Skip to main content

Gas 'dreams': Failure to get eco-clearance for submarine pipeline costs Gujarat PSU another Rs 760 crore

By A Representative
Failure to get forest and environmental clearance for laying down Rs 826 crore submarine pipeline to tap the gas found off Andhra Pradesh coast has cost former bluechip public sector undertaking (PSU), Gujarat State Petroleum Corporation (GSPC), dear. Latest information available from an internal note has suggested that the GSPC will have to shell out a total of around another US dollars 123.66 million as “standby” or “idle” charges to Punj Lloyd Ltd (PLL), the top multinational contractors who were hired in an international bid, to lay down the submarine pipeline in 2011.
The note, which is in possession of Counterview, said that the total amount would have to be paid “expeditiously”, as the contractors are unable to continue their work because of the failure of the GSPC to get necessary clearances on time, as required by the terms of agreement. “PLL has already submitted communication indicating their standby claim. Early resolution of the issue is necessary to preempt any further claims on account of standby”, the note, put up before a recent board meeting of the GSPC, said. Sources added, failure to get necessary clearances has delayed the completion of the project -- scheduled to end in April 2013 -- by at least a year.
Already, the note says, the GSPC has paid PLL an amount of 71.25 million dollars (or Rs 440 crore). However, insiders said, as the money was disbursed without approval of the GSPC board, there was considerable commotion in the Gujarat bureaucratic circles. “Hence, GSPC managing director Tapan Ray decided to approach the GSPC board for getting an approval for the rest of the amount, which comes to around Rs 44.41 million dollars. The board, which met recently, was “undecided” on the matter, and asked a committee under retired IAS bureaucrat MM Shrivastav to look into the matter and decide on the matter.
The note asks the GSPC board to pay up at least 15 million dollars of the amount still a final decision is made. It says, it should be an “interim measure” till the “final settlement is arrived at”. In the meanwhile, the necessary clearances would be taken. Arguing in favour of the payment, the note said, payment to the contracts is “necessary” because 72 per cent of the work in tapping gas from the Deendayal (West) field off Andhra coast is already over, and gas’ commercial production is pending completion of the submarine project. It has expressed the apprehension, at stake is 2.2 billion dollars investment in tapping gas.
Arguing that the “submarine pipeline is the only interconnection” between the GSPC’s Deendayal fields and the onshore facilities, which would refine the gas and send them into the national grid, the note say, “rescinding the contract at this stage” would imply a new tender would have “delay” the commercial production by another 9-12 months to float. “Nature of the work calls for international competitive bidding”, it points out, adding, there always apprehension that “sufficient offers may not come”. Further, it adds, “dispute resolution with PLL” may prove to be “messy, time consuming and costly.”
The GSPC also expresses the apprehension that the overall cost of maintaining the infrastructure set up by the GSPC for commercial production of gas may go up drastically to 300 million dollars per annum. This includes the “additional burden of fixed cost of already installed capacities, interest payment on borrowed capital, operation and maintenance cost” and so on. On the other hand, “assistance to PLL to mobilize resources would facilitate completion of pipeline project by March 2014.”
The GSPC's Rs 760 crore blow came close on the heels of its formal decision to withdraw from its most important overseas adventure – Egypt. The decision was taken as it was proving to be a very costly affair. Deeply under debt of Rs 8,000 crore, the exploration in Egypt would have cost the GSPC another Rs 5,000, with no surety about possibility of getting gas or oil. It was the first major step to bring out GSPC from the financial mess it is in right now.
Interestingly, the GSPC not just failed to get environmental and coastal regulatory zone (CRZ) clearance for the submarine pipeline but also its onshore gas terminal, a 20 MW captive power plant, 20 underground gas pipelines along with optical fibre cable (OFC), and 10 inches effluent disposal pipeline -- of which it badly needed for commercial production of the gas it struck several years ago. Some of these facilities were to pass through CRZ area of Yanam-Puducherry along the Andhra Pradesh coast. 
It simultaneously failed to get clearance for its offshore process-cum-living quarter platform in at the Deendayal block in the KG Basin in Andhra sea, where the top PSU had claimed in 2005 to have found 20 trillion cubic metres (tcf) of gas -- a claim which has been quashed, as total gas available is just 2 tcf, of which one third is recoverable.
In May last year, the environmental appraisal committee (EAC) had asked the GSPC to “defer” construction commercial facilities until certain conditions were fulfilled. It refused to give blanket CRZ clearance for laying down underground gas pipeline, optical fibre cable (OFC), an effluent disposal pipeline, and process-cum-living quarter platform and captive power plant – all of which would require he CRZ clearance, as these facilities are to be part of the Yanam-Puducherry coastal region. The GSPC wanted all these to be cleared together but the EAC ruled against it, asking the GSPC to make separate applications.
The EAC wanted the GSPC to submit: (1) details of the critical environmental issues identified during laying of pipeline, (2) environment clearance for enhancement of captive power plant, under consideration of environmental appraisal committee (EAC) of the thermal committee, which has also sought examining the requirement of wildlife clearance in view of Coringa Sanctuary located in 2.5 km distance, and (3) the plan of the pipeline to pass through the mangroves. Based on these observations, it recommended to defer the proposal.

