bhim Singh Rawat*  As many as 40 workers were trapped inside Barkot-Silkyara tunnel in Uttarkashi after a portion of the 4.5 km long, supposedly completed portion of the tunnel, collapsed early morning on Sunday, Nov 12, 2023. The incident has once again raised several questions over negligence in planning, appraisal and construction, absence of emergency rescue plan, violations of labour laws and environmental norms resulting in this avoidable accident.

Celebrating 125 yr old legacy of healthcare work of missionaries

Vilas Shende, director, Mure Memorial Hospital By Moin Qazi* Central India has been one of the most fertile belts for several unique experiments undertaken by missionaries in the field of education and healthcare. The result is a network of several well-known schools, colleges and hospitals that have woven themselves into the social landscape of the region. They have also become a byword for quality and affordable services delivered to all sections of the society. These institutions are characterised by committed and compassionate staff driven by the selfless pursuit of improving the well-being of society. This is the reason why the region has nursed and nurtured so many eminent people who occupy high positions in varied fields across the country as well as beyond. One of the fruits of this legacy is a more than century old iconic hospital that nestles in the heart of Nagpur city. Named as Mure Memorial Hospital after a British warrior who lost his life in a war while defending his cou...

New RTI draft rules inspired by citizen-unfriendly, overtly bureaucratic approach

By Venkatesh Nayak* The Department of Personnel and Training , Government of India has invited comments on a new set of Draft Rules (available in English only) to implement The Right to Information Act, 2005 . The RTI Rules were last amended in 2012 after a long period of consultation with various stakeholders. The Government’s move to put the draft RTI Rules out for people’s comments and suggestions for change is a welcome continuation of the tradition of public consultation. Positive aspects of the Draft RTI Rules While 60-65% of the Draft RTI Rules repeat the content of the 2012 RTI Rules, some new aspects deserve appreciation as they clarify the manner of implementation of key provisions of the RTI Act. These are: Provisions for dealing with non-compliance of the orders and directives of the Central Information Commission (CIC) by public authorities- this was missing in the 2012 RTI Rules. Non-compliance is increasingly becoming a major problem- two of my non-compliance cases are...

Dowry over duty: How material greed shattered a seven-year bond

By Archana Kumar*  This account does not seek to expose names or tarnish identities. Its purpose is not to cast blame, but to articulate—with dignity—the silent suffering of a woman who lived her life anchored in love, trust, and duty, only to be ultimately abandoned.

Pairing not with law but with perpetrators: Pavlovian response to lynchings in India

By Vikash Narain Rai* Lynch-law owes its name to James Lynch, the legendary Warden of Galway, Ireland, who tried, condemned and executed his own son in 1493 for defrauding and killing strangers. But, today, what kind of a person will justify the lynching for any reason whatsoever? Will perhaps resemble the proverbial ‘wrong man to meet at wrong road at night!’