Comments

TRENDING

When democracy becomes a performance: The Tibetan exile experience

By Tseten Lhundup*  I was born in Bylakuppe, one of the largest Tibetan settlements in southern India. From childhood, I grew up in simple barracks, along muddy roads, and in fields with limited resources. Over the years, I have watched our democratic system slowly erode. Observing the recent budget session of the 17th Tibetan Parliament-in-Exile, these “democratic procedures” appear grand and orderly on the surface, yet in reality they amount to little more than empty formalities. The parliamentarians seem largely disconnected from the everyday struggles faced by ordinary exiled Tibetans like us.

Study links sanctions to 500,000 deaths annually leading to rise in global backlash

By Bharat Dogra  International opinion is increasingly turning against the expanding burden of sanctions imposed on a growing number of countries. These measures are contributing to humanitarian crises, intensifying domestic discord, and heightening international tensions, thereby increasing the risks of conflicts and wars. 

Dhurandhar: The Revenge — Blurring the line between fiction and political narrative

By Mohd. Ziyaullah Khan*  "Dhurandhar: The Revenge" does not wait to be remembered; it arrives almost on the heels of its predecessor, released on March 19, 2026, just months after the first film’s December 2025 debut. The speed of its arrival feels less like creative urgency and more like calculated timing—cinema responding not to storytelling rhythm but to the emotional climate of its audience. Director Aditya Dhar, along with actor Yami Gautam, appears acutely aware of this moment and how to harness it.

Beyond the island: Top mythologist reorients the geography of the Ramayana

By Jag Jivan   In a compelling new analysis that challenges conventional geographical assumptions about the ancient epic, writer and mythologist Devdutt Pattanaik has traced the roots of the Ramayana to the forests and river systems of Central and Eastern India, rather than the peninsular south or the modern island nation of Sri Lanka.

BJP accounts for 99% of political donations in Gujarat: Corporate giants dominate

By Jag Jivan   An analysis of the official data on donations received by national parties from Gujarat during the Financial Year 2024-25 reveals a staggering concentration of funding, with the Bharatiya Janata Party (BJP) accounting for nearly the entirety of the contributions. The data, compiled in a document titled "National Parties donations received from Gujarat during FY-2024-25," lists thousands of transactions, painting a detailed picture of the financial backing for political parties from one of India’s most industrially significant states.

Alarming decline in India's repair culture threatens circular economy goals: Study

By Jag Jivan  A comprehensive new study by environmental research and advocacy organisation Toxics Link has painted a worrying picture of India's fading repair culture, warning that the trend towards replacement over repair is accelerating the country's already critical e-waste crisis.

Captains extraordinaire: Ranking cricket’s most influential skippers

By Harsh Thakor*  Ranking the greatest cricket captains is a subjective exercise, often sparking passionate debate among fans. The following list is not merely a tally of wins and losses; it is an assessment of leadership’s deeper impact. My criteria fuse a captain’s playing record with their tactical skill, placing the highest consideration on their ability to reshape a team’s fortunes and inspire those around them. A captain who inherited a dominant empire is judged differently from one who resurrected a nation’s cricket from the doldrums. With that in mind, here is my perspective on the finest leaders the game has ever seen.

Swami Vivekananda's views on caste and sexuality were 'painfully' regressive

By Bhaskar Sur* Swami Vivekananda now belongs more to the modern Hindu mythology than reality. It makes a daunting job to discover the real human being who knew unemployment, humiliation of losing a teaching job for 'incompetence', longed in vain for the bliss of a happy conjugal life only to suffer the consequent frustration.

‘No merit’ in Chakraborty’s claims: Personal ethics talk sans details raises questions

By Jag Jivan  A recent opinion piece published in The Quint by Subhash Chandra Garg has raised questions over the circumstances surrounding the resignation of Atanu Chakraborty from HDFC Bank , with Garg stating that the exit “raises doubts about his own ‘ethics’.” Garg, currently Chief Policy Advisor at Subhanjali and former Secretary of the Department of Economic Affairs, Government of India, writes that the Reserve Bank of India ( RBI ) appears to find no substance in Chakraborty’s claims, noting, “It is clear the RBI sees no merit in Atanu Chakraborty’s wild and vague assertions.”